Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in S0 Structural / Misc. Steel × clear
Code
Activity
Start
Finish
Flt
%
CO01YS0110
01Y Erect Structural Steel - Pipe Rack
06-Mar-27
30-Apr-27
39.0d
0%
WO010S0100
010 Erect Steel
06-Mar-27
11-Jun-27
94.0d
0%
CO01BS0120
01B Erect Misc Steel
03-Apr-27
30-Apr-27
86.0d
0%
CO01YS0120
01Y Erect Misc Steel - Pipe Rack
24-Apr-27
21-May-27
39.0d
0%
CO01DS0120
01D Erect Misc Steel
05-May-27
01-Jun-27
61.0d
0%
CO01CS0120
01C Erect Misc Steel
15-May-27
28-May-27
106.0d
0%
CO01HS0110
01H Erect Structural Steel - Stairs & Platform
15-May-27
11-Jun-27
51.0d
0%
Q1 2027 Q2 2027 Data Date
CO01YS0110 — 01Y Erect Structural Steel - Pipe Rack | 06-Mar-27 → 30-Apr-27 | Not Started 0% | float 39.0d CO01YS0110 WO010S0100 — 010 Erect Steel | 06-Mar-27 → 11-Jun-27 | Not Started 0% | float 94.0d WO010S0100 CO01BS0120 — 01B Erect Misc Steel | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 86.0d CO01YS0120 — 01Y Erect Misc Steel - Pipe Rack | 24-Apr-27 → 21-May-27 | Not Started 0% | float 39.0d CO01DS0120 — 01D Erect Misc Steel | 05-May-27 → 01-Jun-27 | Not Started 0% | float 61.0d CO01CS0120 — 01C Erect Misc Steel | 15-May-27 → 28-May-27 | Not Started 0% | float 106.0d CO01HS0110 — 01H Erect Structural Steel - Stairs & Platform | 15-May-27 → 11-Jun-27 | Not Started 0% | float 51.0d