Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 1099 activities in E3B3 Construction × clear
Code
Activity
Start
Finish
Flt
%
EK000CK065
Compl. Layout of Temp. Facil. (including OCI)
29-Jan-25
01-Oct-25
100%
EK000CK075
Review Tech & Commercial Proposal - Field Fab Tank
16-Feb-25
02-Oct-25
100%
EK000CK060
Locate tie in pnts for temp water, phone, & pwr
26-Feb-25
16-Mar-25
100%
EK000CK100
Site Visit - Construction
26-Feb-25
16-Mar-25
100%
EK000CK005
OCI Subcontract - Executed
19-Mar-25
19-Nov-25
100%
EK000CK010
OCI Meeting to Define custom clearance requests
20-May-25
19-Jun-25
100%
EK000CK015
Define OCI's Point of Delivery & Liability
20-May-25
19-Jun-25
100%
EK000CV038
Select Geotech Vendor / Issue Award
20-May-25
17-Aug-25
100%
PO000MF000
Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP
28-Jul-25
03-Jan-26
100%
EK000CV039
Geotech Conducts Soil Borings / Draft Prelim Report
24-Aug-25
17-Dec-25
100%
CO000GE105
Commence Admin. Building Design (OCI)
05-Oct-25
05-Oct-25
100%
CO000K0106
Mobilize Temporary Facilities (& Punchlist & Perm. Power)
09-Nov-25
27-Dec-26
40%
EK000GE150
Execute OCI Subcontract (KBR)
16-Nov-25
16-Nov-25
100%
PO000C0045
Purch/Fab/Deliver - Fencing Materials
01-Dec-25
15-Dec-25
100%
EK000GE170
Issue Material Supply PO to OCI (Elect, Struct, Insul)
11-Dec-25
11-Dec-25
100%
CK000YA306
Establish Tax Free Zone Status
13-Dec-25
31-Jan-26
100%
PO000C0050
Receive at Site - Fencing Materials
14-Dec-25
14-Dec-25
100%
CO000C0150
Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
WO010K0110
010 Site Prep - Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
PO000MF010
Field Erected Tanks Subcontract - Purchasing & Fabrication
04-Jan-26
27-Dec-26
31%
CO000M0100
Commence Engineering - Field Fab Tanks
04-Jan-26
04-Jan-26
100%
CO02HC0140
02H Form Pour Strip Fnds - Structure
21-Mar-26
27-Dec-26
12%
WO020C0100
020 Concrete & Excavation
21-Mar-26
23-Mar-27
215.0d
9%
CK01UU4150
01U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK02UU4150
02U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK03UU4150
03U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
164.0d
10%
CK05UU4150
05U U/G Pipe Spool Fabrication & Delivery (FW) HDPE
24-Mar-26
16-Jan-27
318.0d
10%
CO000CK110
Set-Up KBR Pipe Fab Shop
24-Mar-26
27-Dec-26
11%
WO010C0100
010 Concrete & Excavation
27-Mar-26
04-May-27
149.0d
7%
CO01GC0150
01G Form, Pour, Strip Fnd - Control Building
27-Mar-26
01-Apr-26
100%
CO02JC0150
02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter)
30-Mar-26
27-Dec-26
9%
CO02JC0160
02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter)
30-Mar-26
27-Dec-26
9%
CO01DC0150
01D Form, Pour, Strip Fnd - 2101-U (Cooling Tower)
31-Mar-26
27-Dec-26
9%
CO000A0110
Start Buildings - Admin, Canteen, Warehouse, Control
31-Mar-26
31-Mar-26
100%
CO000K0100
Start Construction
31-Mar-26
31-Mar-26
100%
CO02JC0110
02J Form, Pour, Strip Fnds - Major Fnds Gen'l
01-Apr-26
27-Dec-26
9%
CO000A0150
Install Guard Towers
01-Apr-26
14-Apr-26
100%
CO01GA0115
01G Erect Control Building (Columns & Parapet Only)
03-Apr-26
27-Dec-26
8%
CO02LC0150
02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber)
03-Apr-26
27-Dec-26
8%
CO02MC0110
02M Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Apr-26
27-Dec-26
8%
CO02MC0140
02M Form Pour Strip Fnds - Structure
03-Apr-26
27-Dec-26
8%
CO02KC0150
02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank)
04-Apr-26
27-Dec-26
7%
CO03DC0110
03D Form, Pour, Strip Fnds - 2002-F (Demin Water Tank)
06-Apr-26
27-Dec-26
7%
WO030C0100
030 Concrete & Excavation
06-Apr-26
19-Mar-27
229.0d
5%
CO02BC0110
02B Form, Pour, Strip Fnds - Major Fnds
09-Apr-26
27-Dec-26
6%
CO000K0108
Start Foundations - Field Fab Tanks
09-Apr-26
09-Apr-26
100%
CO000K0110
Start Foundations - Equipment & Piperacks
09-Apr-26
09-Apr-26
100%
CO010K0120
010 Construct Perimeter Roads
15-Apr-26
28-Dec-26
5%
CO02AC0110
02A Form, Pour, Strip Fnds - Major Fnds
15-Apr-26
09-Mar-27
189.0d
5%
CO01BC0160
01B Form, Pour, Strip Fnd - 2001-FB (Water Storage Tank)
20-Apr-26
27-Dec-26
5%
CO02HC0150
02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer)
21-Apr-26
27-Dec-26
5%
CO03CC0110
03C Form, Pour, Strip Fnds - Major Fnds
21-Apr-26
27-Dec-26
5%
WK000U4100
000 U/G Pipe Spool Fabrication
10-Aug-26
07-Dec-26
0%
CO000M0110
Mobilize Field Fab Tank Contractor
27-Dec-26
27-Dec-26
0%
CO01BC0110
01B Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
0%
CO01BC0150
01B Form, Pour, Strip Fnd - 2001-FA (Water Storage Tank)
27-Dec-26
27-Dec-26
0%
CO01DC0140
01D Form Pour Strip Fnds - Sleepers
27-Dec-26
27-Dec-26
0%
CO01YC0140
01Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
0%
CO02CC0160
02C Form, Pour, Strip Fnd - 103-JTC
27-Dec-26
27-Dec-26
0%
CO02CM0140
02C Set - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
0%
CO02EC0110
02E Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
0%
CO02EC0140
02E Form Pour Strip Fnds - Structure
27-Dec-26
27-Dec-26
0%
CO02GC0160
02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
0%
CO02HC0110
02H Form, Pour, Strip Fnds - 101B (Primary Reformer)
27-Dec-26
27-Dec-26
0%
CO02HC0160
02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum)
27-Dec-26
27-Dec-26
0%
CO02HM0140
02H Set - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
0%
CO02LC0160
02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper)
27-Dec-26
27-Dec-26
0%
CO02MC0150
02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter)
27-Dec-26
27-Dec-26
0%
CO02NC0110
02N Form, Pour, Strip Fnds - Major Fnds
27-Dec-26
27-Dec-26
0%
CO02YC0140
02Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
0%
CO03CM0110
03C Set Static Equipment - 2203/4-F Caustic, Sulfuric Acid Tanks
27-Dec-26
27-Dec-26
0%
CO03DC0150
03D Form, Pour, Strip Fnd - 2002J/JA (Fresh Cooling Water Pumps)
27-Dec-26
27-Dec-26
0%
CO03FC0110
03F Form, Pour, Strip Fnds - Package Boiler
27-Dec-26
27-Dec-26
0%
CO05AC0170
05A Install Test Piles
27-Dec-26
27-Dec-26
0%
PO000P0015
Purch/Fab/Delv - Temporary Testing Materials
27-Dec-26
27-Dec-26
0%
PO000P0020
Receive at Site - Temporary Testing Materials
27-Dec-26
27-Dec-26
0%
PO000V1000
Purch/Fab/Delv - Painting Materials
27-Dec-26
27-Dec-26
0%
PO000V1005
Receive at Site - Painting Materials
27-Dec-26
27-Dec-26
0%
PO020EL155
020 Issue E&I Cable/Bulks/JB Reqn (OCI)
27-Dec-26
27-Dec-26
0%
CK000P0110
000 Pipe Fabrication
28-Dec-26
31-May-27
49.0d
0%
CK000U4110
Start Pipe Fab
28-Dec-26
28-Dec-26
0%
CK01AP0110
01A A/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK01BU4110
01B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK01CU4110
01C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK01DP0110
01D A/G Pipe Spool Fabrication
28-Dec-26
22-Mar-27
104.0d
0%
CK01DU4110
01D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK01EU4120
01E/F/G U/G Pipe Spool Fabrication (to Blg Stub Outs)
28-Dec-26
28-Dec-26
0%
CK01YP0110
01Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
117.0d
0%
CK02AU4110
02A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02BP0110
02B A/G Pipe Spool Fabrication
28-Dec-26
24-May-27
55.0d
0%
CK02BU4110
02B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02CU4110
02C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02DP0110
02D A/G Pipe Spool Fabrication
28-Dec-26
30-Apr-27
75.0d
0%
CK02DU4110
02D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02EP0110
02E A/G Pipe Spool Fabrication
28-Dec-26
25-Feb-27
130.0d
0%
CK02EU4110
02E U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02FP0110
02F A/G Pipe Spool Fabrication
28-Dec-26
20-Apr-27
84.0d
0%
CK02FU4110
02F U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02GU4110
02G U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02HU4110
02H U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02JU4110
02J U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02KU4110
02K U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02LU4110
02L U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02MU4110
02M U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK02NP0110
02N A/G Pipe Spool Fabrication
28-Dec-26
27-Mar-27
104.0d
0%
CK02PP0110
02P A/G Pipe Spool Fabrication
28-Dec-26
21-Apr-27
83.0d
0%
CK02UU4110
02U U/G Pipe Spool Fabrication (CW & Misc Headers)
28-Dec-26
28-Dec-26
0%
CK02YP0110
02Y A/G Pipe Spool Fabrication
28-Dec-26
29-Jan-27
27.0d
0%
CK03AU4110
03A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03BU4110
03B U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03CP0110
03C A/G Pipe Spool Fabrication
28-Dec-26
17-Feb-27
137.0d
0%
CK03CU4110
03C U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03DU4110
03D U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03EU4110
03E U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03FU4110
03F U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CK03YP0110
03Y A/G Pipe Spool Fabrication
28-Dec-26
06-Feb-27
80.0d
0%
CK05AU4110
05A U/G Pipe Spool Fabrication
28-Dec-26
28-Dec-26
0%
CO01AC0120
01A Form, Pour, Strip Fnds - Misc Fnds & Sumps...
28-Dec-26
09-Jan-27
247.0d
0%
CO01BC0120
01B Form, Pour, Strip Fnds - Misc Fnds
28-Dec-26
06-Jan-27
210.0d
0%
CO01BC0140
01B Form Pour Strip Fnds - Sleepers to Evap Pond
28-Dec-26
27-Jan-27
148.0d
0%
CO01BM0130
01B Tank Erection 2001-FA (Water Storage Tank)
28-Dec-26
21-Apr-27
9.0d
0%
CO01BM0140
01B Tank Erection 2001-FB (Water Storage Tank)
28-Dec-26
25-Mar-27
32.0d
0%
CO01DM0130
01D Erect 2101-U Cooling Tower
28-Dec-26
04-May-27
61.0d
0%
CO01GA0110
01G Erect Control Building (Continuation w/ Design Rev)
28-Dec-26
24-Jun-27
-14.0d
0%
CO01HC0110
01H Form, Pour, Strip Piers - Substation Building
28-Dec-26
06-Feb-27
112.0d
0%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CC0110
02C Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
26-Jan-27
165.0d
0%
CO02CC0150
02C Form, Pour, Strip Fnd - 103/105-J & Table Tops
28-Dec-26
28-Dec-26
0%
CO02CM0110
02C Set Static Equipment - 128/167-C
28-Dec-26
28-Dec-26
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DC0110
02D Form, Pour, Strip Fnds - Major Fnds
28-Dec-26
09-Jan-27
252.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FC0110
02F Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
234.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02GC0150
02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops
28-Dec-26
01-Feb-27
134.0d
0%
CO02GM0140
02G Set/Install - 102-J Fd Gas Compr. & Aux.
28-Dec-26
22-Apr-27
188.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KC0110
02K Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
192.0d
0%
CO02KM0130
02K Tank Erection 114-F (Benfield Solution Tank)
28-Dec-26
08-Jan-27
97.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02LC0110
02L Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
123.0d
0%
CO02LC0140
02L Form Pour Strip Fnds - 02L Structure
28-Dec-26
29-Jan-27
45.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
0%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
CO03AC0110
03A Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
16-Jan-27
155.0d
0%
CO03BC0110
03B Form, Pour, Strip Fnds - Major Fnds (N/A)
28-Dec-26
28-Dec-26
0%
CO03BC0140
03B Form, Pour, Strip Fnds - 2401-A Wastewater Sump
28-Dec-26
30-Dec-26
266.0d
0%
CO03DM0145
03D Tank Erection 2002-F (Demin Water Tank)
28-Dec-26
12-Jan-27
105.0d
0%
CO03DU4120
03D U/G Piping Installation
28-Dec-26
05-Jan-27
199.0d
0%
CO03EC0110
03E Form, Pour, Strip Fnds - 2001-U Water Treatment
28-Dec-26
20-Feb-27
126.0d
0%
CO03FM0110
03F Erect 2002-U Package Boiler
28-Dec-26
13-Mar-27
159.0d
0%
CO03YC0110
03Y Form, Pour, Strip Fnds - Sleeper Fnds
28-Dec-26
01-Jan-27
98.0d
0%
CO03YC0120
03Y Form, Pour, Strip Fnds - Pipe Rack Fnds
28-Dec-26
28-Dec-26
0%
CO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
CO05AC0175
05A Test Piles (Load Test)
28-Dec-26
09-Jan-27
-51.0d
0%
P002YS0010
02Y Recv at Site - Structural Steel (First Shipment)
28-Dec-26
28-Dec-26
0%
PO000E0000
Purch/Fab/Deliver - A/G Electrical Bulks (First)
28-Dec-26
10-Apr-27
20.0d
0%
PO000V2000
Purch/Fab/Delv - Insulation Materials
28-Dec-26
15-May-27
98.0d
0%
PO01BS0130
01B Fab & Ship Miscellaneous Steel
28-Dec-26
26-Feb-27
86.0d
0%
PO01DS0120
01D Fab & Ship Structural Steel
28-Dec-26
19-Feb-27
94.0d
0%
PO01DS0130
01D Fab & Ship Miscellaneous Steel
28-Dec-26
19-Feb-27
94.0d
0%
PO01EA0135
01E Guard House Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
200.0d
0%
PO01FA0135
01F Mosque Design Drawings - Submit to KBR
28-Dec-26
02-Jan-27
143.0d
0%
PO01HS0130
01H Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
51.0d
0%
PO01YS0120
01Y Fab & Ship Structural Steel
28-Dec-26
29-Jan-27
39.0d
0%
PO02AS0120
02A Fab & Ship Structural Steel
28-Dec-26
09-Apr-27
103.0d
0%
PO02AS0130
02A Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
115.0d
0%
PO02CS0130
02C Fab & Ship Miscellaneous Steel
28-Dec-26
26-Mar-27
83.0d
0%
PO02DS0120
02D Fab & Ship Structural Steel
28-Dec-26
02-Apr-27
93.0d
0%
PO02DS0130
02D Fab & Ship Miscellaneous Steel
28-Dec-26
02-Apr-27
105.0d
0%
PO02ES0120
02E Fab & Ship Structural Steel
28-Dec-26
16-Apr-27
127.0d
0%
PO02ES0130
02E Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
67.0d
0%
PO02FS0130
02F Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
133.0d
0%
PO02HS0120
02H Fab & Ship Structural Steel
28-Dec-26
26-Mar-27
92.0d
0%
PO02HS0130
02H Fab & Ship Miscellaneous Steel
28-Dec-26
26-Mar-27
78.0d
0%
PO02JS0120
02J Fab & Ship Structural Steel
28-Dec-26
16-Apr-27
98.0d
0%
PO02JS0130
02J Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
110.0d
0%
PO02LS0120
02L Fab & Ship Structural Steel
28-Dec-26
05-Mar-27
-15.0d
0%
PO02LS0130
02L Fab & Ship Miscellaneous Steel
28-Dec-26
05-Mar-27
93.0d
0%
PO02MS0120
02M Fab & Ship Structural Steel
28-Dec-26
19-Mar-27
123.0d
0%
PO02MS0130
02M Fab & Ship Miscellaneous Steel
28-Dec-26
19-Mar-27
147.0d
0%
PO02NMS100
02N Fab & Ship Miscellaneous Steel
28-Dec-26
30-Apr-27
67.0d
0%
PO02QMS100
02Q Fab & Ship Miscellaneous Steel
28-Dec-26
23-Apr-27
121.0d
0%
PO02YS0120
02Y Fab & Ship Structural Steel
28-Dec-26
05-Mar-27
-22.0d
0%
PO03AS0130
03A Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
56.0d
0%
PO03BS0130
03B Fab & Ship Miscellaneous Steel
28-Dec-26
09-Apr-27
169.0d
0%
PO03CS0130
03C Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
87.0d
0%
PO03DS0130
03D Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
98.0d
0%
PO03ES0130
03E Fab & Ship Miscellaneous Steel
28-Dec-26
16-Apr-27
58.0d
0%
PO03YS0120
03Y Fab & Ship Structural Steel
28-Dec-26
29-Jan-27
39.0d
0%
WK000P0100
000 A/G Pipe Spool Fabrication
28-Dec-26
31-May-27
49.0d
0%
WO010A0100
010 Buildings
28-Dec-26
24-Jun-27
94.0d
0%
WO010M0100
010 Major Equipment
28-Dec-26
01-Sep-27
54.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
WO020M0100
020 Major Equipment
28-Dec-26
16-Aug-27
156.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
WO030M0100
030 Major Equipment
28-Dec-26
26-Apr-27
192.0d
0%
WO030U4100
030 U/G Piping Installation
28-Dec-26
26-Feb-27
229.0d
0%
WO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
WO050C0110
050 Concrete Paving
28-Dec-26
28-Dec-26
0.0d
0%
WT010M0100
010 Tank Erection
28-Dec-26
21-Apr-27
9.0d
0%
WT020M0100
020 Tank Erection
28-Dec-26
08-Jan-27
97.0d
0%
WT030M0100
030 Tank Erection
28-Dec-26
12-Jan-27
105.0d
0%
SC01JT0120
01J RFSU
28-Dec-26
28-Dec-26
441.0d
0%
CK01BP0110
01B A/G Pipe Spool Fabrication
31-Dec-26
23-Mar-27
101.0d
0%
CO01AV1110
01A Paint Fabricated Pipe Spools
31-Dec-26
02-Jan-27
253.0d
0%
WO010V1100
010 Paint
31-Dec-26
05-Oct-27
131.0d
0%
CO02HM0200
02H Start Primary Reformer Erection (101-B)
02-Jan-27
02-Jan-27
108.0d
0%
CO02HM0210
02H Erect Radiant Section Shell (101-B)
02-Jan-27
02-Apr-27
108.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
PO03FS0130
03F Fab & Ship Miscellaneous Steel
02-Jan-27
09-Apr-27
88.0d
0%
EK01EA0140
01E Guard House Design Drawings - Approval
03-Jan-27
16-Jan-27
175.0d
0%
EK01FA0140
01F Mosque Design Drawings - Approval
03-Jan-27
16-Jan-27
119.0d
0%
PO01CS0130
01C Fab & Ship Miscellaneous Steel
04-Jan-27
09-Apr-27
106.0d
0%
PO02GS0130
02G Fab & Ship Miscellaneous Steel
04-Jan-27
26-Mar-27
107.0d
0%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO03DC0120
03D Form, Pour, Strip Fnds - Misc Fnds
06-Jan-27
19-Jan-27
199.0d
0%
CK02QP0110
02Q A/G Pipe Spool Fabrication
11-Jan-27
13-Apr-27
90.0d
0%
EK05ACV210
05A COSMO Design Approval (Assuming No Change)
11-Jan-27
16-Jan-27
-51.0d
0%
CO02CM0125
02C Set - 103/105-J Compressors
12-Jan-27
16-Jan-27
167.0d
0%
CO02YS0110
02Y Erect Structural Steel - Pipe Rack
12-Jan-27
14-Jun-27
-35.0d
0%
WO020S0100
020 Erect Steel
12-Jan-27
07-Oct-27
69.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO03YV1110
03Y Paint Fabricated Pipe Spools
13-Jan-27
13-Feb-27
154.0d
0%
WO030V1100
030 Paint
13-Jan-27
23-Aug-27
153.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO03DU3110
03D U/G Earthing Installation
15-Jan-27
19-Jan-27
199.0d
0%
WO030U3100
030 Install U/G Electrical
15-Jan-27
12-Mar-27
229.0d
0%
PO05AS0120
05A Fab & Ship Structural Steel
15-Jan-27
04-Jun-27
23.0d
0%
PO05AS0130
05A Fab & Ship Miscellaneous Steel
15-Jan-27
04-Jun-27
27.0d
0%
CO02HC0120
02H Form, Pour, Strip Fnds - Misc Fnds
16-Jan-27
05-Feb-27
174.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO03UP0150
03U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO02CM0130
02C Install - 103/105-J Compressors & Aux. Equip.
