Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 15 activities in P0 A/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO01YP0130
01Y LB Pipe Erection - Pipe Rack
01-May-27
25-Jun-27
39.0d
0%
WO010P0100
010 Above Ground Pipe
01-May-27
05-Oct-27
95.0d
0%
CO01YP0140
01Y SB Pipe Erection - Pipe Rack
29-May-27
23-Jul-27
39.0d
0%
CO01CP0130
01C LB Pipe Erection
07-Jun-27
28-Jun-27
93.0d
0%
CO01BP0130
01B LB Pipe Erection
12-Jun-27
21-Sep-27
32.0d
0%
CO01DP0130
01D LB Pipe Erection
12-Jun-27
13-Aug-27
34.0d
0%
CO01CP0140
01C SB Pipe Erection
14-Jun-27
05-Jul-27
93.0d
0%
CO01BP0140
01B SB Pipe Erection
19-Jun-27
28-Sep-27
32.0d
0%
CO01DP0140
01D SB Pipe Erection
19-Jun-27
27-Aug-27
34.0d
0%
CO01CP0150
01C Punchlist / Test Piping
01-Jul-27
12-Jul-27
96.0d
0%
CO01YP0150
01Y Punchlist / Test Piping - Pipe Rack
03-Jul-27
30-Jul-27
133.0d
0%
CO01DP0150
01D Punchlist / Test Piping
28-Jul-27
10-Sep-27
34.0d
0%
CO01BP0150
01B Punchlist / Test Piping
05-Aug-27
05-Oct-27
32.0d
0%
CO01AP0130
01A LB Pipe Erection
03-Sep-27
28-Sep-27
54.0d
0%
CO01AP0150
01A Punchlist / Test Piping
29-Sep-27
01-Oct-27
57.0d
0%
Q2 2027 Q3 2027 Q4 2027 Data Date
CO01YP0130 — 01Y LB Pipe Erection - Pipe Rack | 01-May-27 → 25-Jun-27 | Not Started 0% | float 39.0d CO01YP0130 WO010P0100 — 010 Above Ground Pipe | 01-May-27 → 05-Oct-27 | Not Started 0% | float 95.0d WO010P0100 CO01YP0140 — 01Y SB Pipe Erection - Pipe Rack | 29-May-27 → 23-Jul-27 | Not Started 0% | float 39.0d CO01YP0140 CO01CP0130 — 01C LB Pipe Erection | 07-Jun-27 → 28-Jun-27 | Not Started 0% | float 93.0d CO01BP0130 — 01B LB Pipe Erection | 12-Jun-27 → 21-Sep-27 | Not Started 0% | float 32.0d CO01BP0130 CO01DP0130 — 01D LB Pipe Erection | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 34.0d CO01DP0130 CO01CP0140 — 01C SB Pipe Erection | 14-Jun-27 → 05-Jul-27 | Not Started 0% | float 93.0d CO01BP0140 — 01B SB Pipe Erection | 19-Jun-27 → 28-Sep-27 | Not Started 0% | float 32.0d CO01BP0140 CO01DP0140 — 01D SB Pipe Erection | 19-Jun-27 → 27-Aug-27 | Not Started 0% | float 34.0d CO01DP0140 CO01CP0150 — 01C Punchlist / Test Piping | 01-Jul-27 → 12-Jul-27 | Not Started 0% | float 96.0d CO01YP0150 — 01Y Punchlist / Test Piping - Pipe Rack | 03-Jul-27 → 30-Jul-27 | Not Started 0% | float 133.0d CO01DP0150 — 01D Punchlist / Test Piping | 28-Jul-27 → 10-Sep-27 | Not Started 0% | float 34.0d CO01DP0150 CO01BP0150 — 01B Punchlist / Test Piping | 05-Aug-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BP0150 CO01AP0130 — 01A LB Pipe Erection | 03-Sep-27 → 28-Sep-27 | Not Started 0% | float 54.0d CO01AP0150 — 01A Punchlist / Test Piping | 29-Sep-27 → 01-Oct-27 | Not Started 0% | float 57.0d