EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 15
activities
in P0 A/G Piping
× clear
Code
Activity
Start
Finish
Flt
%
CO01YP0130
01Y LB Pipe Erection - Pipe Rack
01-May-27
25-Jun-27
39.0d
0%
WO010P0100
010 Above Ground Pipe
01-May-27
05-Oct-27
95.0d
0%
CO01YP0140
01Y SB Pipe Erection - Pipe Rack
29-May-27
23-Jul-27
39.0d
0%
CO01CP0130
01C LB Pipe Erection
07-Jun-27
28-Jun-27
93.0d
0%
CO01BP0130
01B LB Pipe Erection
12-Jun-27
21-Sep-27
32.0d
0%
CO01DP0130
01D LB Pipe Erection
12-Jun-27
13-Aug-27
34.0d
0%
CO01CP0140
01C SB Pipe Erection
14-Jun-27
05-Jul-27
93.0d
0%
CO01BP0140
01B SB Pipe Erection
19-Jun-27
28-Sep-27
32.0d
0%
CO01DP0140
01D SB Pipe Erection
19-Jun-27
27-Aug-27
34.0d
0%
CO01CP0150
01C Punchlist / Test Piping
01-Jul-27
12-Jul-27
96.0d
0%
CO01YP0150
01Y Punchlist / Test Piping - Pipe Rack
03-Jul-27
30-Jul-27
133.0d
0%
CO01DP0150
01D Punchlist / Test Piping
28-Jul-27
10-Sep-27
34.0d
0%
CO01BP0150
01B Punchlist / Test Piping
05-Aug-27
05-Oct-27
32.0d
0%
CO01AP0130
01A LB Pipe Erection
03-Sep-27
28-Sep-27
54.0d
0%
CO01AP0150
01A Punchlist / Test Piping
29-Sep-27
01-Oct-27
57.0d
0%