18-Jan-27
13-May-27
167.0d
0%
CO05AC0185
05A Procure Material & Mob Piling Contractor
18-Jan-27
30-Jan-27
-51.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%
CO02GC0110
02G Form, Pour, Strip Fnds - Major Fnds Gen'l
23-Jan-27
26-Feb-27
159.0d
0%
CK02CP0110
02C A/G Pipe Spool Fabrication
25-Jan-27
20-Feb-27
134.0d
0%
CO01HU3110
01H U/G Earthing Installation
25-Jan-27
06-Feb-27
134.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
PO05BS0130
05B Fab & Ship Miscellaneous Steel
25-Jan-27
12-Jun-27
87.0d
0%
CO02BM0110
02B Set Static Equipment
25-Jan-27
25-Jan-27
0%
CO02BV1130
02B Paint Touch-up - Equipment
25-Jan-27
01-Feb-27
300.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO01YV1110
01Y Paint Fabricated Pipe Spools
28-Jan-27
05-Feb-27
149.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO01JP0230
01J U/G Pipe Erection - Piping to Corridor
29-Jan-27
26-Feb-27
160.0d
0%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO02BC0120
02B Form, Pour, Strip Fnds - Misc Fnds
29-Jan-27
29-Jan-27
0%
PO01YS0000
01Y Recv at Site - Structural Steel
29-Jan-27
29-Jan-27
39.0d
0%
PO03YS0000
03Y Recv at Site - Structural Steel
29-Jan-27
29-Jan-27
39.0d
0%
CO01BU4120
01B U/G Piping Installation
30-Jan-27
10-Mar-27
173.0d
0%
CO01DU4120
01D U/G Piping Installation
30-Jan-27
02-Mar-27
49.0d
0%
CO01EU4130
01E/F/G U/G Piping Installation (to Bldg Stub Outs)
30-Jan-27
26-Mar-27
147.0d
0%
CO02CC0120
02C Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
162.0d
0%
CO02DC0120
02D Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
30-Jan-27
260.0d
0%
CO02EC0120
02E Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
227.0d
0%
CO02FC0120
02F Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
234.0d
0%
CO02FM0110
02F Set Static Equipment
30-Jan-27
26-Feb-27
241.0d
0%
CO02JC0120
02J Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
211.0d
0%
CO02KC0120
02K Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
214.0d
0%
CO02LC0120
02L Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
123.0d
0%
CO02MC0120
02M Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
239.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02YC0130
02Y Install Paving
30-Jan-27
17-Mar-27
71.0d
0%
CO03AU4120
03A U/G Piping Installation
30-Jan-27
18-Feb-27
135.0d
0%
CO03BU4120
03B U/G Piping Installation
30-Jan-27
17-Feb-27
237.0d
0%
CO03CU4120
03C U/G Piping Installation
30-Jan-27
18-Feb-27
166.0d
0%
CO03EU4120
03E U/G Piping Installation
30-Jan-27
26-Feb-27
121.0d
0%
CO03FU4120
03F U/G Piping Installation
30-Jan-27
18-Feb-27
155.0d
0%
WO020C0110
020 Concrete Paving
30-Jan-27
22-May-27
210.0d
0%
CO01HC0140
01H Form Pour Strip Fnds - Transformers & Generator
01-Feb-27
27-Feb-27
116.0d
0%
CO03DC0130
03D Install Paving
01-Feb-27
06-Feb-27
189.0d
0%
CO03FM0150
03F Install Chemical Injection System
01-Feb-27
13-Mar-27
159.0d
0%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
PO000EL000
Electrical Heat Tracing - Purchase & Deliver Materials (By OCI)
01-Feb-27
04-May-27
108.0d
0%
WO030C0110
030 Concrete Paving
01-Feb-27
17-Apr-27
210.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO01EA0130
01E Erect Guard House
04-Feb-27
03-Mar-27
191.0d
0%
CO01FA0130
01F Erect Mosque
04-Feb-27
28-Apr-27
143.0d
0%
CO02YV1110
02Y Paint Fabricated Pipe Spools
05-Feb-27
19-Feb-27
131.0d
0%
CO01CC0110
01C Form, Pour, Strip Fnds - Major Fnds Gen'l
08-Feb-27
06-Mar-27
117.0d
0%
CO01YC0130
01Y Install Paving
08-Feb-27
27-Feb-27
134.0d
0%
WO010C0110
010 Concrete Paving
08-Feb-27
08-Jul-27
188.0d
0%
CK02GP0110
02G A/G Pipe Spool Fabrication
09-Feb-27
15-Mar-27
115.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CK03EP0110
03E A/G Pipe Spool Fabrication
12-Feb-27
02-Mar-27
126.0d
0%
CK03FP0110
03F A/G Pipe Spool Fabrication
12-Feb-27
23-Feb-27
132.0d
0%
CO02EV1110
02E Paint Fabricated Pipe Spools
12-Feb-27
04-Mar-27
250.0d
0%
CO03AC0120
03A Form, Pour, Strip Fnds - Misc Fnds
12-Feb-27
25-Feb-27
141.0d
0%
CO03CV1110
03C Paint Fabricated Pipe Spools
13-Feb-27
24-Feb-27
191.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%
CO02GV1110
02G Paint Fabricated Pipe Spools
16-Feb-27
22-Mar-27
230.0d
0%
CO03BC0120
03B Form, Pour, Strip Fnds - Misc Fnds
18-Feb-27
03-Mar-27
243.0d
0%
CO03CC0120
03C Form, Pour, Strip Fnds - Misc Fnds
19-Feb-27
04-Mar-27
166.0d
0%
CO03EV1110
03E Paint Fabricated Pipe Spools
19-Feb-27
09-Mar-27
171.0d
0%
CO03FC0120
03F Form, Pour, Strip Fnds - Misc Fnds
19-Feb-27
11-Mar-27
155.0d
0%
CO03FV1110
03F Paint Fabricated Pipe Spools
19-Feb-27
02-Mar-27
183.0d
0%
PO01DS0000
01D Recv at Site - Structural Steel
19-Feb-27
19-Feb-27
94.0d
0%
PO01DS0010
01D Recv at Site - Misc Steel
19-Feb-27
19-Feb-27
94.0d
0%
CK03AP0110
03A A/G Pipe Spool Fabrication
20-Feb-27
03-Mar-27
125.0d
0%
CO02CC0130
02C Install Paving
20-Feb-27
05-Mar-27
162.0d
0%
CO02LC0130
02L Install Paving
20-Feb-27
05-Mar-27
123.0d
0%
CO01CU4120
01C U/G Piping Installation
22-Feb-27
06-Mar-27
160.0d
0%
CO02HM0220
02H Erect Radiant Ducting / Burners (101-B)
22-Feb-27
20-Mar-27
151.0d
0%
PO02KS0130
02K Fab & Ship Miscellaneous Steel
22-Feb-27
09-Apr-27
120.0d
0%
CO03BU3110
03B U/G Earthing Installation
23-Feb-27
03-Mar-27
237.0d
0%
CK02JP0110
02J A/G Pipe Spool Fabrication
23-Feb-27
20-Mar-27
111.0d
0%
CO03CU3110
03C U/G Earthing Installation
24-Feb-27
04-Mar-27
166.0d
0%
CO03FU3110
03F U/G Earthing Installation
24-Feb-27
04-Mar-27
161.0d
0%
CO03AU3110
03A U/G Earthing Installation
26-Feb-27
04-Mar-27
135.0d
0%
CO02UDT110
02U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
CO03UDT110
03U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
PO01BS0010
01B Recv at Site - Misc Steel
26-Feb-27
26-Feb-27
86.0d
0%
SC02UT0120
02U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
SC03UT0120
03U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CK03DP0110
03D A/G Pipe Spool Fabrication
27-Feb-27
04-Mar-27
124.0d
0%
CO02GC0120
02G Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
165.0d
0%
CO02GM0110
02G Set Static Equipment - Gen'l
27-Feb-27
31-Mar-27
208.0d
0%
CO03AV1110
03A Paint Fabricated Pipe Spools
27-Feb-27
10-Mar-27
148.0d
0%
CO03EC0120
03E Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
121.0d
0%
CO03EU3110
03E U/G Earthing Installation
27-Feb-27
12-Mar-27
127.0d
0%
CK01CP0110
01C A/G Pipe Spool Fabrication
27-Feb-27
06-Mar-27
123.0d
0%
CO01HC0120
01H Form, Pour, Strip Fnds - Misc Fnds
01-Mar-27
13-Mar-27
176.0d
0%
CO02JS0130
02J Pre-Install Misc Steel - 104-D2
01-Mar-27
15-Mar-27
103.0d
0%
CO02JS0140
02J Pre-Install Misc Steel - 104-D1
01-Mar-27
15-Mar-27
108.0d
0%
CO02LS0130
02L Pre-Install Misc Steel - 101-E
01-Mar-27
15-Mar-27
113.0d
0%
CO03BM0110
03B Set Static Equipment - Gen'l
01-Mar-27
02-Apr-27
212.0d
0%
CO03EM0110
03E Set Static Equipment - Gen'l
01-Mar-27
05-Apr-27
135.0d
0%
CO01DC0110
01D Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Mar-27
13-Apr-27
49.0d
0%
CO01DU3110
01D U/G Earthing Installation
03-Mar-27
17-Mar-27
113.0d
0%
CO01EC0135
01E Install Paving - Guard House
04-Mar-27
17-Mar-27
285.0d
0%
CO03BC0130
03B Install Paving
04-Mar-27
17-Mar-27
237.0d
0%
CO01BU3110
01B U/G Earthing Installation
05-Mar-27
24-Mar-27
173.0d
0%
PO02LS0000
02L Recv at Site - Structural Steel
05-Mar-27
05-Mar-27
-15.0d
0%
PO02LS0010
02L Recv at Site - Misc Steel
05-Mar-27
05-Mar-27
93.0d
0%
PO02YS0000
02Y Recv at Site - Structural Steel (Last Shipment)
05-Mar-27
05-Mar-27
-14.0d
0%
CO01YS0110
01Y Erect Structural Steel - Pipe Rack
06-Mar-27
30-Apr-27
39.0d
0%
CO03DV1110
03D Paint Fabricated Pipe Spools
06-Mar-27
11-Mar-27
172.0d
0%
CO03YS0110
03Y Erect Structural Steel
06-Mar-27
26-Mar-27
39.0d
0%
WO010S0100
010 Erect Steel
06-Mar-27
11-Jun-27
94.0d
0%
WO030S0100
030 Erect Steel
06-Mar-27
25-Jun-27
157.0d
0%
CO01CV1110
01C Paint Fabricated Pipe Spools
06-Mar-27
13-Mar-27
174.0d
0%
CO01BV1110
01B Paint Fabricated Pipe Spools
08-Mar-27
30-Mar-27
153.0d
0%
CO01CC0120
01C Form, Pour, Strip Fnds - Misc Fnds
08-Mar-27
27-Mar-27
160.0d
0%
CO03AC0130
03A Install Paving
08-Mar-27
13-Mar-27
133.0d
0%
CO02GM0125
02G Set - 101-J/JT Air Compr.
08-Mar-27
05-Apr-27
105.0d
0%
CO02AC0120
02A Form, Pour, Strip Fnds - Misc Fnds
10-Mar-27
23-Mar-27
189.0d
0%
CO02AM0150
02A Set Rotating Equipment
10-Mar-27
06-Apr-27
207.0d
0%
CO01DV1110
01D Paint Fabricated Pipe Spools
11-Mar-27
29-Mar-27
142.0d
0%
CO02GC0130
02G Install Paving
13-Mar-27
26-Mar-27
159.0d
0%
CO01CU3110
01C U/G Earthing Installation
15-Mar-27
20-Mar-27
166.0d
0%
CO01GU3110
01G U/G Earthing Installation
15-Mar-27
27-Mar-27
146.0d
0%
CO03CC0130
03C Install Paving
15-Mar-27
20-Mar-27
158.0d
0%
CO02HM0250
02H Set Forced Draft Fan (101-B)
15-Mar-27
12-Apr-27
234.0d
0%
CO03CM0150
03C Set Rotating Equipment
15-Mar-27
22-Mar-27
146.0d
0%
CO03DM0150
03D Set Rotating Equipment
15-Mar-27
29-Mar-27
158.0d
0%
CO02HM0135
02H Give 30 Day notice to Manufacture Refractory (103-D)
16-Mar-27
16-Mar-27
-40.0d
0%
CO03FV1130
03F Paint Touch-up - Equipment
17-Mar-27
27-Mar-27
183.0d
0%
CO02YS0120
02Y Erect Misc Steel - Pipe Rack
19-Mar-27
14-Jun-27
102.0d
0%
PO02MS0000
02M Recv at Site - Structural Steel
19-Mar-27
19-Mar-27
123.0d
0%
PO02MS0010
02M Recv at Site - Misc Steel
19-Mar-27
19-Mar-27
147.0d
0%
CK02MP0110
02M A/G Pipe Spool Fabrication
22-Mar-27
07-Apr-27
95.0d
0%
CO02HM0246
02H Install Radiant Sect Coils (101-B)
22-Mar-27
17-Apr-27
151.0d
0%
CO03FC0130
03F Install Paving
22-Mar-27
03-Apr-27
147.0d
0%
CO02HM0255
02H Set Induced Draft Fan (101-B)
22-Mar-27
19-Apr-27
234.0d
0%
CO02KV1130
02K Paint Touch-up - Equipment
23-Mar-27
15-Apr-27
236.0d
0%
CO02AC0130
02A Install Paving
24-Mar-27
30-Mar-27
189.0d
0%
CO03CV1130
03C Paint Touch-up - Equipment
24-Mar-27
05-Apr-27
195.0d
0%
CO02CM0150
02C Set Rotating Equipment - 112-J/JA/JM
26-Mar-27
30-Mar-27
205.0d
0%
CO02GM0150
02G Set Rotating Equipment
26-Mar-27
10-Apr-27
199.0d
0%
CO02KM0150
02K Set Rotating Equipment
26-Mar-27
01-Apr-27
163.0d
0%
CO02LM0150
02L Set Rotating Equipment
26-Mar-27
27-Apr-27
170.0d
0%
CO03BM0150
03B Set Rotating Equipment
26-Mar-27
15-Apr-27
200.0d
0%
CO01UDT110
01U Mechanical Completion
26-Mar-27
26-Mar-27
277.0d
0%
PO02CS0010
02C Recv at Site - Misc Steel
26-Mar-27
26-Mar-27
83.0d
0%
PO02GS0010
02G Recv at Site - Misc Steel
26-Mar-27
26-Mar-27
107.0d
0%
PO02HS0000
02H Recv at Site - Structural Steel
26-Mar-27
26-Mar-27
92.0d
0%
PO02HS0010
02H Recv at Site - Misc Steel
26-Mar-27
26-Mar-27
78.0d
0%
SC01UT0120
01U RFSU
26-Mar-27
26-Mar-27
352.0d
0%
CO02HS0140
02H Install Misc Steel - 156-F
27-Mar-27
09-Apr-27
102.0d
0%
CO03YP0130
03Y LB Pipe Erection
27-Mar-27
09-Jul-27
39.0d
0%
WO030P0100
030 Above Ground Pipe
27-Mar-27
23-Aug-27
138.0d
0%
CO02JV1110
02J Paint Fabricated Pipe Spools
27-Mar-27
27-Mar-27
164.0d
0%
CK03BP0110
03B A/G Pipe Spool Fabrication
29-Mar-27
08-Apr-27
94.0d
0%
CO01CC0130
01C Install Paving
29-Mar-27
10-Apr-27
160.0d
0%
CO03AM0110
03A Set Static Equipment
29-Mar-27
26-Apr-27
95.0d
0%
CO02AV1130
02A Paint Touch-up - Equipment
30-Mar-27
20-Apr-27
232.0d
0%
CO01BM0110
01B Set Static Equipment
31-Mar-27
27-Apr-27
71.0d
0%
CO02MV1110
02M Paint Fabricated Pipe Spools
01-Apr-27
14-Apr-27
215.0d
0%
CO02NV1110
02N Paint Fabricated Pipe Spools
01-Apr-27
03-Apr-27
216.0d
0%
CO04AU3110
04A U/G Fiber Optic Cable Installation
01-Apr-27
10-Aug-27
137.0d
0%
WO04AU3100
04A Install U/G Electrical
01-Apr-27
10-Aug-27
137.0d
0%
CK02LP0110
02L A/G Pipe Spool Fabrication
02-Apr-27
22-May-27
32.0d
0%
CO02DM0150
02D Set Rotating Equipment
02-Apr-27
15-Apr-27
182.0d
0%
PO02DS0000
02D Recv at Site - Structural Steel
02-Apr-27
02-Apr-27
93.0d
0%
PO02DS0010
02D Recv at Site - Misc Steel
02-Apr-27
02-Apr-27
105.0d
0%
CK02KP0110
02K A/G Pipe Spool Fabrication
03-Apr-27
27-Apr-27
78.0d
0%
CO01BS0120
01B Erect Misc Steel
03-Apr-27
30-Apr-27
86.0d
0%
CO02HC0130
02H Install Paving
03-Apr-27
16-Apr-27
120.0d
0%
CO02HM0230
02H Set Convection Sections (101-B)
03-Apr-27
30-Apr-27
108.0d
0%
CO02HM0240
02H Set Stack for (101-B)
03-Apr-27
30-Apr-27
223.0d
0%
CO03YP0140
03Y SB Pipe Erection
03-Apr-27
16-Jul-27
45.0d
0%
CO02JC0130
02J Install Paving
05-Apr-27
10-Apr-27
168.0d
0%
CO03BV1110
03B Paint Fabricated Pipe Spools
05-Apr-27
15-Apr-27
223.0d
0%
CO03EC0130
03E Install Paving
05-Apr-27
17-Apr-27
108.0d
0%
CO01CM0110
01C Set Static Equipment - EDR Equipment
05-Apr-27
31-May-27
93.0d
0%
CO01CM0115
01C Set Rotating Equipment - EDR Equipment
05-Apr-27
31-May-27
99.0d
0%
CO02GM0130
02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux.
05-Apr-27
30-Jul-27
105.0d
0%
CO02HS0130
02H Pre-Install Misc Steel - 103-D
05-Apr-27
19-Apr-27
68.0d
0%
CO03DV1130
03D Paint Touch-up - Equipment (& 2002-F Tank)
06-Apr-27
12-Apr-27
189.0d
0%
CO02FV1110
02F Paint Fabricated Pipe Spools
09-Apr-27
27-Apr-27
204.0d
0%
CO02LV1110
02L Paint Fabricated Pipe Spools
09-Apr-27
29-May-27
162.0d
0%
PO01CS0010
01C Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
106.0d
0%
PO01HS0010
01H Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
51.0d
0%
PO02AS0000
02A Recv at Site - Structural Steel
09-Apr-27
09-Apr-27
103.0d
0%
PO02AS0010
02A Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
115.0d
0%
PO02KS0010
02K Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
120.0d
0%
PO03BS0010
03B Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
169.0d
0%
PO03FS0010
03F Recv at Site - Misc Steel
09-Apr-27
09-Apr-27
88.0d
0%
CO02KV1110
02K Paint Fabricated Pipe Spools
10-Apr-27
04-May-27
181.0d
0%
CO02LS0110
02L Erect Structure
10-Apr-27
18-Jun-27
-15.0d
0%
PO000E0010
Receive at Site - A/G Electrical Bulks (First)
10-Apr-27
10-Apr-27
20.0d
0%
CO02KC0130
02K Install Paving
12-Apr-27
17-Apr-27
165.0d
0%
CO01HA0110
01H Set 2610-K Electrical Power House
12-Apr-27
03-May-27
76.0d
0%
CO02YP0130
02Y LB Pipe Erection
13-Apr-27
05-Oct-27
-35.0d
0%
WO020P0100
020 Above Ground Pipe
13-Apr-27
14-Feb-28
-1.0d
0%
CO01DC0120
01D Form, Pour, Strip Fnds - Misc Fnds
14-Apr-27
04-May-27
72.0d
0%
CO01DM0110
01D Set Static Equipment
14-Apr-27
25-May-27
49.0d
0%
CO02DV1130
02D Paint Touch-up - Equipment
15-Apr-27
29-Apr-27
224.0d
0%
CO02FM0150
02F Set Rotating Equipment
16-Apr-27
13-May-27
176.0d
0%
CO02QV1110
02Q Paint Fabricated Pipe Spools
16-Apr-27
20-Apr-27
210.0d
0%
PO02ES0000
02E Recv at Site - Structural Steel
16-Apr-27
16-Apr-27
127.0d
0%
PO02ES0010
02E Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
67.0d
0%
PO02FS0010
02F Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
133.0d
0%
PO02JS0000
02J Recv at Site - Structural Steel
16-Apr-27
16-Apr-27
98.0d
0%
PO02JS0010
02J Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
110.0d
0%
PO03AS0010
03A Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
56.0d
0%
PO03CS0010
03C Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
87.0d
0%
PO03DS0010
03D Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
98.0d
0%
PO03ES0010
03E Recv at Site - Misc Steel
16-Apr-27
16-Apr-27
58.0d
0%
CO020M0110
Mobilize / Assemble / Test Heavy Lift Crane
19-Apr-27
01-May-27
56.0d
0%
CO02EC0130
02E Install Paving
19-Apr-27
24-Apr-27
172.0d
0%
CO02HM0248
02H Install Effluent Transfer Line (107-D)
19-Apr-27
01-May-27
151.0d
0%
CO03BV1130
03B Paint Touch-up - Equipment
19-Apr-27
29-Apr-27
248.0d
0%
CK02HP0110
02H A/G Pipe Spool Fabrication
19-Apr-27
29-May-27
51.0d
0%
CO01HM0110
01H Set Static Equipment - 2303-J Emergency Pwr Gen.
