EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 10
activities
in M0 Mechanical Equipment
× clear
Code
Activity
Start
Finish
Flt
%
CO01DM0130
01D Erect 2101-U Cooling Tower
28-Dec-26
04-May-27
61.0d
0%
WO010M0100
010 Major Equipment
28-Dec-26
01-Sep-27
54.0d
0%
CO01BM0110
01B Set Static Equipment
31-Mar-27
27-Apr-27
71.0d
0%
CO01CM0110
01C Set Static Equipment - EDR Equipment
05-Apr-27
31-May-27
93.0d
0%
CO01CM0115
01C Set Rotating Equipment - EDR Equipment
05-Apr-27
31-May-27
99.0d
0%
CO01DM0110
01D Set Static Equipment
14-Apr-27
25-May-27
49.0d
0%
CO01HM0110
01H Set Static Equipment - 2303-J Emergency Pwr Gen.
19-Apr-27
31-May-27
86.0d
0%
CO01BM0150
01B Set Rotating Equipment
01-May-27
11-Jun-27
32.0d
0%
CO01DM0150
01D Set Rotating Equipment
01-May-27
11-Jun-27
34.0d
0%
CO01AM0150
01A Install Spray Devices
20-Aug-27
01-Sep-27
54.0d
0%