EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in K0 Site Prep × clear
Code
Activity
Start
Finish
Flt
%
CO01AK0150
01A Excavate Evaporation Pond
01-Jun-27
12-Jul-27
54.0d
0%
WO010K0100
010 Site Prep
01-Jun-27
28-Jan-28
37.0d
0%
CO01AK0160
01A Install Liner at Evaporation Pond
13-Jul-27
18-Aug-27
54.0d
0%
CO01JC0150
01K Excavate Pond
13-Jul-27
09-Aug-27
55.0d
0%
CO010K0130
010 Compl Roads, Ditches, Paving, & Rock Surfacing
01-Nov-27
28-Jan-28
9.0d
0%
CO010K0140
010 Finish Grading
01-Nov-27
28-Jan-28
37.0d
0%
31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan Data Date
CO01AK0150 — 01A Excavate Evaporation Pond | 01-Jun-27 → 12-Jul-27 | Not Started 0% | float 54.0d CO01AK0150 WO010K0100 — 010 Site Prep | 01-Jun-27 → 28-Jan-28 | Not Started 0% | float 37.0d WO010K0100 CO01AK0160 — 01A Install Liner at Evaporation Pond | 13-Jul-27 → 18-Aug-27 | Not Started 0% | float 54.0d CO01AK0160 CO01JC0150 — 01K Excavate Pond | 13-Jul-27 → 09-Aug-27 | Not Started 0% | float 55.0d CO01JC0150 CO010K0130 — 010 Compl Roads, Ditches, Paving, & Rock Surfacing | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 9.0d CO010K0130 CO010K0140 — 010 Finish Grading | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 37.0d CO010K0140