19-Apr-27
31-May-27
86.0d
0%
CO02LS0140
02L Pre-Install Misc Steel - 102-E
19-Apr-27
03-May-27
76.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO02DV1110
02D Paint Fabricated Pipe Spools
23-Apr-27
07-May-27
177.0d
0%
CO04AC0110
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
WO04AC0100
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
PO02QMS110
02Q Recv at Site - Misc Steel
23-Apr-27
23-Apr-27
121.0d
0%
CO01YS0120
01Y Erect Misc Steel - Pipe Rack
24-Apr-27
21-May-27
39.0d
0%
CO02MS0110
02M Erect Structural Steel - Structure
24-Apr-27
14-May-27
123.0d
0%
CO02PV1110
02P Paint Fabricated Pipe Spools
24-Apr-27
28-Apr-27
199.0d
0%
CO02FC0130
02F Install Paving
26-Apr-27
01-May-27
173.0d
0%
CO02HV1110
02H Paint Fabricated Pipe Spools
26-Apr-27
05-Jun-27
54.0d
0%
CK05AP0110
05A A/G Pipe Spool Fabrication
28-Apr-27
31-May-27
49.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%
CO01FC0135
01F Install Paving - Mosque
29-Apr-27
19-May-27
203.0d
0%
PO02NMS110
02N Recv at Site - Misc Steel
30-Apr-27
30-Apr-27
67.0d
0%
CO01BM0150
01B Set Rotating Equipment
01-May-27
11-Jun-27
32.0d
0%
CO01DM0150
01D Set Rotating Equipment
01-May-27
11-Jun-27
34.0d
0%
CO01YP0130
01Y LB Pipe Erection - Pipe Rack
01-May-27
25-Jun-27
39.0d
0%
CO02CS0120
02C Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
83.0d
0%
CO02GS0130
02G Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
107.0d
0%
CO02HM0235
02H Erect Preheater (101-B)
01-May-27
25-Jun-27
175.0d
0%
WO010P0100
010 Above Ground Pipe
01-May-27
05-Oct-27
95.0d
0%
CO020M0120
Heavy Lift Crane Useage
03-May-27
04-Aug-27
56.0d
0%
CO02HM0130
02H Set (Heavy Lift) - 103-D (Secondary Reformer)
03-May-27
07-May-27
56.0d
0%
CO02HM0225
02H Erect Penthouse Roof, & Siding (101-B)
03-May-27
29-May-27
151.0d
0%
CO02MC0130
02M Install Paving
03-May-27
08-May-27
172.0d
0%
CO02KS0130
02K Pre-Install Misc Steel - Static Equipment
03-May-27
17-May-27
101.0d
0%
CO02GP0130
02G LB Pipe Erection
04-May-27
10-Sep-27
105.0d
0%
CK02AP0110
02A A/G Pipe Spool Fabrication
05-May-27
26-May-27
53.0d
0%
CO000E0500
Cathodic Protection - Installation
05-May-27
17-Oct-27
6.0d
0%
CO01DC0130
01D Install Paving
05-May-27
18-May-27
72.0d
0%
CO01DS0120
01D Erect Misc Steel
05-May-27
01-Jun-27
61.0d
0%
CO05AV1110
05A Paint Fabricated Pipe Spools
05-May-27
07-Jun-27
166.0d
0%
WO050V1100
050 Paint
05-May-27
12-Apr-28
12.0d
0%
WP000U3100
Cathodic Protection
05-May-27
17-Oct-27
6.0d
0%
CO02CP0130
02C LB Pipe Erection
08-May-27
08-Oct-27
83.0d
0%
CO02DS0110
02D Erect Structural Steel
08-May-27
28-May-27
93.0d
0%
CO02JM0130
02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter)
08-May-27
13-May-27
56.0d
0%
CO02LS0120
02L Erect Misc Steel
08-May-27
04-Jun-27
39.0d
0%
CO02DC0130
02D Install Paving
10-May-27
15-May-27
175.0d
0%
CO02FV1130
02F Paint Touch-up - Equipment
10-May-27
27-May-27
200.0d
0%
CO02MS0130
02M Pre-Install Misc Steel - 105-D
10-May-27
24-May-27
63.0d
0%
CO02YP0140
02Y SB Pipe Erection
11-May-27
02-Nov-27
-29.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO02GP0140
02G SB Pipe Erection
11-May-27
25-Sep-27
105.0d
0%
CO04AV2110
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
WO04AV2100
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
CO05AU4120
05A U/G Piping Installation
13-May-27
07-Jul-27
77.0d
0%
WO050U4100
050 U/G Piping Installation
13-May-27
30-Sep-27
135.0d
0%
CO02CV1130
02C Paint Touch-up - Equipment
14-May-27
22-Jun-27
190.0d
0%
CO02JM0140
02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter)
14-May-27
19-May-27
56.0d
0%
CO01CS0120
01C Erect Misc Steel
15-May-27
28-May-27
106.0d
0%
CO01HS0110
01H Erect Structural Steel - Stairs & Platform
15-May-27
11-Jun-27
51.0d
0%
CO02AS0110
02A Erect Structural Steel
15-May-27
04-Jun-27
103.0d
0%
CO02CP0140
02C SB Pipe Erection
15-May-27
15-Oct-27
83.0d
0%
CO02MM0110
02M Set Static Equipment - Gen'l
15-May-27
16-Jun-27
147.0d
0%
CO03BS0120
03B Erect Misc Steel - Structure
15-May-27
11-Jun-27
169.0d
0%
CO03FS0120
03F Erect Misc Steel
15-May-27
25-Jun-27
88.0d
0%
PO000V2005
Receive at Site - Insulation Materials
15-May-27
15-May-27
98.0d
0%
CO01BE0110
01B Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO01EE0110
01E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
180.0d
0%
CO01FE0110
01F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
152.0d
0%
CO01GE0130
01G Power Tray, Cable, Terminations
17-May-27
12-Jun-27
92.0d
0%
CO02BC0130
02B Install Paving
17-May-27
22-May-27
210.0d
0%
CO03CE0110
03C Lighting JB's, Stands, Tray & Cable
17-May-27
12-Jun-27
123.0d
0%
CO03DE0110
03D Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03DE0130
03D Power/Control JB's, Tray, Cable, Termination
17-May-27
04-Jun-27
131.0d
0%
CO03EE0110
03E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03FE0110
03F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
111.0d
0%
CO03YE0110
03Y Lighting JB's, Stands, Tray & Cable
17-May-27
07-Aug-27
162.0d
0%
CO03YE0130
03Y Power/Control JB's, Tray, Cable, Termination
17-May-27
07-Aug-27
32.0d
0%
CO03YI0120
03Y Instrument JB's, Field Instr, Tray, Cable
17-May-27
07-Aug-27
32.0d
0%
WO010E0100
010 Above Ground Electrical
17-May-27
05-Oct-27
131.0d
0%
WO030E0100
030 Above Ground Electrical
17-May-27
23-Aug-27
153.0d
0%
WO030I0100
030 Install Instruments & Test
17-May-27
17-Jan-28
41.0d
0%
CO02KM0110
02K Set Static Equipment - Gen'l
17-May-27
07-Jun-27
101.0d
0%
CO04AK0110
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
WO04AK0100
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
CO02AV1110
02A Paint Fabricated Pipe Spools
20-May-27
02-Jun-27
172.0d
0%
CO02LM0130
02L Set (Heavy Lift) - 101-E (CO2 Absorber)
20-May-27
25-May-27
56.0d
0%
CK05BP0110
05B A/G Pipe Spool Fabrication
22-May-27
31-May-27
49.0d
0%
CO01YE0110
01Y Lighting JB's, Stands, Tray & Cable
22-May-27
02-Jul-27
175.0d
0%
CO02ES0110
02E Erect Structural Steel
22-May-27
11-Jun-27
127.0d
0%
CO02ES0120
02E Erect Misc Steel
22-May-27
11-Jun-27
67.0d
0%
CO02FS0120
02F Erect Misc Steel
22-May-27
11-Jun-27
133.0d
0%
CO02JS0110
02J Erect Structural Steel - Structure
22-May-27
04-Jun-27
98.0d
0%
CO02MS0120
02M Erect Misc Steel - Structure
22-May-27
11-Jun-27
123.0d
0%
CO03AS0120
03A Erect Misc Steel - Structure
22-May-27
18-Jun-27
56.0d
0%
CO03CS0120
03C Erect Misc Steel
22-May-27
11-Jun-27
87.0d
0%
CO03DS0120
03D Erect Misc Steel
22-May-27
18-Jun-27
98.0d
0%
CO03ES0120
03E Erect Misc Steel - Structure
22-May-27
18-Jun-27
58.0d
0%
CO02BV1110
02B Paint Fabricated Pipe Spools
25-May-27
31-May-27
175.0d
0%
CO03FP0130
03F LB Pipe Erection
25-May-27
02-Jul-27
88.0d
0%
CO02LM0140
02L Set (Heavy Lift) - 102-E (CO2 Stripper)
26-May-27
31-May-27
56.0d
0%
CO02GE0130
02G Power/Control JB's, Tray, Cable, Termination
26-May-27
02-Oct-27
108.0d
0%
CO02GI0120
02G Instrument JB's, Field Instr, Tray, Cable
26-May-27
02-Oct-27
108.0d
0%
WO020E0100
020 Above Ground Electrical
26-May-27
14-Feb-28
23.0d
0%
WO020I0100
020 Install Instruments & Test
26-May-27
01-Mar-28
9.0d
0%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO01CE0110
01C Lighting JB's, Stands, Tray & Cable
29-May-27
18-Jun-27
124.0d
0%
CO01YP0140
01Y SB Pipe Erection - Pipe Rack
29-May-27
23-Jul-27
39.0d
0%
CO02DM0110
02D Set Static Equipment
29-May-27
11-Jun-27
133.0d
0%
CO02DS0120
02D Erect Misc Steel
29-May-27
18-Jun-27
93.0d
0%
CO02EP0130
02E LB Pipe Erection
29-May-27
06-Nov-27
67.0d
0%
CO02HM0260
02H Compete Installation of Ducts (101-B)
29-May-27
23-Jul-27
175.0d
0%
CO03AP0130
03A LB Pipe Erection
29-May-27
07-Jul-27
56.0d
0%
CO03CP0130
03C LB Pipe Erection
29-May-27
07-Jul-27
87.0d
0%
CO03EP0130
03E LB Pipe Erection
29-May-27
30-Jul-27
58.0d
0%
CO03YV1120
03Y Paint Touch-up - Piping
29-May-27
23-Jul-27
175.0d
0%
CO05BV1110
05B Paint Fabricated Pipe Spools
29-May-27
07-Jun-27
214.0d
0%
CO02HM0215
02H Erect Fuel Gas Lines (101-B)
31-May-27
26-Jun-27
151.0d
0%
CO02HM0227
02H Install Spring Hangers & Align (101-B)
31-May-27
10-Jul-27
186.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO01CA0110
01C Erect - EDR Shelter
31-May-27
21-Jun-27
98.0d
0%
CO01AK0150
01A Excavate Evaporation Pond
01-Jun-27
12-Jul-27
54.0d
0%
CO02CE0130
02C Power/Control JB's, Tray, Cable, Termination
01-Jun-27
22-Oct-27
88.0d
0%
CO02CI0120
02C Instrument JB's, Field Instr, Tray, Cable
01-Jun-27
22-Oct-27
88.0d
0%
CO02JM0110
02J Set Static Equipment - Gen'l
01-Jun-27
11-Jun-27
98.0d
0%
CO02MM0130
02M Set (Heavy Lift) - 105-D (Ammonia Converter)
01-Jun-27
05-Jun-27
56.0d
0%
CO03FP0140
03F SB Pipe Erection
01-Jun-27
09-Jul-27
88.0d
0%
WO010K0100
010 Site Prep
01-Jun-27
28-Jan-28
37.0d
0%
CO01DE0110
01D Lighting JB's, Stands, Tray & Cable
02-Jun-27
13-Jul-27
66.0d
0%
CO03YP0150
03Y Punchlist / Test Piping
02-Jun-27
23-Jul-27
139.0d
0%
CO01BV1130
01B Paint Touch-up - Equipment
03-Jun-27
25-Jun-27
100.0d
0%
PO05AS0000
05A Recv at Site - Structural Steel
04-Jun-27
04-Jun-27
23.0d
0%
PO05AS0010
05A Recv at Site - Misc Steel
04-Jun-27
04-Jun-27
27.0d
0%
CO02AM0110
02A Set Static Equipment
05-Jun-27
18-Jun-27
144.0d
0%
CO02JS0120
02J Erect Misc Steel - Structure
05-Jun-27
11-Jun-27
98.0d
0%
CO02LE0110
02L Lighting JB's, Stands, Tray & Cable
05-Jun-27
16-Jul-27
163.0d
0%
CO03AP0140
03A SB Pipe Erection
05-Jun-27
14-Jul-27
56.0d
0%
CO03CP0140
03C SB Pipe Erection
05-Jun-27
14-Jul-27
87.0d
0%
CO03EP0140
03E SB Pipe Erection
05-Jun-27
06-Aug-27
58.0d
0%
CO03FV2110
03F Insulate - Equipment
05-Jun-27
19-Jun-27
135.0d
0%
WO030V2100
030 Insulation
05-Jun-27
02-Oct-27
133.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02MM0140
02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.)
07-Jun-27
11-Jun-27
56.0d
0%
CO03DP0130
03D LB Pipe Erection
07-Jun-27
25-Jun-27
98.0d
0%
CO01CP0130
01C LB Pipe Erection
07-Jun-27
28-Jun-27
93.0d
0%
CO02KS0120
02K Erect Misc Steel
07-Jun-27
28-Jun-27
101.0d
0%
CO01DV1130
01D Paint Touch-up - Equipment
08-Jun-27
25-Jun-27
88.0d
0%
CO03FE0130
03F Power/Control JB's, Tray, Cable, Termination
08-Jun-27
16-Jul-27
97.0d
0%
CO03FI0120
03F Instrument JB's, Field Instr, Tray, Cable
08-Jun-27
16-Jul-27
97.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO01BP0130
01B LB Pipe Erection
12-Jun-27
21-Sep-27
32.0d
0%
CO01DP0130
01D LB Pipe Erection
12-Jun-27
13-Aug-27
34.0d
0%
CO01HE0110
01H Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
69.0d
0%
CO02AS0120
02A Erect Misc Steel
12-Jun-27
02-Jul-27
103.0d
0%
CO02BE0110
02B Lighting JB's, Stands, Tray & Cable
12-Jun-27
25-Jun-27
193.0d
0%
CO02EE0110
02E Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02EM0110
02E Set Static Equipment
12-Jun-27
09-Jul-27
127.0d
0%
CO02FE0110
02F Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02JE0110
02J Lighting JB's, Stands, Tray & Cable
12-Jun-27
23-Jul-27
157.0d
0%
CO02JP0130
02J LB Pipe Erection
12-Jun-27
27-Sep-27
98.0d
0%
CO02ME0110
02M Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02MV1130
02M Paint Touch-up - Equipment
12-Jun-27
29-Jun-27
172.0d
0%
CO02NM0110
02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller)
12-Jun-27
17-Jun-27
56.0d
0%
CO03AE0130
03A Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
56.0d
0%
CO03AI0120
03A Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
56.0d
0%
CO03BE0110
03B Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
187.0d
0%
CO03CE0130
03C Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
87.0d
0%
CO03CI0120
03C Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
87.0d
0%
CO03EE0130
03E Power/Control JB's, Tray, Cable, Termination
12-Jun-27
13-Aug-27
61.0d
0%
CO03EI0120
03E Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
13-Aug-27
61.0d
0%
PO05BS0010
05B Recv at Site - Misc Steel
12-Jun-27
12-Jun-27
87.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO03CE0120
03C Lighting Fixture Installation/Termination
14-Jun-27
26-Jun-27
123.0d
0%
CO01CP0140
01C SB Pipe Erection
14-Jun-27
05-Jul-27
93.0d
0%
CO02PM0110
02P Set 101-U Dearator
15-Jun-27
28-Jun-27
103.0d
0%
CO02QM0110
02Q Set 101-F Steam Drum
15-Jun-27
21-Jun-27
101.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO03DP0140
03D SB Pipe Erection
15-Jun-27
05-Jul-27
97.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%
CO05AU3110
05A U/G Earthing Installation
17-Jun-27
14-Jul-27
77.0d
0%
CO05UP0150
05U LB Pipe Erection (Firewater Piping)
17-Jun-27
30-Sep-27
135.0d
0%
WO050U3100
050 Install U/G Electrical
17-Jun-27
14-Jul-27
77.0d
0%
CO02NS0120
02N Erect Misc Steel
18-Jun-27
22-Jul-27
56.0d
0%
CO01BP0140
01B SB Pipe Erection
19-Jun-27
28-Sep-27
32.0d
0%
CO01CE0120
01C Lighting Fixture Installation/Termination
19-Jun-27
25-Jun-27
124.0d
0%
CO01DP0140
01D SB Pipe Erection
19-Jun-27
27-Aug-27
34.0d
0%
CO01HE0140
01H Set Transformers TR-100/ 103/ 104/ 105
19-Jun-27
02-Jul-27
33.0d
0%
CO01YE0130
01Y Power/Control JB's, Tray, Cable, Termination
19-Jun-27
30-Jul-27
39.0d
0%
CO01YI0120
01Y Instrument JB's, Field Instr, Tray, Cable
19-Jun-27
30-Jul-27
39.0d
0%
CO01YV1120
01Y Paint Touch-up - Piping
19-Jun-27
30-Jul-27
169.0d
0%
CO02DE0110
02D Lighting JB's, Stands, Tray & Cable
19-Jun-27
16-Jul-27
169.0d
0%
CO02JP0140
02J SB Pipe Erection
19-Jun-27
04-Oct-27
98.0d
0%
CO02LM0110
02L Set Static Equipment - Gen'l
19-Jun-27
21-Jul-27
103.0d
0%
CO02LM0120
02L Set Static Equipment - 02L Structure
19-Jun-27
30-Jul-27
-15.0d
0%
CO03AE0110
03A Lighting JB's, Stands, Tray & Cable
19-Jun-27
09-Jul-27
75.0d
0%
WO010I0100
010 Install Instruments & Test
19-Jun-27
03-Jan-28
53.0d
0%
CO01CE0130
01C Power/Control JB's, Tray, Cable, Termination
21-Jun-27
12-Jul-27
100.0d
0%
CO01CI0120
01C Instrument JB's, Field Instr, Tray, Cable
21-Jun-27
12-Jul-27
100.0d
0%
CO01CV1120
01C Paint Touch-up - Piping
21-Jun-27
12-Jul-27
93.0d
0%
CO01CV1130
01C Paint Touch-up - Equipment
21-Jun-27
12-Jul-27
93.0d
0%
CO02QS0120
02Q Erect Misc Steel
22-Jun-27
12-Jul-27
101.0d
0%
CO03DI0120
03D Instrument JB's, Field Instr, Tray, Cable
22-Jun-27
12-Jul-27
100.0d
0%
CO01GC0130
01G Install Paving - Control Building
25-Jun-27
08-Jul-27
70.0d
0%
CO01GE0110
01G Lighting JB's, Stands, Tray & Cable
25-Jun-27
05-Aug-27
28.0d
0%
CO01GE0140
01G Install UPS in Control Building
25-Jun-27
15-Jul-27
-8.0d
0%
CO01GI0150
01G Install DCS
25-Jun-27
25-Aug-27
-14.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02NP0130
02N LB Pipe Erection
25-Jun-27
10-Nov-27
56.0d
0%
CO01BE0130
01B Power/Control JB's, Tray, Cable, Termination
26-Jun-27
05-Oct-27
32.0d
0%
CO01BI0120
01B Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
05-Oct-27
32.0d
0%
CO01DE0130
01D Power/Control JB's, Tray, Cable, Termination
26-Jun-27
10-Sep-27
39.0d
0%
CO01DI0120
01D Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
10-Sep-27
39.0d
0%
CO02BE0120
02B Lighting Fixture Installation/Termination
26-Jun-27
02-Jul-27
193.0d
0%
CO01BE0120
01B Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO01EE0120
01E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
180.0d
0%
CO01FE0120
01F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
152.0d
0%
CO02MP0130
02M LB Pipe Erection
28-Jun-27
08-Oct-27
92.0d
0%
CO03BP0130
03B LB Pipe Erection
28-Jun-27
04-Aug-27
138.0d
0%
CO03DE0120
03D Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03EE0120
03E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03FE0120
03F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
111.0d
0%
CO03FP0150
03F Punchlist / Test Piping
28-Jun-27
16-Jul-27
88.0d
0%
CO02KE0110
02K Lighting JB's, Stands, Tray & Cable
28-Jun-27
09-Aug-27
144.0d
0%
CO02PS0120
02P Erect Misc Steel
29-Jun-27
26-Jul-27
103.0d
0%
CO02QP0130
02Q LB Pipe Erection
29-Jun-27
28-Sep-27
101.0d
0%
CO02YE0110
02Y Lighting JB's, Stands, Tray & Cable
29-Jun-27
12-Oct-27
90.0d
0%
CO03YV2120
03Y Insulate - Piping
30-Jun-27
03-Sep-27
148.0d
0%
CO01BV2110
01B Insulate - Equipment
01-Jul-27
23-Jul-27
100.0d
0%
CO05AM0145
05A Tank Erection 2101-F (Ammonia Storage Tank)
01-Jul-27
25-Feb-28
-51.0d
0%
WO010V2100
010 Insulation
01-Jul-27
02-Nov-27
107.0d
0%
WT050M0100
05A Tank Erection
01-Jul-27
09-Mar-28
-51.0d
0%
CO01CP0150
01C Punchlist / Test Piping
01-Jul-27
12-Jul-27
96.0d
0%
CO02JE0130
02J Power/Control JB's, Tray, Cable, Termination
02-Jul-27
11-Oct-27
98.0d
0%
CO02JI0120
02J Instrument JB's, Field Instr, Tray, Cable
02-Jul-27
11-Oct-27
98.0d
0%
CO03AP0150
03A Punchlist / Test Piping
02-Jul-27
21-Jul-27
62.0d
0%
CO03CP0150
03C Punchlist / Test Piping
02-Jul-27
21-Jul-27
87.0d
0%
CO03DP0150
03D Punchlist / Test Piping
02-Jul-27
12-Jul-27
97.0d
0%
CO01HE0120
01H Lighting Fixture Installation/Termination
03-Jul-27
16-Jul-27
69.0d
0%
CO01HE0130
01H Power/Control JB's, Tray, Cable, Termination
03-Jul-27
10-Sep-27
33.0d
0%
CO01YE0120
01Y Lighting Fixture Installation/Termination
03-Jul-27
23-Jul-27
175.0d
0%
CO01YP0150
01Y Punchlist / Test Piping - Pipe Rack
03-Jul-27
30-Jul-27
133.0d
0%
CO02AE0110
02A Lighting JB's, Stands, Tray & Cable
03-Jul-27
30-Jul-27
157.0d
0%
CO02EV1130
02E Paint Touch-up - Equipment
03-Jul-27
23-Jul-27
151.0d
0%
CO03BE0120
03B Lighting Fixture Installation/Termination
03-Jul-27
09-Jul-27
187.0d
0%
CO02FP0130
02F LB Pipe Erection
05-Jul-27
27-Sep-27
102.0d
0%
CO03BP0140
03B SB Pipe Erection
05-Jul-27
11-Aug-27
138.0d
0%
CO01DV2110
01D Insulate - Equipment
06-Jul-27
