Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in S0 Structural / Misc. Steel × clear
Code
Activity
Start
Finish
Flt
%
CO01YS0110
01Y Erect Structural Steel - Pipe Rack
06-Mar-27
30-Apr-27
39.0d
0%
WO010S0100
010 Erect Steel
06-Mar-27
11-Jun-27
94.0d
0%
CO01BS0120
01B Erect Misc Steel
03-Apr-27
30-Apr-27
86.0d
0%
CO01YS0120
01Y Erect Misc Steel - Pipe Rack
24-Apr-27
21-May-27
39.0d
0%
CO01DS0120
01D Erect Misc Steel
05-May-27
01-Jun-27
61.0d
0%
CO01CS0120
01C Erect Misc Steel
15-May-27
28-May-27
106.0d
0%
CO01HS0110
01H Erect Structural Steel - Stairs & Platform
15-May-27
11-Jun-27
51.0d
0%
01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun Data Date
CO01YS0110 — 01Y Erect Structural Steel - Pipe Rack | 06-Mar-27 → 30-Apr-27 | Not Started 0% | float 39.0d CO01YS0110 WO010S0100 — 010 Erect Steel | 06-Mar-27 → 11-Jun-27 | Not Started 0% | float 94.0d WO010S0100 CO01BS0120 — 01B Erect Misc Steel | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 86.0d CO01BS0120 CO01YS0120 — 01Y Erect Misc Steel - Pipe Rack | 24-Apr-27 → 21-May-27 | Not Started 0% | float 39.0d CO01YS0120 CO01DS0120 — 01D Erect Misc Steel | 05-May-27 → 01-Jun-27 | Not Started 0% | float 61.0d CO01DS0120 CO01CS0120 — 01C Erect Misc Steel | 15-May-27 → 28-May-27 | Not Started 0% | float 106.0d CO01CS0120 CO01HS0110 — 01H Erect Structural Steel - Stairs & Platform | 15-May-27 → 11-Jun-27 | Not Started 0% | float 51.0d CO01HS0110