Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in K0 Site Prep × clear
Code
Activity
Start
Finish
Flt
%
CO01AK0150
01A Excavate Evaporation Pond
01-Jun-27
12-Jul-27
54.0d
0%
WO010K0100
010 Site Prep
01-Jun-27
28-Jan-28
37.0d
0%
CO01AK0160
01A Install Liner at Evaporation Pond
13-Jul-27
18-Aug-27
54.0d
0%
CO01JC0150
01K Excavate Pond
13-Jul-27
09-Aug-27
55.0d
0%
CO010K0130
010 Compl Roads, Ditches, Paving, & Rock Surfacing
01-Nov-27
28-Jan-28
9.0d
0%
CO010K0140
010 Finish Grading
01-Nov-27
28-Jan-28
37.0d
0%
31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CO01AK0150 — 01A Excavate Evaporation Pond | 01-Jun-27 → 12-Jul-27 | Not Started 0% | float 54.0d CO01AK0150 WO010K0100 — 010 Site Prep | 01-Jun-27 → 28-Jan-28 | Not Started 0% | float 37.0d WO010K0100 CO01AK0160 — 01A Install Liner at Evaporation Pond | 13-Jul-27 → 18-Aug-27 | Not Started 0% | float 54.0d CO01AK0160 CO01JC0150 — 01K Excavate Pond | 13-Jul-27 → 09-Aug-27 | Not Started 0% | float 55.0d CO01JC0150 CO010K0130 — 010 Compl Roads, Ditches, Paving, & Rock Surfacing | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 9.0d CO010K0130 CO010K0140 — 010 Finish Grading | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 37.0d CO010K0140