23-Jul-27
88.0d
0%
CO02GE0110
02G Lighting JB's, Stands, Tray & Cable
06-Jul-27
18-Aug-27
149.0d
0%
CO02PP0130
02P LB Pipe Erection
06-Jul-27
21-Sep-27
103.0d
0%
CO03FV1120
03F Paint Touch-up - Piping
06-Jul-27
16-Jul-27
112.0d
0%
CO03DV1120
03D Paint Touch-up - Piping
06-Jul-27
12-Jul-27
111.0d
0%
CO01CV2120
01C Insulate - Piping
08-Jul-27
29-Jul-27
96.0d
0%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO02EE0120
02E Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02FE0120
02F Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02ME0120
02M Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO03AE0120
03A Lighting Fixture Installation/Termination
10-Jul-27
16-Jul-27
75.0d
0%
CO03AV1120
03A Paint Touch-up - Piping
10-Jul-27
21-Jul-27
58.0d
0%
CO03AV1130
03A Paint Touch-up - Equipment
10-Jul-27
21-Jul-27
58.0d
0%
CO03CV1120
03C Paint Touch-up - Piping
10-Jul-27
21-Jul-27
102.0d
0%
CO02DP0130
02D LB Pipe Erection
12-Jul-27
22-Oct-27
62.0d
0%
CO02FP0140
02F SB Pipe Erection
12-Jul-27
04-Oct-27
102.0d
0%
CO03BE0130
03B Power/Control JB's, Tray, Cable, Termination
12-Jul-27
23-Aug-27
138.0d
0%
CO03BI0120
03B Instrument JB's, Field Instr, Tray, Cable
12-Jul-27
23-Aug-27
138.0d
0%
CO01CI0130
01C Install In Line Instruments
12-Jul-27
15-Jul-27
96.0d
0%
CO01CV2110
01C Insulate - Equipment
12-Jul-27
02-Aug-27
93.0d
0%
CO02KP0130
02K LB Pipe Erection
12-Jul-27
23-Oct-27
77.0d
0%
CO03DI0130
03D Install In Line Instruments
12-Jul-27
14-Jul-27
97.0d
0%
CO01AE0110
01A Lighting JB's, Stands, Tray & Cable
13-Jul-27
26-Jul-27
91.0d
0%
CO01AK0160
01A Install Liner at Evaporation Pond
13-Jul-27
18-Aug-27
54.0d
0%
CO01JC0150
01K Excavate Pond
13-Jul-27
09-Aug-27
55.0d
0%
CO02QE0110
02Q Lighting JB's, Stands, Tray & Cable
13-Jul-27
19-Jul-27
162.0d
0%
CO01DE0120
01D Lighting Fixture Installation/Termination
14-Jul-27
03-Aug-27
66.0d
0%
CO03EP0150
03E Punchlist / Test Piping
14-Jul-27
13-Aug-27
58.0d
0%
CO05AM0155
05A Tank Erection 2102-F (Ammonia Storage Tank)
14-Jul-27
09-Mar-28
-51.0d
0%
CO03AV2120
03A Insulate - Piping
16-Jul-27
30-Jul-27
63.0d
0%
CO02GP0150
02G Punchlist / Test Piping
16-Jul-27
02-Oct-27
105.0d
0%
CO02DE0120
02D Lighting Fixture Installation/Termination
17-Jul-27
30-Jul-27
169.0d
0%
CO02LE0120
02L Lighting Fixture Installation/Termination
17-Jul-27
06-Aug-27
163.0d
0%
CO02LP0130
02L LB Pipe Erection
17-Jul-27
31-Jan-28
-15.0d
0%
CO02LV1130
02L Paint Touch-up - Equipment
17-Jul-27
28-Sep-27
69.0d
0%
CO03FI0130
03F Install In Line Instruments
17-Jul-27
20-Jul-27
97.0d
0%
CO01ET0110
01E Mechanical Completion
17-Jul-27
17-Jul-27
180.0d
0%
CO01FT0110
01F Mechanical Completion
17-Jul-27
17-Jul-27
152.0d
0%
SC01ET0120
01E RFSU
17-Jul-27
17-Jul-27
239.0d
0%
SC01FT0120
01F RFSU
17-Jul-27
17-Jul-27
239.0d
0%
CO02AP0130
02A LB Pipe Erection
19-Jul-27
23-Oct-27
78.0d
0%
CO02BP0130
02B LB Pipe Erection
19-Jul-27
16-Aug-27
120.0d
0%
CO02KP0140
02K SB Pipe Erection
19-Jul-27
30-Oct-27
77.0d
0%
CO02QE0120
02Q Lighting Fixture Installation/Termination
20-Jul-27
26-Jul-27
173.0d
0%
CO02YE0130
02Y Power/Control JB's, Tray, Cable, Termination
20-Jul-27
16-Nov-27
-35.0d
0%
CO02YI0120
02Y Instrument JB's, Field Instr, Tray, Cable
20-Jul-27
16-Nov-27
-35.0d
0%
CO02FE0130
02F Power/Control JB's, Tray, Cable, Termination
22-Jul-27
11-Oct-27
104.0d
0%
CO02FI0120
02F Instrument JB's, Field Instr, Tray, Cable
22-Jul-27
11-Oct-27
104.0d
0%
CO03AI0130
03A Install In Line Instruments
22-Jul-27
24-Jul-27
62.0d
0%
CO03AV2110
03A Insulate - Equipment
22-Jul-27
05-Aug-27
58.0d
0%
CO03CI0130
03C Install In Line Instruments
22-Jul-27
24-Jul-27
87.0d
0%
CO02NE0110
02N Lighting JB's, Stands, Tray & Cable
23-Jul-27
12-Aug-27
152.0d
0%
CO02NV1130
02N Paint Touch-up - Equipment
23-Jul-27
29-Jul-27
146.0d
0%
CO02JE0120
02J Lighting Fixture Installation/Termination
24-Jul-27
13-Aug-27
157.0d
0%
CO02LP0140
02L SB Pipe Erection
24-Jul-27
07-Feb-28
-15.0d
0%
CO03YI0130
03Y Install In Line Instruments
24-Jul-27
27-Aug-27
139.0d
0%
CO02HM0275
02H Complete Primary Reformer Erection (101-B)
24-Jul-27
24-Jul-27
174.0d
0%
CO02AP0140
02A SB Pipe Erection
26-Jul-27
30-Oct-27
78.0d
0%
CO01AE0120
01A Lighting Fixture Installation/Termination
27-Jul-27
02-Aug-27
91.0d
0%
CO02HP0130
02H LB Pipe Erection
27-Jul-27
05-Jan-28
10.0d
0%
CO02MP0140
02M SB Pipe Erection
27-Jul-27
15-Oct-27
92.0d
0%
CO02PE0110
02P Lighting JB's, Stands, Tray & Cable
27-Jul-27
02-Aug-27
150.0d
0%
CO02YV1120
02Y Paint Touch-up - Piping
27-Jul-27
09-Nov-27
101.0d
0%
CO02YV1130
02Y Paint Touch-up - Pipe Rack
27-Jul-27
09-Nov-27
101.0d
0%
CO03EV1120
03E Paint Touch-up - Piping
27-Jul-27
13-Aug-27
58.0d
0%
CO03EV1130
03E Paint Touch-up - Equipment
27-Jul-27
13-Aug-27
58.0d
0%
CO01DP0150
01D Punchlist / Test Piping
28-Jul-27
10-Sep-27
34.0d
0%
CO02CP0150
02C Punchlist / Test Piping
28-Jul-27
22-Oct-27
83.0d
0%
CO02HM0120
02H Set (Heavey Lift) - 101-C & 102-C
30-Jul-27
04-Aug-27
10.0d
0%
CO03FV2120
03F Insulate - Piping
30-Jul-27
13-Aug-27
88.0d
0%
CO02GV1130
02G Paint Touch-up - Equipment
30-Jul-27
25-Sep-27
116.0d
0%
CO02KE0130
02K Power/Control JB's, Tray, Cable, Termination
30-Jul-27
06-Nov-27
77.0d
0%
CO02KI0120
02K Instrument JB's, Field Instr, Tray, Cable
30-Jul-27
06-Nov-27
77.0d
0%
CO01YI0130
01Y Install In Line Instruments
31-Jul-27
27-Aug-27
139.0d
0%
CO01YV2120
01Y Insulate - Piping
31-Jul-27
02-Oct-27
133.0d
0%
CO02AE0120
02A Lighting Fixture Installation/Termination
31-Jul-27
13-Aug-27
157.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO03BP0150
03B Punchlist / Test Piping
31-Jul-27
23-Aug-27
138.0d
0%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BM0110
05B Install Loading Arm
02-Aug-27
04-Dec-27
62.0d
0%
WO050M0100
050 Major Equipment
02-Aug-27
04-Dec-27
61.0d
0%
CO02CE0110
02C Lighting JB's, Stands, Tray & Cable
03-Aug-27
05-Oct-27
113.0d
0%
CO02GE0120
02G Lighting Fixture Installation/Termination
03-Aug-27
01-Sep-27
149.0d
0%
CO02HP0140
02H SB Pipe Erection
03-Aug-27
12-Jan-28
10.0d
0%
CO02PE0120
02P Lighting Fixture Installation/Termination
03-Aug-27
09-Aug-27
161.0d
0%
CO01BP0150
01B Punchlist / Test Piping
05-Aug-27
05-Oct-27
32.0d
0%
CO020M0130
Demobilize Heavy Lift Crane
05-Aug-27
16-Aug-27
56.0d
0%
CO02HS0110
02H Erect Structural Steel - Structure
05-Aug-27
07-Oct-27
10.0d
0%
CO01GE0120
01G Lighting Fixture Installation/Termination
06-Aug-27
08-Sep-27
28.0d
0%
CO02GV1120
02G Paint Touch-up - Piping
06-Aug-27
02-Oct-27
134.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
CO02AE0130
02A Power/Control JB's, Tray, Cable, Termination
07-Aug-27
06-Nov-27
78.0d
0%
CO02AI0120
02A Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
06-Nov-27
78.0d
0%
CO02ME0130
02M Power/Control JB's, Tray, Cable, Termination
07-Aug-27
22-Oct-27
95.0d
0%
CO02MI0120
02M Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
22-Oct-27
95.0d
0%
CO03BV1120
03B Paint Touch-up - Piping
07-Aug-27
23-Aug-27
153.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO02BP0140
02B SB Pipe Erection
09-Aug-27
30-Aug-27
120.0d
0%
CO02JP0150
02J Punchlist / Test Piping
09-Aug-27
11-Oct-27
102.0d
0%
CO02KE0120
02K Lighting Fixture Installation/Termination
09-Aug-27
21-Sep-27
144.0d
0%
CO01DV1120
01D Paint Touch-up - Piping
10-Aug-27
10-Sep-27
45.0d
0%
CO02YP0150
02Y Punchlist / Test Piping
10-Aug-27
09-Nov-27
65.0d
0%
CO02LE0130
02L Power/Control JB's, Tray, Cable, Termination
11-Aug-27
14-Feb-28
-12.0d
0%
CO02LI0120
02L Instrument JB's, Field Instr, Tray, Cable
11-Aug-27
14-Feb-28
-12.0d
0%
CO02NE0120
02N Lighting Fixture Installation/Termination
13-Aug-27
25-Aug-27
152.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02EP0140
02E SB Pipe Erection
16-Aug-27
13-Nov-27
67.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO03EI0130
03E Install In Line Instruments
16-Aug-27
25-Aug-27
65.0d
0%
CO01AM0150
01A Install Spray Devices
20-Aug-27
01-Sep-27
54.0d
0%
CO03EV2110
03E Insulate - Equipment
20-Aug-27
02-Oct-27
58.0d
0%
CO03EV2120
03E Insulate - Piping
20-Aug-27
02-Oct-27
58.0d
0%
CO02HE0130
02H Power/Control JB's, Tray, Cable, Termination
23-Aug-27
19-Jan-28
15.0d
0%
CO02HI0120
02H Instrument JB's, Field Instr, Tray, Cable
23-Aug-27
19-Jan-28
15.0d
0%
CO05AM0160
05A Tank Erection 2105-F (Fire Water Tank)
23-Aug-27
16-Oct-27
-29.0d
0%
CO02FP0150
02F Punchlist / Test Piping
25-Aug-27
11-Oct-27
102.0d
0%
CO03BI0130
03B Install In Line Instruments
25-Aug-27
30-Aug-27
138.0d
0%
CO01BV1120
01B Paint Touch-up - Piping
30-Aug-27
05-Oct-27
56.0d
0%
CO02BE0130
02B Power/Control JB's, Tray, Cable, Termination
30-Aug-27
20-Sep-27
136.0d
0%
CO02BI0120
02B Instrument JB's, Field Instr, Tray, Cable
30-Aug-27
20-Sep-27
136.0d
0%
CO02PP0140
02P SB Pipe Erection
30-Aug-27
28-Sep-27
103.0d
0%
CO02BP0150
02B Punchlist / Test Piping
01-Sep-27
20-Sep-27
120.0d
0%
CO02BV1120
02B Paint Touch-up - Piping
01-Sep-27
20-Sep-27
144.0d
0%
CO02CV1120
02C Paint Touch-up - Piping
01-Sep-27
22-Oct-27
116.0d
0%
CO01AE0130
01A Power/Control JB's, Tray, Cable, Termination
03-Sep-27
21-Sep-27
66.0d
0%
CO01AP0130
01A LB Pipe Erection
03-Sep-27
28-Sep-27
54.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02JV1120
02J Paint Touch-up - Piping
06-Sep-27
11-Oct-27
102.0d
0%
CO02JV1130
02J Paint Touch-up - Equipment
06-Sep-27
11-Oct-27
102.0d
0%
CO02EE0130
02E Power/Control JB's, Tray, Cable, Termination
08-Sep-27
26-Nov-27
67.0d
0%
CO02EI0120
02E Instrument JB's, Field Instr, Tray, Cable
08-Sep-27
26-Nov-27
67.0d
0%
CO02HV1130
02H Paint Touch-up - Equipment
10-Sep-27
28-Oct-27
52.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO01HT0110
01H Mechanical Completion
10-Sep-27
10-Sep-27
33.0d
0%
CO01DI0130
01D Install In Line Instruments
20-Sep-27
24-Sep-27
41.0d
0%
CO02QP0140
02Q SB Pipe Erection
20-Sep-27
05-Oct-27
101.0d
0%
CO02BI0130
02B Install In Line Instruments
21-Sep-27
22-Sep-27
130.0d
0%
CO02PI0120
02P Instrument JB's, Field Instr, Tray, Cable
21-Sep-27
05-Oct-27
121.0d
0%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
CO01DV2120
01D Insulate - Piping
23-Sep-27
16-Oct-27
34.0d
0%
CO02FV1120
02F Paint Touch-up - Piping
23-Sep-27
11-Oct-27
126.0d
0%
CO02HE0110
02H Lighting JB's, Stands, Tray & Cable
24-Sep-27
04-Nov-27
87.0d
0%
CO02MP0150
02M Punchlist / Test Piping
24-Sep-27
22-Oct-27
92.0d
0%
CO05BV1120
05B Paint Touch-up - Piping
27-Sep-27
05-Oct-27
170.0d
0%
CO02KP0150
02K Punchlist / Test Piping
27-Sep-27
06-Nov-27
80.0d
0%
CO02PP0150
02P Punchlist / Test Piping
28-Sep-27
05-Oct-27
107.0d
0%
CO02QI0120
02Q Instrument JB's, Field Instr, Tray, Cable
28-Sep-27
12-Oct-27
115.0d
0%
CO01AI0120
01A Instrument JB's, Field Instr, Tray, Cable
29-Sep-27
05-Oct-27
54.0d
0%
CO01AP0150
01A Punchlist / Test Piping
29-Sep-27
01-Oct-27
57.0d
0%
CO01AV1120
01A Paint Touch-up - Piping
29-Sep-27
01-Oct-27
58.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02PV1130
02P Paint Touch-up - Equipment
29-Sep-27
02-Oct-27
103.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02DP0140
02D SB Pipe Erection
30-Sep-27
25-Nov-27
62.0d
0%
CO02AP0150
02A Punchlist / Test Piping
01-Oct-27
06-Nov-27
79.0d
0%
CO02PV1120
02P Paint Touch-up - Piping
01-Oct-27
05-Oct-27
125.0d
0%
CO01AI0130
01A Install In Line Instruments
02-Oct-27
02-Oct-27
57.0d
0%
CO01BV2120
01B Insulate - Piping
02-Oct-27
02-Nov-27
32.0d
0%
CO02GI0130
02G Install In Line Instruments
02-Oct-27
13-Oct-27
105.0d
0%
CO02QP0150
02Q Punchlist / Test Piping
05-Oct-27
12-Oct-27
101.0d
0%
CO04AT0110
04A Mechanical Completion
05-Oct-27
05-Oct-27
108.0d
0%
CO01BI0130
01B Install In Line Instruments
06-Oct-27
13-Oct-27
37.0d
0%
CO01GI0120
01G DCS Cable Terminations
06-Oct-27
06-Dec-27
-35.0d
0%
CO02CE0120
02C Lighting Fixture Installation/Termination
06-Oct-27
26-Oct-27
113.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02MV1120
02M Paint Touch-up - Piping
06-Oct-27
22-Oct-27
116.0d
0%
CO02PI0130
02P Install In Line Instruments
06-Oct-27
06-Oct-27
118.0d
0%
CO02QV1120
02Q Paint Touch-up - Piping
06-Oct-27
09-Oct-27
121.0d
0%
CO02QV1130
02Q Paint Touch-up - Equipment
06-Oct-27
09-Oct-27
121.0d
0%
CO02DE0130
02D Power/Control JB's, Tray, Cable, Termination
11-Oct-27
02-Dec-27
68.0d
0%
CO02DI0120
02D Instrument JB's, Field Instr, Tray, Cable
11-Oct-27
02-Dec-27
68.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FI0130
02F Install In Line Instruments
12-Oct-27
16-Oct-27
109.0d
0%
CO02JI0130
02J Install In Line Instruments
12-Oct-27
19-Oct-27
104.0d
0%
CO02QI0130
02Q Install In Line Instruments
13-Oct-27
13-Oct-27
112.0d
0%
CO02YE0120
02Y Lighting Fixture Installation/Termination
13-Oct-27
27-Nov-27
90.0d
0%
CO02KV1120
02K Paint Touch-up - Piping
13-Oct-27
06-Nov-27
104.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02AV1120
02A Paint Touch-up - Piping
16-Oct-27
06-Nov-27
103.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
SC01HT0120
01H RFSU
17-Oct-27
17-Oct-27
10.0d
0%
CO02EP0150
02E Punchlist / Test Piping
18-Oct-27
26-Nov-27
67.0d
0%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
CO05BI0120
05B Instrument JB's, Field Instr, Tray, Cable
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
WO050I0100
050 Install Instruments & Test
19-Oct-27
25-Mar-28
24.0d
0%
CO02CI0130
02C Install In Line Instruments
23-Oct-27
04-Nov-27
83.0d
0%
CO02MI0130
02M Install In Line Instruments
23-Oct-27
28-Oct-27
99.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO05AM0110
05A Set 2202-B Flare & KO Drum
28-Oct-27
04-Dec-27
21.0d
0%
CO05AM0130
05A Set 2101-L Ammonia Refrigeration Package
28-Oct-27
30-Oct-27
46.0d
0%
CO05AM0150
05A Set Rotating Equipment
28-Oct-27
17-Nov-27
31.0d
0%
CO010K0130
010 Compl Roads, Ditches, Paving, & Rock Surfacing
01-Nov-27
28-Jan-28
9.0d
0%
CO010K0140
010 Finish Grading
01-Nov-27
28-Jan-28
37.0d
0%
CO020K0100
020 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
CO02EV1120
02E Paint Touch-up - Piping
01-Nov-27
26-Nov-27
91.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
CO030K0100
030 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
WO020K0100
020 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
WO030K0100
030 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
CO02DP0150
02D Punchlist / Test Piping
02-Nov-27
02-Dec-27
62.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
SC04AT0120
04A RFSU
02-Nov-27
02-Nov-27
132.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02HE0120
02H Lighting Fixture Installation/Termination
05-Nov-27
01-Dec-27
87.0d
0%
CO02KI0130
02K Install In Line Instruments
06-Nov-27
15-Nov-27
83.0d
0%
CO02AI0130
02A Install In Line Instruments
08-Nov-27
13-Nov-27
84.0d
0%
CO02NP0140
02N SB Pipe Erection
08-Nov-27
17-Nov-27
56.0d
0%
CO02YI0130
02Y Install In Line Instruments
10-Nov-27
13-Dec-27
65.0d
0%
CO02HP0150
02H Punchlist / Test Piping
11-Nov-27
19-Jan-28
10.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO02DV1120
02D Paint Touch-up - Piping
12-Nov-27
02-Dec-27
86.0d
0%
CO02NE0130
02N Power/Control JB's, Tray, Cable, Termination
15-Nov-27
30-Nov-27
80.0d
0%
CO02NI0120
02N Instrument JB's, Field Instr, Tray, Cable
15-Nov-27
30-Nov-27
80.0d
0%
CO02LP0150
02L Punchlist / Test Piping
16-Nov-27
14-Feb-28
-15.0d
0%
CO02NV1120
02N Paint Touch-up - Piping
18-Nov-27
30-Nov-27
88.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AI0120
05A Instrument JB's, Field Instr, Tray, Cable
18-Nov-27
14-Mar-28
-25.0d
0%
CO02NP0150
02N Punchlist / Test Piping
26-Nov-27
30-Nov-27
56.0d
0%
CO02EI0130
02E Install In Line Instruments
27-Nov-27
03-Dec-27
73.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02NI0130
02N Install In Line Instruments
01-Dec-27
01-Dec-27
75.0d
0%
CO02DI0130
02D Install In Line Instruments
03-Dec-27
07-Dec-27
70.0d
0%
CO01GT0110
01G Mechanical Completion
06-Dec-27
06-Dec-27
-35.0d
0%
SC01GT0120
01G RFSU
06-Dec-27
06-Dec-27
-47.0d
0%
CO01DI0140
01D Continuity Testing
07-Dec-27
11-Dec-27
-22.0d
0%
CO02GI0140
02G Continuity Testing
07-Dec-27
16-Dec-27
54.0d
0%
CO02YI0140
02Y Continuity Testing
07-Dec-27
03-Jan-28
53.0d
0%
CO03AI0140
03A Continuity Testing
07-Dec-27
09-Dec-27
-35.0d
0%
CO03YI0140
03Y Continuity Testing
07-Dec-27
17-Jan-28
41.0d
0%
CO05BI0140
05B Continuity Testing
07-Dec-27
07-Dec-27
118.0d
0%
SC02GI0150
02G Function Testing
07-Dec-27
09-Jan-28
63.0d
0%
WC000T1100
000 Commissioning
07-Dec-27
22-Sep-28
-59.0d
0%
CO03AT0110
03A Mechanical Completion
09-Dec-27
09-Dec-27
-26.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV1120
02H Paint Touch-up - Piping
10-Dec-27
19-Jan-28
45.0d
0%
CO03FI0140
03F Continuity Testing
10-Dec-27
13-Dec-27
-1.0d
0%
SC03AI0150
03A Function Testing
10-Dec-27
20-Dec-27
-47.0d
0%
CO01DT0110
01D Mechanical Completion
11-Dec-27
11-Dec-27
-22.0d
0%
SC01DI0150
01D Function Testing
12-Dec-27
29-Dec-27
-28.0d
0%
CO03FT0110
03F Mechanical Completion
13-Dec-27
13-Dec-27
8.0d
0%
CO01YI0140
01Y Continuity Testing
14-Dec-27
03-Jan-28
53.0d
0%
CO02AI0140
02A Continuity Testing
14-Dec-27
20-Dec-27
52.0d
0%
CO02BI0140
02B Continuity Testing
14-Dec-27
15-Dec-27
73.0d
0%
SC03FI0150
03F Function Testing
14-Dec-27
24-Dec-27
-2.0d
0%
CO02KI0140
02K Continuity Testing
15-Dec-27
22-Dec-27
48.0d
0%
CO02BT0110
02B Mechanical Completion
15-Dec-27
15-Dec-27
75.0d
0%
CO02DI0140
02D Continuity Testing
16-Dec-27
20-Dec-27
59.0d
0%
SC02BI0150
02B Function Testing
16-Dec-27
18-Dec-27
85.0d
0%
CO02GT0110
02G Mechanical Completion
16-Dec-27
16-Dec-27
74.0d
0%
CO02CI0140
02C Continuity Testing
17-Dec-27
29-Dec-27
41.0d
0%
SC02CI0150
02C Function Testing
17-Dec-27
24-Jan-28
48.0d
0%
SC02YI0150
02Y Function Testing
18-Dec-27
10-Jan-28
62.0d
0%
SC02BT0120
02B RFSU
18-Dec-27
18-Dec-27
85.0d
0%
CO02AT0110
02A Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02DT0110
02D Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
SC03AT0120
03A RFSU
20-Dec-27
20-Dec-27
-47.0d
0%
CO01BI0140
01B Continuity Testing
21-Dec-27
28-Dec-27
-29.0d
0%
CO01CI0140
01C Continuity Testing
21-Dec-27
23-Dec-27
-12.0d
0%
CO02EI0140
02E Continuity Testing
21-Dec-27
27-Dec-27
47.0d
0%
CO02JI0140
02J Continuity Testing
21-Dec-27
28-Dec-27
42.0d
0%
CO02MI0140
02M Continuity Testing
21-Dec-27
25-Dec-27
51.0d
0%
CO03BI0140
03B Continuity Testing
21-Dec-27
23-Dec-27
59.0d
0%
SC02AI0150
02A Function Testing
21-Dec-27
12-Jan-28
60.0d
0%
SC02DI0150
02D Function Testing
21-Dec-27
04-Jan-28
68.0d
0%
SC03AT0130
03A Commission
21-Dec-27
27-Dec-27
-47.0d
0%
CO02NI0140
02N Continuity Testing
22-Dec-27
22-Dec-27
67.0d
0%
CO02KT0110
02K Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02NT0110
02N Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02PI0140
02P Continuity Testing
23-Dec-27
23-Dec-27
64.0d
0%
SC02KI0150
02K Function Testing
23-Dec-27
16-Jan-28
56.0d
0%
SC02NI0150
02N Function Testing
23-Dec-27
25-Dec-27
78.0d
0%
CO01CT0110
01C Mechanical Completion
23-Dec-27
23-Dec-27
-7.0d
0%
CO02PT0110
02P Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO03BT0110
03B Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02QI0140
02Q Continuity Testing
24-Dec-27
24-Dec-27
63.0d
0%
CO03CI0140
03C Continuity Testing
24-Dec-27
27-Dec-27
-19.0d
0%
SC01CI0150
01C Function Testing
24-Dec-27
29-Dec-27
-14.0d
0%
SC01YI0150
01Y Function Testing
24-Dec-27
10-Jan-28
62.0d
0%
SC02PI0150
02P Function Testing
24-Dec-27
28-Dec-27
75.0d
0%
SC03BI0150
03B Function Testing
24-Dec-27
03-Jan-28
69.0d
0%
CO02QT0110
02Q Mechanical Completion
24-Dec-27
24-Dec-27
67.0d
0%
SC03FT0120
03F RFSU
24-Dec-27
24-Dec-27
-2.0d
0%
CO02LV1120
02L Paint Touch-up - Piping
25-Dec-27
14-Feb-28
23.0d
0%
SC02QI0150
02Q Function Testing
25-Dec-27
29-Dec-27
74.0d
0%
CO02MT0110
02M Mechanical Completion
25-Dec-27
25-Dec-27
66.0d
0%
SC02MI0150
02M Function Testing
26-Dec-27
12-Jan-28
60.0d
0%
CO02ET0110
02E Mechanical Completion
27-Dec-27
27-Dec-27
65.0d
0%
CO03CT0110
03C Mechanical Completion
27-Dec-27
27-Dec-27
-10.0d
0%
CO01AI0140
01A Continuity Testing
28-Dec-27
28-Dec-27
-12.0d
0%
CO02FI0140
02F Continuity Testing
28-Dec-27
01-Jan-28
44.0d
0%
CO03DI0140
03D Continuity Testing
28-Dec-27
29-Dec-27
-17.0d
0%
SC01DT0130
01D Commission
28-Dec-27
07-Feb-28
-47.0d
0%
SC02EI0150
02E Function Testing
28-Dec-27
17-Jan-28
55.0d
0%
SC03CI0150
03C Function Testing
28-Dec-27
07-Jan-28
-23.0d
0%
CO01AT0110
01A Mechanical Completion
28-Dec-27
28-Dec-27
-12.0d
0%
CO01BT0110
01B Mechanical Completion
28-Dec-27
28-Dec-27
-11.0d
0%
CO02JT0110
02J Mechanical Completion
28-Dec-27
28-Dec-27
64.0d
0%
SC02PT0120
02P RFSU
28-Dec-27
28-Dec-27
75.0d
0%
SC01AI0150
01A Function Testing
29-Dec-27
29-Dec-27
-14.0d
0%
SC01BI0150
01B Function Testing
29-Dec-27
19-Jan-28
-35.0d
0%
SC02JI0150
02J Function Testing
29-Dec-27
23-Jan-28
49.0d
0%
CO02CT0110
02C Mechanical Completion
29-Dec-27
29-Dec-27
63.0d
0%
CO03DT0110
03D Mechanical Completion
29-Dec-27
29-Dec-27
-12.0d
0%
SC01AT0120
01A RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01CT0120
01C RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01DT0120
01D RFSU
29-Dec-27
29-Dec-27
-28.0d
0%
SC02QT0120
02Q RFSU
29-Dec-27
29-Dec-27
74.0d
0%
CO03EI0140
03E Continuity Testing
30-Dec-27
04-Jan-28
-32.0d
0%
SC03DI0150
03D Function Testing
30-Dec-27
04-Jan-28
-20.0d
0%
SC03YI0150
03Y Function Testing
01-Jan-28
24-Jan-28
48.0d
0%
CO02FT0110
02F Mechanical Completion
01-Jan-28
01-Jan-28
60.0d
0%
SC02FI0150
02F Function Testing
02-Jan-28
20-Jan-28
52.0d
0%
CO01YT0110
01Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
CO02YT0110
02Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC03BT0120
03B RFSU
03-Jan-28
03-Jan-28
69.0d
0%
CO03ET0110
03E Mechanical Completion
04-Jan-28
04-Jan-28
-17.0d
0%
SC02DT0120
02D RFSU
04-Jan-28
04-Jan-28
68.0d
0%
SC03DT0120
03D RFSU
04-Jan-28
04-Jan-28
-20.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%
SC03EI0150
03E Function Testing
05-Jan-28
22-Jan-28
-38.0d
0%
SC02NT0120
02N RFSU
06-Jan-28
06-Jan-28
66.0d
0%
SC03CT0120
03C RFSU
07-Jan-28
07-Jan-28
-23.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05BV1130
05B Paint Touch-up - Equipment
08-Jan-28
18-Jan-28
62.0d
0%
SC02GT0120
02G RFSU
09-Jan-28
09-Jan-28
63.0d
0%
SC01YT0120
01Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02YT0120
02Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02AT0120
02A RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02MT0120
02M RFSU
12-Jan-28
12-Jan-28
60.0d
0%
CO02HI0140
02H Continuity Testing
14-Jan-28
26-Jan-28
15.0d
0%
SC02KT0120
02K RFSU
16-Jan-28
16-Jan-28
56.0d
0%
CO03YT0110
03Y Mechanical Completion
17-Jan-28
17-Jan-28
47.0d
0%
SC02ET0120
02E RFSU
17-Jan-28
17-Jan-28
55.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
SC01BT0120
01B RFSU
19-Jan-28
19-Jan-28
-35.0d
0%
CO02HI0130
02H Install In Line Instruments
20-Jan-28
01-Feb-28
10.0d
0%
SC02HI0150
02H Function Testing
20-Jan-28
29-Feb-28
12.0d
0%
SC02FT0120
02F RFSU
20-Jan-28
20-Jan-28
52.0d
0%
SC03ET0120
03E RFSU
22-Jan-28
22-Jan-28
-38.0d
0%
SC02JT0120
02J RFSU
23-Jan-28
23-Jan-28
49.0d
0%
CO05BI0130
05B Install In Line Instruments
24-Jan-28
25-Jan-28
68.0d
0%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
CO05BV2120
05B Insulate - Piping
24-Jan-28
14-Feb-28
63.0d
0%
WO050V2100
050 Insulation
24-Jan-28
10-May-28
-12.0d
0%
SC02CT0120
02C RFSU
24-Jan-28
24-Jan-28
48.0d
0%
SC03YT0120
03Y RFSU
24-Jan-28
24-Jan-28
48.0d
0%
CO05BV2110
05B Insulate - Equipment
25-Jan-28
15-Feb-28
62.0d
0%
CO02HI0145
02H Contingency (101-B)
27-Jan-28
23-Feb-28
15.0d
0%
CO02LI0140
02L Continuity Testing
05-Feb-28
21-Feb-28
-12.0d
0%
SC05BI0150
05B Function Testing
05-Feb-28
08-Feb-28
79.0d
0%
SC02LI0150
02L Function Testing
08-Feb-28
29-Mar-28
-17.0d
0%
SC03FT0130
03F Commission
08-Feb-28
28-Feb-28
-47.0d
0%
CO05AV1120
05A Paint Touch-up - Piping
10-Feb-28
14-Mar-28
-2.0d
0%
CO02LI0130
02L Install In Line Instruments
15-Feb-28
01-Mar-28
-15.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO02LT0110
02L Mechanical Completion
21-Feb-28
21-Feb-28
17.0d
0%
CO02HT0110
02H Mechanical Completion
23-Feb-28
23-Feb-28
15.0d
0%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
CO05AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO06AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
SC000T0100
020 Commission ISBL
29-Feb-28
28-Apr-28
-47.0d
0%
SC02HT0120
02H RFSU
29-Feb-28
29-Feb-28
12.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AI0140
05A Continuity Testing
10-Mar-28
21-Mar-28
-25.0d
0%
CO05AV1130
05A Paint Touch-up - Equipment
10-Mar-28
12-Apr-28
-51.0d
0%
CO05AI0130
05A Install In Line Instruments
15-Mar-28
25-Mar-28
-29.0d
0%
SC05AI0150
05A Function Testing
15-Mar-28
15-Apr-28
-34.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
CO05AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO06AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
SC02LT0120
02L RFSU
29-Mar-28
29-Mar-28
-17.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%
SC000T0105
020 Startup ISBL
11-May-28
24-Jun-28
-59.0d
0%
SC000T0110
Performance Test Period
25-Jun-28
22-Sep-28
-59.0d
0%
SC000YA100
Construction Bonus Period
23-Sep-28
15-Mar-29
-59.0d
0%
Jan 2025 Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Apr 2028 May 2028 Jun 2028 Jul 2028 Aug 2028 Sep 2028 Oct 2028 Nov 2028 Dec 2028 Jan 2029 Feb 2029 Mar 2029 Data Date
EK000CK065 — Compl. Layout of Temp. Facil. (including OCI) | 29-Jan-25 → 01-Oct-25 | Complete 100% | float — EK000CK065 EK000CK075 — Review Tech & Commercial Proposal - Field Fab Tank | 16-Feb-25 → 02-Oct-25 | Complete 100% | float — EK000CK075 EK000CK060 — Locate tie in pnts for temp water, phone, & pwr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK060 EK000CK100 — Site Visit - Construction | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CK100 EK000CK005 — OCI Subcontract - Executed | 19-Mar-25 → 19-Nov-25 | Complete 100% | float — EK000CK005 EK000CK010 — OCI Meeting to Define custom clearance requests | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK010 EK000CK015 — Define OCI's Point of Delivery & Liability | 20-May-25 → 19-Jun-25 | Complete 100% | float — EK000CK015 EK000CV038 — Select Geotech Vendor / Issue Award | 20-May-25 → 17-Aug-25 | Complete 100% | float — EK000CV038 PO000MF000 — Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP | 28-Jul-25 → 03-Jan-26 | Complete 100% | float — PO000MF000 EK000CV039 — Geotech Conducts Soil Borings / Draft Prelim Report | 24-Aug-25 → 17-Dec-25 | Complete 100% | float — EK000CV039 CO000GE105 — Commence Admin. Building Design (OCI) | 05-Oct-25 | Complete CO000K0106 — Mobilize Temporary Facilities (& Punchlist & Perm. Power) | 09-Nov-25 → 27-Dec-26 | In Progress 40% | float — CO000K0106 EK000GE150 — Execute OCI Subcontract (KBR) | 16-Nov-25 | Complete PO000C0045 — Purch/Fab/Deliver - Fencing Materials | 01-Dec-25 → 15-Dec-25 | Complete 100% | float — PO000C0045 EK000GE170 — Issue Material Supply PO to OCI (Elect, Struct, Insul) | 11-Dec-25 | Complete CK000YA306 — Establish Tax Free Zone Status | 13-Dec-25 → 31-Jan-26 | Complete 100% | float — CK000YA306 PO000C0050 — Receive at Site - Fencing Materials | 14-Dec-25 | Complete CO000C0150 — Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d CO000C0150 WO010K0110 — 010 Site Prep - Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d WO010K0110 PO000MF010 — Field Erected Tanks Subcontract - Purchasing & Fabrication | 04-Jan-26 → 27-Dec-26 | In Progress 31% | float — PO000MF010 CO000M0100 — Commence Engineering - Field Fab Tanks | 04-Jan-26 | Complete CO02HC0140 — 02H Form Pour Strip Fnds - Structure | 21-Mar-26 → 27-Dec-26 | In Progress 12% | float — CO02HC0140 WO020C0100 — 020 Concrete & Excavation | 21-Mar-26 → 23-Mar-27 | In Progress 9% | float 215.0d WO020C0100 CK01UU4150 — 01U U/G Pipe Spool Fabrication & Delivery (FW) HDPE | 24-Mar-26 → 16-Jan-27 | In Progress 10% | float 164.0d CK01UU4150 CK02UU4150 — 02U U/G Pipe Spool Fabrication & Delivery (FW) HDPE | 24-Mar-26 → 16-Jan-27 | In Progress 10% | float 164.0d CK02UU4150 CK03UU4150 — 03U U/G Pipe Spool Fabrication & Delivery (FW) HDPE | 24-Mar-26 → 16-Jan-27 | In Progress 10% | float 164.0d CK03UU4150 CK05UU4150 — 05U U/G Pipe Spool Fabrication & Delivery (FW) HDPE | 24-Mar-26 → 16-Jan-27 | In Progress 10% | float 318.0d CK05UU4150 CO000CK110 — Set-Up KBR Pipe Fab Shop | 24-Mar-26 → 27-Dec-26 | In Progress 11% | float — CO000CK110 WO010C0100 — 010 Concrete & Excavation | 27-Mar-26 → 04-May-27 | In Progress 7% | float 149.0d WO010C0100 CO01GC0150 — 01G Form, Pour, Strip Fnd - Control Building | 27-Mar-26 → 01-Apr-26 | Complete 100% | float — CO01GC0150 CO02JC0150 — 02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter) | 30-Mar-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0150 CO02JC0160 — 02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter) | 30-Mar-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0160 CO01DC0150 — 01D Form, Pour, Strip Fnd - 2101-U (Cooling Tower) | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — CO01DC0150 CO000A0110 — Start Buildings - Admin, Canteen, Warehouse, Control | 31-Mar-26 | Complete CO000K0100 — Start Construction | 31-Mar-26 | Complete CO02JC0110 — 02J Form, Pour, Strip Fnds - Major Fnds Gen'l | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — CO02JC0110 CO000A0150 — Install Guard Towers | 01-Apr-26 → 14-Apr-26 | Complete 100% | float — CO000A0150 CO01GA0115 — 01G Erect Control Building (Columns & Parapet Only) | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO01GA0115 CO02LC0150 — 02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber) | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02LC0150 CO02MC0110 — 02M Form, Pour, Strip Fnds - Major Fnds Gen'l | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02MC0110 CO02MC0140 — 02M Form Pour Strip Fnds - Structure | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — CO02MC0140 CO02KC0150 — 02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank) | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — CO02KC0150 CO03DC0110 — 03D Form, Pour, Strip Fnds - 2002-F (Demin Water Tank) | 06-Apr-26 → 27-Dec-26 | In Progress 7% | float — CO03DC0110 WO030C0100 — 030 Concrete & Excavation | 06-Apr-26 → 19-Mar-27 | In Progress 5% | float 229.0d WO030C0100 CO02BC0110 — 02B Form, Pour, Strip Fnds - Major Fnds | 09-Apr-26 → 27-Dec-26 | In Progress 6% | float — CO02BC0110 CO000K0108 — Start Foundations - Field Fab Tanks | 09-Apr-26 | Complete CO000K0110 — Start Foundations - Equipment & Piperacks | 09-Apr-26 | Complete CO010K0120 — 010 Construct Perimeter Roads | 15-Apr-26 → 28-Dec-26 | In Progress 5% | float — CO010K0120 CO02AC0110 — 02A Form, Pour, Strip Fnds - Major Fnds | 15-Apr-26 → 09-Mar-27 | In Progress 5% | float 189.0d CO02AC0110 CO01BC0160 — 01B Form, Pour, Strip Fnd - 2001-FB (Water Storage Tank) | 20-Apr-26 → 27-Dec-26 | In Progress 5% | float — CO01BC0160 CO02HC0150 — 02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer) | 21-Apr-26 → 27-Dec-26 | In Progress 5% | float — CO02HC0150 CO03CC0110 — 03C Form, Pour, Strip Fnds - Major Fnds | 21-Apr-26 → 27-Dec-26 | In Progress 5% | float — CO03CC0110 WK000U4100 — 000 U/G Pipe Spool Fabrication | 10-Aug-26 → 07-Dec-26 | Not Started 0% | float — WK000U4100 CO000M0110 — Mobilize Field Fab Tank Contractor | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO01BC0110 — 01B Form, Pour, Strip Fnds - Major Fnds Gen'l | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO01BC0150 — 01B Form, Pour, Strip Fnd - 2001-FA (Water Storage Tank) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO01DC0140 — 01D Form Pour Strip Fnds - Sleepers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO01YC0140 — 01Y Form Pour Strip Fnds - Pipe Rack | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02CC0160 — 02C Form, Pour, Strip Fnd - 103-JTC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02CM0140 — 02C Set - 103-JTC Surface Condenser | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02EC0110 — 02E Form, Pour, Strip Fnds - Major Fnds Gen'l | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02EC0140 — 02E Form Pour Strip Fnds - Structure | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02GC0160 — 02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux. | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HC0110 — 02H Form, Pour, Strip Fnds - 101B (Primary Reformer) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HC0160 — 02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02HM0140 — 02H Set - 156-F Steam Blowdown Drum | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02LC0160 — 02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02MC0150 — 02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02NC0110 — 02N Form, Pour, Strip Fnds - Major Fnds | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO02YC0140 — 02Y Form Pour Strip Fnds - Pipe Rack | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO03CM0110 — 03C Set Static Equipment - 2203/4-F Caustic, Sulfuric Acid Tanks | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO03DC0150 — 03D Form, Pour, Strip Fnd - 2002J/JA (Fresh Cooling Water Pumps) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO03FC0110 — 03F Form, Pour, Strip Fnds - Package Boiler | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CO05AC0170 — 05A Install Test Piles | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PO000P0015 — Purch/Fab/Delv - Temporary Testing Materials | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PO000P0020 — Receive at Site - Temporary Testing Materials | 27-Dec-26 | Not Started PO000V1000 — Purch/Fab/Delv - Painting Materials | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PO000V1005 — Receive at Site - Painting Materials | 27-Dec-26 | Not Started PO020EL155 — 020 Issue E&I Cable/Bulks/JB Reqn (OCI) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — CK000P0110 — 000 Pipe Fabrication | 28-Dec-26 → 31-May-27 | Not Started 0% | float 49.0d CK000P0110 CK000U4110 — Start Pipe Fab | 28-Dec-26 | Not Started CK01AP0110 — 01A A/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK01BU4110 — 01B U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK01CU4110 — 01C U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK01DP0110 — 01D A/G Pipe Spool Fabrication | 28-Dec-26 → 22-Mar-27 | Not Started 0% | float 104.0d CK01DP0110 CK01DU4110 — 01D U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK01EU4120 — 01E/F/G U/G Pipe Spool Fabrication (to Blg Stub Outs) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK01YP0110 — 01Y A/G Pipe Spool Fabrication | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 117.0d CK01YP0110 CK02AU4110 — 02A U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02BP0110 — 02B A/G Pipe Spool Fabrication | 28-Dec-26 → 24-May-27 | Not Started 0% | float 55.0d CK02BP0110 CK02BU4110 — 02B U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02CU4110 — 02C U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02DP0110 — 02D A/G Pipe Spool Fabrication | 28-Dec-26 → 30-Apr-27 | Not Started 0% | float 75.0d CK02DP0110 CK02DU4110 — 02D U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02EP0110 — 02E A/G Pipe Spool Fabrication | 28-Dec-26 → 25-Feb-27 | Not Started 0% | float 130.0d CK02EP0110 CK02EU4110 — 02E U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02FP0110 — 02F A/G Pipe Spool Fabrication | 28-Dec-26 → 20-Apr-27 | Not Started 0% | float 84.0d CK02FP0110 CK02FU4110 — 02F U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02GU4110 — 02G U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02HU4110 — 02H U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02JU4110 — 02J U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02KU4110 — 02K U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02LU4110 — 02L U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02MU4110 — 02M U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02NP0110 — 02N A/G Pipe Spool Fabrication | 28-Dec-26 → 27-Mar-27 | Not Started 0% | float 104.0d CK02NP0110 CK02PP0110 — 02P A/G Pipe Spool Fabrication | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 83.0d CK02PP0110 CK02UU4110 — 02U U/G Pipe Spool Fabrication (CW & Misc Headers) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK02YP0110 — 02Y A/G Pipe Spool Fabrication | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 27.0d CK02YP0110 CK03AU4110 — 03A U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03BU4110 — 03B U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03CP0110 — 03C A/G Pipe Spool Fabrication | 28-Dec-26 → 17-Feb-27 | Not Started 0% | float 137.0d CK03CP0110 CK03CU4110 — 03C U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03DU4110 — 03D U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03EU4110 — 03E U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03FU4110 — 03F U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CK03YP0110 — 03Y A/G Pipe Spool Fabrication | 28-Dec-26 → 06-Feb-27 | Not Started 0% | float 80.0d CK03YP0110 CK05AU4110 — 05A U/G Pipe Spool Fabrication | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO01AC0120 — 01A Form, Pour, Strip Fnds - Misc Fnds & Sumps... | 28-Dec-26 → 09-Jan-27 | Not Started 0% | float 247.0d CO01AC0120 CO01BC0120 — 01B Form, Pour, Strip Fnds - Misc Fnds | 28-Dec-26 → 06-Jan-27 | Not Started 0% | float 210.0d CO01BC0120 CO01BC0140 — 01B Form Pour Strip Fnds - Sleepers to Evap Pond | 28-Dec-26 → 27-Jan-27 | Not Started 0% | float 148.0d CO01BC0140 CO01BM0130 — 01B Tank Erection 2001-FA (Water Storage Tank) | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d CO01BM0130 CO01BM0140 — 01B Tank Erection 2001-FB (Water Storage Tank) | 28-Dec-26 → 25-Mar-27 | Not Started 0% | float 32.0d CO01BM0140 CO01DM0130 — 01D Erect 2101-U Cooling Tower | 28-Dec-26 → 04-May-27 | Not Started 0% | float 61.0d CO01DM0130 CO01GA0110 — 01G Erect Control Building (Continuation w/ Design Rev) | 28-Dec-26 → 24-Jun-27 | Not Started 0% | float -14.0d CO01GA0110 CO01HC0110 — 01H Form, Pour, Strip Piers - Substation Building | 28-Dec-26 → 06-Feb-27 | Not Started 0% | float 112.0d CO01HC0110 CO01YU3110 — 01Y U/G Earthing Installation - Pipe Rack | 28-Dec-26 → 06-Feb-27 | Not Started 0% | float 134.0d CO01YU3110 CO02AU4120 — 02A U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 222.0d CO02AU4120 CO02BU4120 — 02B U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 219.0d CO02BU4120 CO02CC0110 — 02C Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 26-Jan-27 | Not Started 0% | float 165.0d CO02CC0110 CO02CC0150 — 02C Form, Pour, Strip Fnd - 103/105-J & Table Tops | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02CM0110 — 02C Set Static Equipment - 128/167-C | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02CU4120 — 02C U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 162.0d CO02CU4120 CO02DC0110 — 02D Form, Pour, Strip Fnds - Major Fnds | 28-Dec-26 → 09-Jan-27 | Not Started 0% | float 252.0d CO02DC0110 CO02DU4120 — 02D U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 248.0d CO02DU4120 CO02EU4120 — 02E U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 227.0d CO02EU4120 CO02FC0110 — 02F Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 234.0d CO02FC0110 CO02FU4120 — 02F U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 234.0d CO02FU4120 CO02GC0150 — 02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops | 28-Dec-26 → 01-Feb-27 | Not Started 0% | float 134.0d CO02GC0150 CO02GM0140 — 02G Set/Install - 102-J Fd Gas Compr. & Aux. | 28-Dec-26 → 22-Apr-27 | Not Started 0% | float 188.0d CO02GM0140 CO02HU4120 — 02H U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 162.0d CO02HU4120 CO02JU4120 — 02J U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 211.0d CO02JU4120 CO02KC0110 — 02K Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 192.0d CO02KC0110 CO02KM0130 — 02K Tank Erection 114-F (Benfield Solution Tank) | 28-Dec-26 → 08-Jan-27 | Not Started 0% | float 97.0d CO02KM0130 CO02KU4120 — 02K U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 214.0d CO02KU4120 CO02LC0110 — 02L Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 123.0d CO02LC0110 CO02LC0140 — 02L Form Pour Strip Fnds - 02L Structure | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 45.0d CO02LC0140 CO02MU4120 — 02M U/G Piping Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 239.0d CO02MU4120 CO02UP0130 — 02U LB Pipe Erection (CW & Misc Headers) | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 71.0d CO02UP0130 CO02UV1110 — 02U Paint Fabricated Pipe Spools (CW & Misc Headers) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02YU3110 — 02Y U/G Earthing Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 100.0d CO02YU3110 CO03AC0110 — 03A Form, Pour, Strip Fnds - Major Fnds Gen'l | 28-Dec-26 → 16-Jan-27 | Not Started 0% | float 155.0d CO03AC0110 CO03BC0110 — 03B Form, Pour, Strip Fnds - Major Fnds (N/A) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO03BC0140 — 03B Form, Pour, Strip Fnds - 2401-A Wastewater Sump | 28-Dec-26 → 30-Dec-26 | Not Started 0% | float 266.0d CO03DM0145 — 03D Tank Erection 2002-F (Demin Water Tank) | 28-Dec-26 → 12-Jan-27 | Not Started 0% | float 105.0d CO03DM0145 CO03DU4120 — 03D U/G Piping Installation | 28-Dec-26 → 05-Jan-27 | Not Started 0% | float 199.0d CO03DU4120 CO03EC0110 — 03E Form, Pour, Strip Fnds - 2001-U Water Treatment | 28-Dec-26 → 20-Feb-27 | Not Started 0% | float 126.0d CO03EC0110 CO03FM0110 — 03F Erect 2002-U Package Boiler | 28-Dec-26 → 13-Mar-27 | Not Started 0% | float 159.0d CO03FM0110 CO03YC0110 — 03Y Form, Pour, Strip Fnds - Sleeper Fnds | 28-Dec-26 → 01-Jan-27 | Not Started 0% | float 98.0d CO03YC0110 CO03YC0120 — 03Y Form, Pour, Strip Fnds - Pipe Rack Fnds | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO04AV1100 — 04A Paint | 28-Dec-26 → 25-May-27 | Not Started 0% | float 148.0d CO04AV1100 CO05AC0175 — 05A Test Piles (Load Test) | 28-Dec-26 → 09-Jan-27 | Not Started 0% | float -51.0d CO05AC0175 P002YS0010 — 02Y Recv at Site - Structural Steel (First Shipment) | 28-Dec-26 | Not Started PO000E0000 — Purch/Fab/Deliver - A/G Electrical Bulks (First) | 28-Dec-26 → 10-Apr-27 | Not Started 0% | float 20.0d PO000E0000 PO000V2000 — Purch/Fab/Delv - Insulation Materials | 28-Dec-26 → 15-May-27 | Not Started 0% | float 98.0d PO000V2000 PO01BS0130 — 01B Fab & Ship Miscellaneous Steel | 28-Dec-26 → 26-Feb-27 | Not Started 0% | float 86.0d PO01BS0130 PO01DS0120 — 01D Fab & Ship Structural Steel | 28-Dec-26 → 19-Feb-27 | Not Started 0% | float 94.0d PO01DS0120 PO01DS0130 — 01D Fab & Ship Miscellaneous Steel | 28-Dec-26 → 19-Feb-27 | Not Started 0% | float 94.0d PO01DS0130 PO01EA0135 — 01E Guard House Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 200.0d PO01EA0135 PO01FA0135 — 01F Mosque Design Drawings - Submit to KBR | 28-Dec-26 → 02-Jan-27 | Not Started 0% | float 143.0d PO01FA0135 PO01HS0130 — 01H Fab & Ship Miscellaneous Steel | 28-Dec-26 → 09-Apr-27 | Not Started 0% | float 51.0d PO01HS0130 PO01YS0120 — 01Y Fab & Ship Structural Steel | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 39.0d PO01YS0120 PO02AS0120 — 02A Fab & Ship Structural Steel | 28-Dec-26 → 09-Apr-27 | Not Started 0% | float 103.0d PO02AS0120 PO02AS0130 — 02A Fab & Ship Miscellaneous Steel | 28-Dec-26 → 09-Apr-27 | Not Started 0% | float 115.0d PO02AS0130 PO02CS0130 — 02C Fab & Ship Miscellaneous Steel | 28-Dec-26 → 26-Mar-27 | Not Started 0% | float 83.0d PO02CS0130 PO02DS0120 — 02D Fab & Ship Structural Steel | 28-Dec-26 → 02-Apr-27 | Not Started 0% | float 93.0d PO02DS0120 PO02DS0130 — 02D Fab & Ship Miscellaneous Steel | 28-Dec-26 → 02-Apr-27 | Not Started 0% | float 105.0d PO02DS0130 PO02ES0120 — 02E Fab & Ship Structural Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 127.0d PO02ES0120 PO02ES0130 — 02E Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 67.0d PO02ES0130 PO02FS0130 — 02F Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 133.0d PO02FS0130 PO02HS0120 — 02H Fab & Ship Structural Steel | 28-Dec-26 → 26-Mar-27 | Not Started 0% | float 92.0d PO02HS0120 PO02HS0130 — 02H Fab & Ship Miscellaneous Steel | 28-Dec-26 → 26-Mar-27 | Not Started 0% | float 78.0d PO02HS0130 PO02JS0120 — 02J Fab & Ship Structural Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 98.0d PO02JS0120 PO02JS0130 — 02J Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 110.0d PO02JS0130 PO02LS0120 — 02L Fab & Ship Structural Steel | 28-Dec-26 → 05-Mar-27 | Not Started 0% | float -15.0d PO02LS0120 PO02LS0130 — 02L Fab & Ship Miscellaneous Steel | 28-Dec-26 → 05-Mar-27 | Not Started 0% | float 93.0d PO02LS0130 PO02MS0120 — 02M Fab & Ship Structural Steel | 28-Dec-26 → 19-Mar-27 | Not Started 0% | float 123.0d PO02MS0120 PO02MS0130 — 02M Fab & Ship Miscellaneous Steel | 28-Dec-26 → 19-Mar-27 | Not Started 0% | float 147.0d PO02MS0130 PO02NMS100 — 02N Fab & Ship Miscellaneous Steel | 28-Dec-26 → 30-Apr-27 | Not Started 0% | float 67.0d PO02NMS100 PO02QMS100 — 02Q Fab & Ship Miscellaneous Steel | 28-Dec-26 → 23-Apr-27 | Not Started 0% | float 121.0d PO02QMS100 PO02YS0120 — 02Y Fab & Ship Structural Steel | 28-Dec-26 → 05-Mar-27 | Not Started 0% | float -22.0d PO02YS0120 PO03AS0130 — 03A Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 56.0d PO03AS0130 PO03BS0130 — 03B Fab & Ship Miscellaneous Steel | 28-Dec-26 → 09-Apr-27 | Not Started 0% | float 169.0d PO03BS0130 PO03CS0130 — 03C Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 87.0d PO03CS0130 PO03DS0130 — 03D Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 98.0d PO03DS0130 PO03ES0130 — 03E Fab & Ship Miscellaneous Steel | 28-Dec-26 → 16-Apr-27 | Not Started 0% | float 58.0d PO03ES0130 PO03YS0120 — 03Y Fab & Ship Structural Steel | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 39.0d PO03YS0120 WK000P0100 — 000 A/G Pipe Spool Fabrication | 28-Dec-26 → 31-May-27 | Not Started 0% | float 49.0d WK000P0100 WO010A0100 — 010 Buildings | 28-Dec-26 → 24-Jun-27 | Not Started 0% | float 94.0d WO010A0100 WO010M0100 — 010 Major Equipment | 28-Dec-26 → 01-Sep-27 | Not Started 0% | float 54.0d WO010M0100 WO010U3100 — 010 Install U/G Electrical | 28-Dec-26 → 27-Mar-27 | Not Started 0% | float 170.0d WO010U3100 WO020M0100 — 020 Major Equipment | 28-Dec-26 → 16-Aug-27 | Not Started 0% | float 156.0d WO020M0100 WO020U3100 — 020 Install U/G Electrical | 28-Dec-26 → 12-Mar-27 | Not Started 0% | float 265.0d WO020U3100 WO020U4100 — 020 U/G Piping Installation | 28-Dec-26 → 26-Feb-27 | Not Started 0% | float 224.0d WO020U4100 WO030M0100 — 030 Major Equipment | 28-Dec-26 → 26-Apr-27 | Not Started 0% | float 192.0d WO030M0100 WO030U4100 — 030 U/G Piping Installation | 28-Dec-26 → 26-Feb-27 | Not Started 0% | float 229.0d WO030U4100 WO04AV1100 — 04A Paint | 28-Dec-26 → 25-May-27 | Not Started 0% | float 148.0d WO04AV1100 WO050C0110 — 050 Concrete Paving | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float 0.0d WT010M0100 — 010 Tank Erection | 28-Dec-26 → 21-Apr-27 | Not Started 0% | float 9.0d WT010M0100 WT020M0100 — 020 Tank Erection | 28-Dec-26 → 08-Jan-27 | Not Started 0% | float 97.0d WT020M0100 WT030M0100 — 030 Tank Erection | 28-Dec-26 → 12-Jan-27 | Not Started 0% | float 105.0d WT030M0100 SC01JT0120 — 01J RFSU | 28-Dec-26 | Not Started CK01BP0110 — 01B A/G Pipe Spool Fabrication | 31-Dec-26 → 23-Mar-27 | Not Started 0% | float 101.0d CK01BP0110 CO01AV1110 — 01A Paint Fabricated Pipe Spools | 31-Dec-26 → 02-Jan-27 | Not Started 0% | float 253.0d WO010V1100 — 010 Paint | 31-Dec-26 → 05-Oct-27 | Not Started 0% | float 131.0d WO010V1100 CO02HM0200 — 02H Start Primary Reformer Erection (101-B) | 02-Jan-27 | Not Started CO02HM0210 — 02H Erect Radiant Section Shell (101-B) | 02-Jan-27 → 02-Apr-27 | Not Started 0% | float 108.0d CO02HM0210 CO02LU4120 — 02L U/G Piping Installation | 02-Jan-27 → 29-Jan-27 | Not Started 0% | float 123.0d CO02LU4120 PO03FS0130 — 03F Fab & Ship Miscellaneous Steel | 02-Jan-27 → 09-Apr-27 | Not Started 0% | float 88.0d PO03FS0130 EK01EA0140 — 01E Guard House Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 175.0d EK01EA0140 EK01FA0140 — 01F Mosque Design Drawings - Approval | 03-Jan-27 → 16-Jan-27 | Not Started 0% | float 119.0d EK01FA0140 PO01CS0130 — 01C Fab & Ship Miscellaneous Steel | 04-Jan-27 → 09-Apr-27 | Not Started 0% | float 106.0d PO01CS0130 PO02GS0130 — 02G Fab & Ship Miscellaneous Steel | 04-Jan-27 → 26-Mar-27 | Not Started 0% | float 107.0d PO02GS0130 CO01UP0150 — 01U LB Pipe Erection (Firewater Piping) | 05-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO01UP0150 WO010U4100 — 010 U/G Piping Installation | 05-Jan-27 → 26-Mar-27 | Not Started 0% | float 171.0d WO010U4100 CO02GU4120 — 02G U/G Piping Installation | 06-Jan-27 → 26-Feb-27 | Not Started 0% | float 159.0d CO02GU4120 CO03DC0120 — 03D Form, Pour, Strip Fnds - Misc Fnds | 06-Jan-27 → 19-Jan-27 | Not Started 0% | float 199.0d CO03DC0120 CK02QP0110 — 02Q A/G Pipe Spool Fabrication | 11-Jan-27 → 13-Apr-27 | Not Started 0% | float 90.0d CK02QP0110 EK05ACV210 — 05A COSMO Design Approval (Assuming No Change) | 11-Jan-27 → 16-Jan-27 | Not Started 0% | float -51.0d EK05ACV210 CO02CM0125 — 02C Set - 103/105-J Compressors | 12-Jan-27 → 16-Jan-27 | Not Started 0% | float 167.0d CO02CM0125 CO02YS0110 — 02Y Erect Structural Steel - Pipe Rack | 12-Jan-27 → 14-Jun-27 | Not Started 0% | float -35.0d CO02YS0110 WO020S0100 — 020 Erect Steel | 12-Jan-27 → 07-Oct-27 | Not Started 0% | float 69.0d WO020S0100 CO02HU3110 — 02H U/G Earthing Installation | 13-Jan-27 → 12-Feb-27 | Not Started 0% | float 162.0d CO02HU3110 CO03YV1110 — 03Y Paint Fabricated Pipe Spools | 13-Jan-27 → 13-Feb-27 | Not Started 0% | float 154.0d CO03YV1110 WO030V1100 — 030 Paint | 13-Jan-27 → 23-Aug-27 | Not Started 0% | float 153.0d WO030V1100 CO02CU3110 — 02C U/G Earthing Installation | 14-Jan-27 → 12-Feb-27 | Not Started 0% | float 168.0d CO02CU3110 CO03DU3110 — 03D U/G Earthing Installation | 15-Jan-27 → 19-Jan-27 | Not Started 0% | float 199.0d CO03DU3110 WO030U3100 — 030 Install U/G Electrical | 15-Jan-27 → 12-Mar-27 | Not Started 0% | float 229.0d WO030U3100 PO05AS0120 — 05A Fab & Ship Structural Steel | 15-Jan-27 → 04-Jun-27 | Not Started 0% | float 23.0d PO05AS0120 PO05AS0130 — 05A Fab & Ship Miscellaneous Steel | 15-Jan-27 → 04-Jun-27 | Not Started 0% | float 27.0d PO05AS0130 CO02HC0120 — 02H Form, Pour, Strip Fnds - Misc Fnds | 16-Jan-27 → 05-Feb-27 | Not Started 0% | float 174.0d CO02HC0120 CO02LU3110 — 02L U/G Earthing Installation | 16-Jan-27 → 12-Feb-27 | Not Started 0% | float 129.0d CO02LU3110 CO02UP0150 — 02U LB Pipe Erection (Firewater Piping) | 16-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO02UP0150 CO03UP0150 — 03U LB Pipe Erection (Firewater Piping) | 16-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO03UP0150 CO02CM0130 — 02C Install - 103/105-J Compressors & Aux. Equip. | 18-Jan-27 → 13-May-27 | Not Started 0% | float 167.0d CO02CM0130 CO05AC0185 — 05A Procure Material & Mob Piling Contractor | 18-Jan-27 → 30-Jan-27 | Not Started 0% | float -51.0d CO05AC0185 CO02AU3110 — 02A U/G Earthing Installation | 20-Jan-27 → 05-Feb-27 | Not Started 0% | float 228.0d CO02AU3110 CO02CV1110 — 02C Paint Fabricated Pipe Spools | 20-Jan-27 → 27-Feb-27 | Not Started 0% | float 245.0d CO02CV1110 WO020V1100 — 020 Paint | 20-Jan-27 → 14-Feb-28 | Not Started 0% | float 23.0d WO020V1100 CO02GC0110 — 02G Form, Pour, Strip Fnds - Major Fnds Gen'l | 23-Jan-27 → 26-Feb-27 | Not Started 0% | float 159.0d CO02GC0110 CK02CP0110 — 02C A/G Pipe Spool Fabrication | 25-Jan-27 → 20-Feb-27 | Not Started 0% | float 134.0d CK02CP0110 CO01HU3110 — 01H U/G Earthing Installation | 25-Jan-27 → 06-Feb-27 | Not Started 0% | float 134.0d CO01HU3110 CO02JU3110 — 02J U/G Earthing Installation | 25-Jan-27 → 12-Feb-27 | Not Started 0% | float 211.0d CO02JU3110 PO05BS0130 — 05B Fab & Ship Miscellaneous Steel | 25-Jan-27 → 12-Jun-27 | Not Started 0% | float 87.0d PO05BS0130 CO02BM0110 — 02B Set Static Equipment | 25-Jan-27 → 25-Jan-27 | Not Started 0% | float — CO02BV1130 — 02B Paint Touch-up - Equipment | 25-Jan-27 → 01-Feb-27 | Not Started 0% | float 300.0d CO02BV1130 CO02KU3110 — 02K U/G Earthing Installation | 26-Jan-27 → 12-Feb-27 | Not Started 0% | float 214.0d CO02KU3110 CO02EU3110 — 02E U/G Earthing Installation | 28-Jan-27 → 12-Feb-27 | Not Started 0% | float 227.0d CO02EU3110 CO01YV1110 — 01Y Paint Fabricated Pipe Spools | 28-Jan-27 → 05-Feb-27 | Not Started 0% | float 149.0d CO01YV1110 CO02FU3110 — 02F U/G Earthing Installation | 29-Jan-27 → 12-Feb-27 | Not Started 0% | float 234.0d CO02FU3110 CO01JP0230 — 01J U/G Pipe Erection - Piping to Corridor | 29-Jan-27 → 26-Feb-27 | Not Started 0% | float 160.0d CO01JP0230 CO04AU4120 — 04A U/G Piping Installation | 29-Jan-27 → 09-Aug-27 | Not Started 0% | float 108.0d CO04AU4120 WO04AE0100 — 04A Above Ground Electrical | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AE0100 WO04AI0100 — 04A Install Instruments & Test | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AI0100 WO04AM0100 — 04A Major Equipment | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AM0100 WO04AS0100 — 04A Erect Steel | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AS0100 WO04AU4100 — 04A U/G Piping Installation | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AU4100 CO02BC0120 — 02B Form, Pour, Strip Fnds - Misc Fnds | 29-Jan-27 → 29-Jan-27 | Not Started 0% | float — PO01YS0000 — 01Y Recv at Site - Structural Steel | 29-Jan-27 | Not Started PO03YS0000 — 03Y Recv at Site - Structural Steel | 29-Jan-27 | Not Started CO01BU4120 — 01B U/G Piping Installation | 30-Jan-27 → 10-Mar-27 | Not Started 0% | float 173.0d CO01BU4120 CO01DU4120 — 01D U/G Piping Installation | 30-Jan-27 → 02-Mar-27 | Not Started 0% | float 49.0d CO01DU4120 CO01EU4130 — 01E/F/G U/G Piping Installation (to Bldg Stub Outs) | 30-Jan-27 → 26-Mar-27 | Not Started 0% | float 147.0d CO01EU4130 CO02CC0120 — 02C Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 19-Feb-27 | Not Started 0% | float 162.0d CO02CC0120 CO02DC0120 — 02D Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 30-Jan-27 | Not Started 0% | float 260.0d CO02EC0120 — 02E Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 227.0d CO02EC0120 CO02FC0120 — 02F Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 234.0d CO02FC0120 CO02FM0110 — 02F Set Static Equipment | 30-Jan-27 → 26-Feb-27 | Not Started 0% | float 241.0d CO02FM0110 CO02JC0120 — 02J Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 211.0d CO02JC0120 CO02KC0120 — 02K Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 214.0d CO02KC0120 CO02LC0120 — 02L Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 19-Feb-27 | Not Started 0% | float 123.0d CO02LC0120 CO02MC0120 — 02M Form, Pour, Strip Fnds - Misc Fnds | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 239.0d CO02MC0120 CO02MU3110 — 02M U/G Earthing Installation | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 239.0d CO02MU3110 CO02YC0130 — 02Y Install Paving | 30-Jan-27 → 17-Mar-27 | Not Started 0% | float 71.0d CO02YC0130 CO03AU4120 — 03A U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 135.0d CO03AU4120 CO03BU4120 — 03B U/G Piping Installation | 30-Jan-27 → 17-Feb-27 | Not Started 0% | float 237.0d CO03BU4120 CO03CU4120 — 03C U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 166.0d CO03CU4120 CO03EU4120 — 03E U/G Piping Installation | 30-Jan-27 → 26-Feb-27 | Not Started 0% | float 121.0d CO03EU4120 CO03FU4120 — 03F U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 155.0d CO03FU4120 WO020C0110 — 020 Concrete Paving | 30-Jan-27 → 22-May-27 | Not Started 0% | float 210.0d WO020C0110 CO01HC0140 — 01H Form Pour Strip Fnds - Transformers & Generator | 01-Feb-27 → 27-Feb-27 | Not Started 0% | float 116.0d CO01HC0140 CO03DC0130 — 03D Install Paving | 01-Feb-27 → 06-Feb-27 | Not Started 0% | float 189.0d CO03DC0130 CO03FM0150 — 03F Install Chemical Injection System | 01-Feb-27 → 13-Mar-27 | Not Started 0% | float 159.0d CO03FM0150 CO05AC0150 — 05A Install Piling - 2101-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -51.0d CO05AC0150 CO05AC0155 — 05A Install Piling - 2102-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -40.0d CO05AC0155 PO000EL000 — Electrical Heat Tracing - Purchase & Deliver Materials (By OCI) | 01-Feb-27 → 04-May-27 | Not Started 0% | float 108.0d PO000EL000 WO030C0110 — 030 Concrete Paving | 01-Feb-27 → 17-Apr-27 | Not Started 0% | float 210.0d WO030C0110 WO050C0100 — 050 Concrete & Excavation | 01-Feb-27 → 30-Jul-27 | Not Started 0% | float 152.0d WO050C0100 CO02DU3110 — 02D U/G Earthing Installation | 02-Feb-27 → 12-Feb-27 | Not Started 0% | float 248.0d CO02DU3110 CO01EA0130 — 01E Erect Guard House | 04-Feb-27 → 03-Mar-27 | Not Started 0% | float 191.0d CO01EA0130 CO01FA0130 — 01F Erect Mosque | 04-Feb-27 → 28-Apr-27 | Not Started 0% | float 143.0d CO01FA0130 CO02YV1110 — 02Y Paint Fabricated Pipe Spools | 05-Feb-27 → 19-Feb-27 | Not Started 0% | float 131.0d CO02YV1110 CO01CC0110 — 01C Form, Pour, Strip Fnds - Major Fnds Gen'l | 08-Feb-27 → 06-Mar-27 | Not Started 0% | float 117.0d CO01CC0110 CO01YC0130 — 01Y Install Paving | 08-Feb-27 → 27-Feb-27 | Not Started 0% | float 134.0d CO01YC0130 WO010C0110 — 010 Concrete Paving | 08-Feb-27 → 08-Jul-27 | Not Started 0% | float 188.0d WO010C0110 CK02GP0110 — 02G A/G Pipe Spool Fabrication | 09-Feb-27 → 15-Mar-27 | Not Started 0% | float 115.0d CK02GP0110 CO02BU3110 — 02B U/G Earthing Installation | 10-Feb-27 → 12-Feb-27 | Not Started 0% | float 289.0d CK03EP0110 — 03E A/G Pipe Spool Fabrication | 12-Feb-27 → 02-Mar-27 | Not Started 0% | float 126.0d CK03EP0110 CK03FP0110 — 03F A/G Pipe Spool Fabrication | 12-Feb-27 → 23-Feb-27 | Not Started 0% | float 132.0d CK03FP0110 CO02EV1110 — 02E Paint Fabricated Pipe Spools | 12-Feb-27 → 04-Mar-27 | Not Started 0% | float 250.0d CO02EV1110 CO03AC0120 — 03A Form, Pour, Strip Fnds - Misc Fnds | 12-Feb-27 → 25-Feb-27 | Not Started 0% | float 141.0d CO03AC0120 CO03CV1110 — 03C Paint Fabricated Pipe Spools | 13-Feb-27 → 24-Feb-27 | Not Started 0% | float 191.0d CO03CV1110 CO02GU3110 — 02G U/G Earthing Installation | 15-Feb-27 → 12-Mar-27 | Not Started 0% | float 159.0d CO02GU3110 CO02GV1110 — 02G Paint Fabricated Pipe Spools | 16-Feb-27 → 22-Mar-27 | Not Started 0% | float 230.0d CO02GV1110 CO03BC0120 — 03B Form, Pour, Strip Fnds - Misc Fnds | 18-Feb-27 → 03-Mar-27 | Not Started 0% | float 243.0d CO03BC0120 CO03CC0120 — 03C Form, Pour, Strip Fnds - Misc Fnds | 19-Feb-27 → 04-Mar-27 | Not Started 0% | float 166.0d CO03CC0120 CO03EV1110 — 03E Paint Fabricated Pipe Spools | 19-Feb-27 → 09-Mar-27 | Not Started 0% | float 171.0d CO03EV1110 CO03FC0120 — 03F Form, Pour, Strip Fnds - Misc Fnds | 19-Feb-27 → 11-Mar-27 | Not Started 0% | float 155.0d CO03FC0120 CO03FV1110 — 03F Paint Fabricated Pipe Spools | 19-Feb-27 → 02-Mar-27 | Not Started 0% | float 183.0d CO03FV1110 PO01DS0000 — 01D Recv at Site - Structural Steel | 19-Feb-27 | Not Started PO01DS0010 — 01D Recv at Site - Misc Steel | 19-Feb-27 | Not Started CK03AP0110 — 03A A/G Pipe Spool Fabrication | 20-Feb-27 → 03-Mar-27 | Not Started 0% | float 125.0d CK03AP0110 CO02CC0130 — 02C Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 162.0d CO02CC0130 CO02LC0130 — 02L Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 123.0d CO02LC0130 CO01CU4120 — 01C U/G Piping Installation | 22-Feb-27 → 06-Mar-27 | Not Started 0% | float 160.0d CO01CU4120 CO02HM0220 — 02H Erect Radiant Ducting / Burners (101-B) | 22-Feb-27 → 20-Mar-27 | Not Started 0% | float 151.0d CO02HM0220 PO02KS0130 — 02K Fab & Ship Miscellaneous Steel | 22-Feb-27 → 09-Apr-27 | Not Started 0% | float 120.0d PO02KS0130 CO03BU3110 — 03B U/G Earthing Installation | 23-Feb-27 → 03-Mar-27 | Not Started 0% | float 237.0d CO03BU3110 CK02JP0110 — 02J A/G Pipe Spool Fabrication | 23-Feb-27 → 20-Mar-27 | Not Started 0% | float 111.0d CK02JP0110 CO03CU3110 — 03C U/G Earthing Installation | 24-Feb-27 → 04-Mar-27 | Not Started 0% | float 166.0d CO03CU3110 CO03FU3110 — 03F U/G Earthing Installation | 24-Feb-27 → 04-Mar-27 | Not Started 0% | float 161.0d CO03FU3110 CO03AU3110 — 03A U/G Earthing Installation | 26-Feb-27 → 04-Mar-27 | Not Started 0% | float 135.0d CO03AU3110 CO02UDT110 — 02U Mechanical Completion | 26-Feb-27 | Not Started CO03UDT110 — 03U Mechanical Completion | 26-Feb-27 | Not Started PO01BS0010 — 01B Recv at Site - Misc Steel | 26-Feb-27 | Not Started SC02UT0120 — 02U RFSU | 26-Feb-27 | Not Started SC03UT0120 — 03U RFSU | 26-Feb-27 | Not Started CK03DP0110 — 03D A/G Pipe Spool Fabrication | 27-Feb-27 → 04-Mar-27 | Not Started 0% | float 124.0d CK03DP0110 CO02GC0120 — 02G Form, Pour, Strip Fnds - Misc Fnds | 27-Feb-27 → 19-Mar-27 | Not Started 0% | float 165.0d CO02GC0120 CO02GM0110 — 02G Set Static Equipment - Gen'l | 27-Feb-27 → 31-Mar-27 | Not Started 0% | float 208.0d CO02GM0110 CO03AV1110 — 03A Paint Fabricated Pipe Spools | 27-Feb-27 → 10-Mar-27 | Not Started 0% | float 148.0d CO03AV1110 CO03EC0120 — 03E Form, Pour, Strip Fnds - Misc Fnds | 27-Feb-27 → 19-Mar-27 | Not Started 0% | float 121.0d CO03EC0120 CO03EU3110 — 03E U/G Earthing Installation | 27-Feb-27 → 12-Mar-27 | Not Started 0% | float 127.0d CO03EU3110 CK01CP0110 — 01C A/G Pipe Spool Fabrication | 27-Feb-27 → 06-Mar-27 | Not Started 0% | float 123.0d CK01CP0110 CO01HC0120 — 01H Form, Pour, Strip Fnds - Misc Fnds | 01-Mar-27 → 13-Mar-27 | Not Started 0% | float 176.0d CO01HC0120 CO02JS0130 — 02J Pre-Install Misc Steel - 104-D2 | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 103.0d CO02JS0130 CO02JS0140 — 02J Pre-Install Misc Steel - 104-D1 | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 108.0d CO02JS0140 CO02LS0130 — 02L Pre-Install Misc Steel - 101-E | 01-Mar-27 → 15-Mar-27 | Not Started 0% | float 113.0d CO02LS0130 CO03BM0110 — 03B Set Static Equipment - Gen'l | 01-Mar-27 → 02-Apr-27 | Not Started 0% | float 212.0d CO03BM0110 CO03EM0110 — 03E Set Static Equipment - Gen'l | 01-Mar-27 → 05-Apr-27 | Not Started 0% | float 135.0d CO03EM0110 CO01DC0110 — 01D Form, Pour, Strip Fnds - Major Fnds Gen'l | 03-Mar-27 → 13-Apr-27 | Not Started 0% | float 49.0d CO01DC0110 CO01DU3110 — 01D U/G Earthing Installation | 03-Mar-27 → 17-Mar-27 | Not Started 0% | float 113.0d CO01DU3110 CO01EC0135 — 01E Install Paving - Guard House | 04-Mar-27 → 17-Mar-27 | Not Started 0% | float 285.0d CO01EC0135 CO03BC0130 — 03B Install Paving | 04-Mar-27 → 17-Mar-27 | Not Started 0% | float 237.0d CO03BC0130 CO01BU3110 — 01B U/G Earthing Installation | 05-Mar-27 → 24-Mar-27 | Not Started 0% | float 173.0d CO01BU3110 PO02LS0000 — 02L Recv at Site - Structural Steel | 05-Mar-27 | Not Started PO02LS0010 — 02L Recv at Site - Misc Steel | 05-Mar-27 | Not Started PO02YS0000 — 02Y Recv at Site - Structural Steel (Last Shipment) | 05-Mar-27 | Not Started CO01YS0110 — 01Y Erect Structural Steel - Pipe Rack | 06-Mar-27 → 30-Apr-27 | Not Started 0% | float 39.0d CO01YS0110 CO03DV1110 — 03D Paint Fabricated Pipe Spools | 06-Mar-27 → 11-Mar-27 | Not Started 0% | float 172.0d CO03DV1110 CO03YS0110 — 03Y Erect Structural Steel | 06-Mar-27 → 26-Mar-27 | Not Started 0% | float 39.0d CO03YS0110 WO010S0100 — 010 Erect Steel | 06-Mar-27 → 11-Jun-27 | Not Started 0% | float 94.0d WO010S0100 WO030S0100 — 030 Erect Steel | 06-Mar-27 → 25-Jun-27 | Not Started 0% | float 157.0d WO030S0100 CO01CV1110 — 01C Paint Fabricated Pipe Spools | 06-Mar-27 → 13-Mar-27 | Not Started 0% | float 174.0d CO01CV1110 CO01BV1110 — 01B Paint Fabricated Pipe Spools | 08-Mar-27 → 30-Mar-27 | Not Started 0% | float 153.0d CO01BV1110 CO01CC0120 — 01C Form, Pour, Strip Fnds - Misc Fnds | 08-Mar-27 → 27-Mar-27 | Not Started 0% | float 160.0d CO01CC0120 CO03AC0130 — 03A Install Paving | 08-Mar-27 → 13-Mar-27 | Not Started 0% | float 133.0d CO03AC0130 CO02GM0125 — 02G Set - 101-J/JT Air Compr. | 08-Mar-27 → 05-Apr-27 | Not Started 0% | float 105.0d CO02GM0125 CO02AC0120 — 02A Form, Pour, Strip Fnds - Misc Fnds | 10-Mar-27 → 23-Mar-27 | Not Started 0% | float 189.0d CO02AC0120 CO02AM0150 — 02A Set Rotating Equipment | 10-Mar-27 → 06-Apr-27 | Not Started 0% | float 207.0d CO02AM0150 CO01DV1110 — 01D Paint Fabricated Pipe Spools | 11-Mar-27 → 29-Mar-27 | Not Started 0% | float 142.0d CO01DV1110 CO02GC0130 — 02G Install Paving | 13-Mar-27 → 26-Mar-27 | Not Started 0% | float 159.0d CO02GC0130 CO01CU3110 — 01C U/G Earthing Installation | 15-Mar-27 → 20-Mar-27 | Not Started 0% | float 166.0d CO01CU3110 CO01GU3110 — 01G U/G Earthing Installation | 15-Mar-27 → 27-Mar-27 | Not Started 0% | float 146.0d CO01GU3110 CO03CC0130 — 03C Install Paving | 15-Mar-27 → 20-Mar-27 | Not Started 0% | float 158.0d CO03CC0130 CO02HM0250 — 02H Set Forced Draft Fan (101-B) | 15-Mar-27 → 12-Apr-27 | Not Started 0% | float 234.0d CO02HM0250 CO03CM0150 — 03C Set Rotating Equipment | 15-Mar-27 → 22-Mar-27 | Not Started 0% | float 146.0d CO03CM0150 CO03DM0150 — 03D Set Rotating Equipment | 15-Mar-27 → 29-Mar-27 | Not Started 0% | float 158.0d CO03DM0150 CO02HM0135 — 02H Give 30 Day notice to Manufacture Refractory (103-D) | 16-Mar-27 | Not Started CO03FV1130 — 03F Paint Touch-up - Equipment | 17-Mar-27 → 27-Mar-27 | Not Started 0% | float 183.0d CO03FV1130 CO02YS0120 — 02Y Erect Misc Steel - Pipe Rack | 19-Mar-27 → 14-Jun-27 | Not Started 0% | float 102.0d CO02YS0120 PO02MS0000 — 02M Recv at Site - Structural Steel | 19-Mar-27 | Not Started PO02MS0010 — 02M Recv at Site - Misc Steel | 19-Mar-27 | Not Started CK02MP0110 — 02M A/G Pipe Spool Fabrication | 22-Mar-27 → 07-Apr-27 | Not Started 0% | float 95.0d CK02MP0110 CO02HM0246 — 02H Install Radiant Sect Coils (101-B) | 22-Mar-27 → 17-Apr-27 | Not Started 0% | float 151.0d CO02HM0246 CO03FC0130 — 03F Install Paving | 22-Mar-27 → 03-Apr-27 | Not Started 0% | float 147.0d CO03FC0130 CO02HM0255 — 02H Set Induced Draft Fan (101-B) | 22-Mar-27 → 19-Apr-27 | Not Started 0% | float 234.0d CO02HM0255 CO02KV1130 — 02K Paint Touch-up - Equipment | 23-Mar-27 → 15-Apr-27 | Not Started 0% | float 236.0d CO02KV1130 CO02AC0130 — 02A Install Paving | 24-Mar-27 → 30-Mar-27 | Not Started 0% | float 189.0d CO02AC0130 CO03CV1130 — 03C Paint Touch-up - Equipment | 24-Mar-27 → 05-Apr-27 | Not Started 0% | float 195.0d CO03CV1130 CO02CM0150 — 02C Set Rotating Equipment - 112-J/JA/JM | 26-Mar-27 → 30-Mar-27 | Not Started 0% | float 205.0d CO02CM0150 CO02GM0150 — 02G Set Rotating Equipment | 26-Mar-27 → 10-Apr-27 | Not Started 0% | float 199.0d CO02GM0150 CO02KM0150 — 02K Set Rotating Equipment | 26-Mar-27 → 01-Apr-27 | Not Started 0% | float 163.0d CO02KM0150 CO02LM0150 — 02L Set Rotating Equipment | 26-Mar-27 → 27-Apr-27 | Not Started 0% | float 170.0d CO02LM0150 CO03BM0150 — 03B Set Rotating Equipment | 26-Mar-27 → 15-Apr-27 | Not Started 0% | float 200.0d CO03BM0150 CO01UDT110 — 01U Mechanical Completion | 26-Mar-27 | Not Started PO02CS0010 — 02C Recv at Site - Misc Steel | 26-Mar-27 | Not Started PO02GS0010 — 02G Recv at Site - Misc Steel | 26-Mar-27 | Not Started PO02HS0000 — 02H Recv at Site - Structural Steel | 26-Mar-27 | Not Started PO02HS0010 — 02H Recv at Site - Misc Steel | 26-Mar-27 | Not Started SC01UT0120 — 01U RFSU | 26-Mar-27 | Not Started CO02HS0140 — 02H Install Misc Steel - 156-F | 27-Mar-27 → 09-Apr-27 | Not Started 0% | float 102.0d CO02HS0140 CO03YP0130 — 03Y LB Pipe Erection | 27-Mar-27 → 09-Jul-27 | Not Started 0% | float 39.0d CO03YP0130 WO030P0100 — 030 Above Ground Pipe | 27-Mar-27 → 23-Aug-27 | Not Started 0% | float 138.0d WO030P0100 CO02JV1110 — 02J Paint Fabricated Pipe Spools | 27-Mar-27 → 27-Mar-27 | Not Started 0% | float 164.0d CK03BP0110 — 03B A/G Pipe Spool Fabrication | 29-Mar-27 → 08-Apr-27 | Not Started 0% | float 94.0d CK03BP0110 CO01CC0130 — 01C Install Paving | 29-Mar-27 → 10-Apr-27 | Not Started 0% | float 160.0d CO01CC0130 CO03AM0110 — 03A Set Static Equipment | 29-Mar-27 → 26-Apr-27 | Not Started 0% | float 95.0d CO03AM0110 CO02AV1130 — 02A Paint Touch-up - Equipment | 30-Mar-27 → 20-Apr-27 | Not Started 0% | float 232.0d CO02AV1130 CO01BM0110 — 01B Set Static Equipment | 31-Mar-27 → 27-Apr-27 | Not Started 0% | float 71.0d CO01BM0110 CO02MV1110 — 02M Paint Fabricated Pipe Spools | 01-Apr-27 → 14-Apr-27 | Not Started 0% | float 215.0d CO02MV1110 CO02NV1110 — 02N Paint Fabricated Pipe Spools | 01-Apr-27 → 03-Apr-27 | Not Started 0% | float 216.0d CO04AU3110 — 04A U/G Fiber Optic Cable Installation | 01-Apr-27 → 10-Aug-27 | Not Started 0% | float 137.0d CO04AU3110 WO04AU3100 — 04A Install U/G Electrical | 01-Apr-27 → 10-Aug-27 | Not Started 0% | float 137.0d WO04AU3100 CK02LP0110 — 02L A/G Pipe Spool Fabrication | 02-Apr-27 → 22-May-27 | Not Started 0% | float 32.0d CK02LP0110 CO02DM0150 — 02D Set Rotating Equipment | 02-Apr-27 → 15-Apr-27 | Not Started 0% | float 182.0d CO02DM0150 PO02DS0000 — 02D Recv at Site - Structural Steel | 02-Apr-27 | Not Started PO02DS0010 — 02D Recv at Site - Misc Steel | 02-Apr-27 | Not Started CK02KP0110 — 02K A/G Pipe Spool Fabrication | 03-Apr-27 → 27-Apr-27 | Not Started 0% | float 78.0d CK02KP0110 CO01BS0120 — 01B Erect Misc Steel | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 86.0d CO01BS0120 CO02HC0130 — 02H Install Paving | 03-Apr-27 → 16-Apr-27 | Not Started 0% | float 120.0d CO02HC0130 CO02HM0230 — 02H Set Convection Sections (101-B) | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 108.0d CO02HM0230 CO02HM0240 — 02H Set Stack for (101-B) | 03-Apr-27 → 30-Apr-27 | Not Started 0% | float 223.0d CO02HM0240 CO03YP0140 — 03Y SB Pipe Erection | 03-Apr-27 → 16-Jul-27 | Not Started 0% | float 45.0d CO03YP0140 CO02JC0130 — 02J Install Paving | 05-Apr-27 → 10-Apr-27 | Not Started 0% | float 168.0d CO02JC0130 CO03BV1110 — 03B Paint Fabricated Pipe Spools | 05-Apr-27 → 15-Apr-27 | Not Started 0% | float 223.0d CO03BV1110 CO03EC0130 — 03E Install Paving | 05-Apr-27 → 17-Apr-27 | Not Started 0% | float 108.0d CO03EC0130 CO01CM0110 — 01C Set Static Equipment - EDR Equipment | 05-Apr-27 → 31-May-27 | Not Started 0% | float 93.0d CO01CM0110 CO01CM0115 — 01C Set Rotating Equipment - EDR Equipment | 05-Apr-27 → 31-May-27 | Not Started 0% | float 99.0d CO01CM0115 CO02GM0130 — 02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux. | 05-Apr-27 → 30-Jul-27 | Not Started 0% | float 105.0d CO02GM0130 CO02HS0130 — 02H Pre-Install Misc Steel - 103-D | 05-Apr-27 → 19-Apr-27 | Not Started 0% | float 68.0d CO02HS0130 CO03DV1130 — 03D Paint Touch-up - Equipment (& 2002-F Tank) | 06-Apr-27 → 12-Apr-27 | Not Started 0% | float 189.0d CO03DV1130 CO02FV1110 — 02F Paint Fabricated Pipe Spools | 09-Apr-27 → 27-Apr-27 | Not Started 0% | float 204.0d CO02FV1110 CO02LV1110 — 02L Paint Fabricated Pipe Spools | 09-Apr-27 → 29-May-27 | Not Started 0% | float 162.0d CO02LV1110 PO01CS0010 — 01C Recv at Site - Misc Steel | 09-Apr-27 | Not Started PO01HS0010 — 01H Recv at Site - Misc Steel | 09-Apr-27 | Not Started PO02AS0000 — 02A Recv at Site - Structural Steel | 09-Apr-27 | Not Started PO02AS0010 — 02A Recv at Site - Misc Steel | 09-Apr-27 | Not Started PO02KS0010 — 02K Recv at Site - Misc Steel | 09-Apr-27 | Not Started PO03BS0010 — 03B Recv at Site - Misc Steel | 09-Apr-27 | Not Started PO03FS0010 — 03F Recv at Site - Misc Steel | 09-Apr-27 | Not Started CO02KV1110 — 02K Paint Fabricated Pipe Spools | 10-Apr-27 → 04-May-27 | Not Started 0% | float 181.0d CO02KV1110 CO02LS0110 — 02L Erect Structure | 10-Apr-27 → 18-Jun-27 | Not Started 0% | float -15.0d CO02LS0110 PO000E0010 — Receive at Site - A/G Electrical Bulks (First) | 10-Apr-27 | Not Started CO02KC0130 — 02K Install Paving | 12-Apr-27 → 17-Apr-27 | Not Started 0% | float 165.0d CO02KC0130 CO01HA0110 — 01H Set 2610-K Electrical Power House | 12-Apr-27 → 03-May-27 | Not Started 0% | float 76.0d CO01HA0110 CO02YP0130 — 02Y LB Pipe Erection | 13-Apr-27 → 05-Oct-27 | Not Started 0% | float -35.0d CO02YP0130 WO020P0100 — 020 Above Ground Pipe | 13-Apr-27 → 14-Feb-28 | Not Started 0% | float -1.0d WO020P0100 CO01DC0120 — 01D Form, Pour, Strip Fnds - Misc Fnds | 14-Apr-27 → 04-May-27 | Not Started 0% | float 72.0d CO01DC0120 CO01DM0110 — 01D Set Static Equipment | 14-Apr-27 → 25-May-27 | Not Started 0% | float 49.0d CO01DM0110 CO02DV1130 — 02D Paint Touch-up - Equipment | 15-Apr-27 → 29-Apr-27 | Not Started 0% | float 224.0d CO02DV1130 CO02FM0150 — 02F Set Rotating Equipment | 16-Apr-27 → 13-May-27 | Not Started 0% | float 176.0d CO02FM0150 CO02QV1110 — 02Q Paint Fabricated Pipe Spools | 16-Apr-27 → 20-Apr-27 | Not Started 0% | float 210.0d CO02QV1110 PO02ES0000 — 02E Recv at Site - Structural Steel | 16-Apr-27 | Not Started PO02ES0010 — 02E Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO02FS0010 — 02F Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO02JS0000 — 02J Recv at Site - Structural Steel | 16-Apr-27 | Not Started PO02JS0010 — 02J Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO03AS0010 — 03A Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO03CS0010 — 03C Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO03DS0010 — 03D Recv at Site - Misc Steel | 16-Apr-27 | Not Started PO03ES0010 — 03E Recv at Site - Misc Steel | 16-Apr-27 | Not Started CO020M0110 — Mobilize / Assemble / Test Heavy Lift Crane | 19-Apr-27 → 01-May-27 | Not Started 0% | float 56.0d CO020M0110 CO02EC0130 — 02E Install Paving | 19-Apr-27 → 24-Apr-27 | Not Started 0% | float 172.0d CO02EC0130 CO02HM0248 — 02H Install Effluent Transfer Line (107-D) | 19-Apr-27 → 01-May-27 | Not Started 0% | float 151.0d CO02HM0248 CO03BV1130 — 03B Paint Touch-up - Equipment | 19-Apr-27 → 29-Apr-27 | Not Started 0% | float 248.0d CO03BV1130 CK02HP0110 — 02H A/G Pipe Spool Fabrication | 19-Apr-27 → 29-May-27 | Not Started 0% | float 51.0d CK02HP0110 CO01HM0110 — 01H Set Static Equipment - 2303-J Emergency Pwr Gen. | 19-Apr-27 → 31-May-27 | Not Started 0% | float 86.0d CO01HM0110 CO02LS0140 — 02L Pre-Install Misc Steel - 102-E | 19-Apr-27 → 03-May-27 | Not Started 0% | float 76.0d CO02LS0140 CO05AC0160 — 05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -51.0d CO05AC0160 CO05AC0165 — 05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -40.0d CO05AC0165 CO02DV1110 — 02D Paint Fabricated Pipe Spools | 23-Apr-27 → 07-May-27 | Not Started 0% | float 177.0d CO02DV1110 CO04AC0110 — 04A Concrete (Valve Boxes & Paving) | 23-Apr-27 → 23-Aug-27 | Not Started 0% | float 130.0d CO04AC0110 WO04AC0100 — 04A Concrete (Valve Boxes & Paving) | 23-Apr-27 → 23-Aug-27 | Not Started 0% | float 130.0d WO04AC0100 PO02QMS110 — 02Q Recv at Site - Misc Steel | 23-Apr-27 | Not Started CO01YS0120 — 01Y Erect Misc Steel - Pipe Rack | 24-Apr-27 → 21-May-27 | Not Started 0% | float 39.0d CO01YS0120 CO02MS0110 — 02M Erect Structural Steel - Structure | 24-Apr-27 → 14-May-27 | Not Started 0% | float 123.0d CO02MS0110 CO02PV1110 — 02P Paint Fabricated Pipe Spools | 24-Apr-27 → 28-Apr-27 | Not Started 0% | float 199.0d CO02PV1110 CO02FC0130 — 02F Install Paving | 26-Apr-27 → 01-May-27 | Not Started 0% | float 173.0d CO02FC0130 CO02HV1110 — 02H Paint Fabricated Pipe Spools | 26-Apr-27 → 05-Jun-27 | Not Started 0% | float 54.0d CO02HV1110 CK05AP0110 — 05A A/G Pipe Spool Fabrication | 28-Apr-27 → 31-May-27 | Not Started 0% | float 49.0d CK05AP0110 CO04AU4130 — 04A Punchlist / Test U/G Piping | 28-Apr-27 → 01-Sep-27 | Not Started 0% | float 108.0d CO04AU4130 CO01FC0135 — 01F Install Paving - Mosque | 29-Apr-27 → 19-May-27 | Not Started 0% | float 203.0d CO01FC0135 PO02NMS110 — 02N Recv at Site - Misc Steel | 30-Apr-27 | Not Started CO01BM0150 — 01B Set Rotating Equipment | 01-May-27 → 11-Jun-27 | Not Started 0% | float 32.0d CO01BM0150 CO01DM0150 — 01D Set Rotating Equipment | 01-May-27 → 11-Jun-27 | Not Started 0% | float 34.0d CO01DM0150 CO01YP0130 — 01Y LB Pipe Erection - Pipe Rack | 01-May-27 → 25-Jun-27 | Not Started 0% | float 39.0d CO01YP0130 CO02CS0120 — 02C Erect Misc. Steel (Platforms) | 01-May-27 → 02-Aug-27 | Not Started 0% | float 83.0d CO02CS0120 CO02GS0130 — 02G Erect Misc. Steel (Platforms) | 01-May-27 → 02-Aug-27 | Not Started 0% | float 107.0d CO02GS0130 CO02HM0235 — 02H Erect Preheater (101-B) | 01-May-27 → 25-Jun-27 | Not Started 0% | float 175.0d CO02HM0235 WO010P0100 — 010 Above Ground Pipe | 01-May-27 → 05-Oct-27 | Not Started 0% | float 95.0d WO010P0100 CO020M0120 — Heavy Lift Crane Useage | 03-May-27 → 04-Aug-27 | Not Started 0% | float 56.0d CO020M0120 CO02HM0130 — 02H Set (Heavy Lift) - 103-D (Secondary Reformer) | 03-May-27 → 07-May-27 | Not Started 0% | float 56.0d CO02HM0130 CO02HM0225 — 02H Erect Penthouse Roof, & Siding (101-B) | 03-May-27 → 29-May-27 | Not Started 0% | float 151.0d CO02HM0225 CO02MC0130 — 02M Install Paving | 03-May-27 → 08-May-27 | Not Started 0% | float 172.0d CO02MC0130 CO02KS0130 — 02K Pre-Install Misc Steel - Static Equipment | 03-May-27 → 17-May-27 | Not Started 0% | float 101.0d CO02KS0130 CO02GP0130 — 02G LB Pipe Erection | 04-May-27 → 10-Sep-27 | Not Started 0% | float 105.0d CO02GP0130 CK02AP0110 — 02A A/G Pipe Spool Fabrication | 05-May-27 → 26-May-27 | Not Started 0% | float 53.0d CK02AP0110 CO000E0500 — Cathodic Protection - Installation | 05-May-27 → 17-Oct-27 | Not Started 0% | float 6.0d CO000E0500 CO01DC0130 — 01D Install Paving | 05-May-27 → 18-May-27 | Not Started 0% | float 72.0d CO01DC0130 CO01DS0120 — 01D Erect Misc Steel | 05-May-27 → 01-Jun-27 | Not Started 0% | float 61.0d CO01DS0120 CO05AV1110 — 05A Paint Fabricated Pipe Spools | 05-May-27 → 07-Jun-27 | Not Started 0% | float 166.0d CO05AV1110 WO050V1100 — 050 Paint | 05-May-27 → 12-Apr-28 | Not Started 0% | float 12.0d WO050V1100 WP000U3100 — Cathodic Protection | 05-May-27 → 17-Oct-27 | Not Started 0% | float 6.0d WP000U3100 CO02CP0130 — 02C LB Pipe Erection | 08-May-27 → 08-Oct-27 | Not Started 0% | float 83.0d CO02CP0130 CO02DS0110 — 02D Erect Structural Steel | 08-May-27 → 28-May-27 | Not Started 0% | float 93.0d CO02DS0110 CO02JM0130 — 02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter) | 08-May-27 → 13-May-27 | Not Started 0% | float 56.0d CO02JM0130 CO02LS0120 — 02L Erect Misc Steel | 08-May-27 → 04-Jun-27 | Not Started 0% | float 39.0d CO02LS0120 CO02DC0130 — 02D Install Paving | 10-May-27 → 15-May-27 | Not Started 0% | float 175.0d CO02DC0130 CO02FV1130 — 02F Paint Touch-up - Equipment | 10-May-27 → 27-May-27 | Not Started 0% | float 200.0d CO02FV1130 CO02MS0130 — 02M Pre-Install Misc Steel - 105-D | 10-May-27 → 24-May-27 | Not Started 0% | float 63.0d CO02MS0130 CO02YP0140 — 02Y SB Pipe Erection | 11-May-27 → 02-Nov-27 | Not Started 0% | float -29.0d CO02YP0140 CO05AC0120 — 05A Form, Pour, Strip Fnds - Sleeper & Rack | 11-May-27 → 14-Jun-27 | Not Started 0% | float 44.0d CO05AC0120 CO02GP0140 — 02G SB Pipe Erection | 11-May-27 → 25-Sep-27 | Not Started 0% | float 105.0d CO02GP0140 CO04AV2110 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d CO04AV2110 WO04AV2100 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d WO04AV2100 CO05AU4120 — 05A U/G Piping Installation | 13-May-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AU4120 WO050U4100 — 050 U/G Piping Installation | 13-May-27 → 30-Sep-27 | Not Started 0% | float 135.0d WO050U4100 CO02CV1130 — 02C Paint Touch-up - Equipment | 14-May-27 → 22-Jun-27 | Not Started 0% | float 190.0d CO02CV1130 CO02JM0140 — 02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter) | 14-May-27 → 19-May-27 | Not Started 0% | float 56.0d CO02JM0140 CO01CS0120 — 01C Erect Misc Steel | 15-May-27 → 28-May-27 | Not Started 0% | float 106.0d CO01CS0120 CO01HS0110 — 01H Erect Structural Steel - Stairs & Platform | 15-May-27 → 11-Jun-27 | Not Started 0% | float 51.0d CO01HS0110 CO02AS0110 — 02A Erect Structural Steel | 15-May-27 → 04-Jun-27 | Not Started 0% | float 103.0d CO02AS0110 CO02CP0140 — 02C SB Pipe Erection | 15-May-27 → 15-Oct-27 | Not Started 0% | float 83.0d CO02CP0140 CO02MM0110 — 02M Set Static Equipment - Gen'l | 15-May-27 → 16-Jun-27 | Not Started 0% | float 147.0d CO02MM0110 CO03BS0120 — 03B Erect Misc Steel - Structure | 15-May-27 → 11-Jun-27 | Not Started 0% | float 169.0d CO03BS0120 CO03FS0120 — 03F Erect Misc Steel | 15-May-27 → 25-Jun-27 | Not Started 0% | float 88.0d CO03FS0120 PO000V2005 — Receive at Site - Insulation Materials | 15-May-27 | Not Started CO01BE0110 — 01B Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO01BE0110 CO01EE0110 — 01E Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 180.0d CO01EE0110 CO01FE0110 — 01F Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 152.0d CO01FE0110 CO01GE0130 — 01G Power Tray, Cable, Terminations | 17-May-27 → 12-Jun-27 | Not Started 0% | float 92.0d CO01GE0130 CO02BC0130 — 02B Install Paving | 17-May-27 → 22-May-27 | Not Started 0% | float 210.0d CO02BC0130 CO03CE0110 — 03C Lighting JB's, Stands, Tray & Cable | 17-May-27 → 12-Jun-27 | Not Started 0% | float 123.0d CO03CE0110 CO03DE0110 — 03D Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO03DE0110 CO03DE0130 — 03D Power/Control JB's, Tray, Cable, Termination | 17-May-27 → 04-Jun-27 | Not Started 0% | float 131.0d CO03DE0130 CO03EE0110 — 03E Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO03EE0110 CO03FE0110 — 03F Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 111.0d CO03FE0110 CO03YE0110 — 03Y Lighting JB's, Stands, Tray & Cable | 17-May-27 → 07-Aug-27 | Not Started 0% | float 162.0d CO03YE0110 CO03YE0130 — 03Y Power/Control JB's, Tray, Cable, Termination | 17-May-27 → 07-Aug-27 | Not Started 0% | float 32.0d CO03YE0130 CO03YI0120 — 03Y Instrument JB's, Field Instr, Tray, Cable | 17-May-27 → 07-Aug-27 | Not Started 0% | float 32.0d CO03YI0120 WO010E0100 — 010 Above Ground Electrical | 17-May-27 → 05-Oct-27 | Not Started 0% | float 131.0d WO010E0100 WO030E0100 — 030 Above Ground Electrical | 17-May-27 → 23-Aug-27 | Not Started 0% | float 153.0d WO030E0100 WO030I0100 — 030 Install Instruments & Test | 17-May-27 → 17-Jan-28 | Not Started 0% | float 41.0d WO030I0100 CO02KM0110 — 02K Set Static Equipment - Gen'l | 17-May-27 → 07-Jun-27 | Not Started 0% | float 101.0d CO02KM0110 CO04AK0110 — 04A Site Prep (Leveling) | 19-May-27 → 05-Oct-27 | Not Started 0% | float 108.0d CO04AK0110 WO04AK0100 — 04A Site Prep (Leveling) | 19-May-27 → 05-Oct-27 | Not Started 0% | float 108.0d WO04AK0100 CO02AV1110 — 02A Paint Fabricated Pipe Spools | 20-May-27 → 02-Jun-27 | Not Started 0% | float 172.0d CO02AV1110 CO02LM0130 — 02L Set (Heavy Lift) - 101-E (CO2 Absorber) | 20-May-27 → 25-May-27 | Not Started 0% | float 56.0d CO02LM0130 CK05BP0110 — 05B A/G Pipe Spool Fabrication | 22-May-27 → 31-May-27 | Not Started 0% | float 49.0d CK05BP0110 CO01YE0110 — 01Y Lighting JB's, Stands, Tray & Cable | 22-May-27 → 02-Jul-27 | Not Started 0% | float 175.0d CO01YE0110 CO02ES0110 — 02E Erect Structural Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 127.0d CO02ES0110 CO02ES0120 — 02E Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 67.0d CO02ES0120 CO02FS0120 — 02F Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 133.0d CO02FS0120 CO02JS0110 — 02J Erect Structural Steel - Structure | 22-May-27 → 04-Jun-27 | Not Started 0% | float 98.0d CO02JS0110 CO02MS0120 — 02M Erect Misc Steel - Structure | 22-May-27 → 11-Jun-27 | Not Started 0% | float 123.0d CO02MS0120 CO03AS0120 — 03A Erect Misc Steel - Structure | 22-May-27 → 18-Jun-27 | Not Started 0% | float 56.0d CO03AS0120 CO03CS0120 — 03C Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 87.0d CO03CS0120 CO03DS0120 — 03D Erect Misc Steel | 22-May-27 → 18-Jun-27 | Not Started 0% | float 98.0d CO03DS0120 CO03ES0120 — 03E Erect Misc Steel - Structure | 22-May-27 → 18-Jun-27 | Not Started 0% | float 58.0d CO03ES0120 CO02BV1110 — 02B Paint Fabricated Pipe Spools | 25-May-27 → 31-May-27 | Not Started 0% | float 175.0d CO02BV1110 CO03FP0130 — 03F LB Pipe Erection | 25-May-27 → 02-Jul-27 | Not Started 0% | float 88.0d CO03FP0130 CO02LM0140 — 02L Set (Heavy Lift) - 102-E (CO2 Stripper) | 26-May-27 → 31-May-27 | Not Started 0% | float 56.0d CO02LM0140 CO02GE0130 — 02G Power/Control JB's, Tray, Cable, Termination | 26-May-27 → 02-Oct-27 | Not Started 0% | float 108.0d CO02GE0130 CO02GI0120 — 02G Instrument JB's, Field Instr, Tray, Cable | 26-May-27 → 02-Oct-27 | Not Started 0% | float 108.0d CO02GI0120 WO020E0100 — 020 Above Ground Electrical | 26-May-27 → 14-Feb-28 | Not Started 0% | float 23.0d WO020E0100 WO020I0100 — 020 Install Instruments & Test | 26-May-27 → 01-Mar-28 | Not Started 0% | float 9.0d WO020I0100 CO02CV2110 — 02C Insulate - Equipment | 28-May-27 → 06-Jul-27 | Not Started 0% | float 190.0d CO02CV2110 WO020V2100 — 020 Insulation | 28-May-27 → 13-Mar-28 | Not Started 0% | float -1.0d WO020V2100 CO01CE0110 — 01C Lighting JB's, Stands, Tray & Cable | 29-May-27 → 18-Jun-27 | Not Started 0% | float 124.0d CO01CE0110 CO01YP0140 — 01Y SB Pipe Erection - Pipe Rack | 29-May-27 → 23-Jul-27 | Not Started 0% | float 39.0d CO01YP0140 CO02DM0110 — 02D Set Static Equipment | 29-May-27 → 11-Jun-27 | Not Started 0% | float 133.0d CO02DM0110 CO02DS0120 — 02D Erect Misc Steel | 29-May-27 → 18-Jun-27 | Not Started 0% | float 93.0d CO02DS0120 CO02EP0130 — 02E LB Pipe Erection | 29-May-27 → 06-Nov-27 | Not Started 0% | float 67.0d CO02EP0130 CO02HM0260 — 02H Compete Installation of Ducts (101-B) | 29-May-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02HM0260 CO03AP0130 — 03A LB Pipe Erection | 29-May-27 → 07-Jul-27 | Not Started 0% | float 56.0d CO03AP0130 CO03CP0130 — 03C LB Pipe Erection | 29-May-27 → 07-Jul-27 | Not Started 0% | float 87.0d CO03CP0130 CO03EP0130 — 03E LB Pipe Erection | 29-May-27 → 30-Jul-27 | Not Started 0% | float 58.0d CO03EP0130 CO03YV1120 — 03Y Paint Touch-up - Piping | 29-May-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO03YV1120 CO05BV1110 — 05B Paint Fabricated Pipe Spools | 29-May-27 → 07-Jun-27 | Not Started 0% | float 214.0d CO05BV1110 CO02HM0215 — 02H Erect Fuel Gas Lines (101-B) | 31-May-27 → 26-Jun-27 | Not Started 0% | float 151.0d CO02HM0215 CO02HM0227 — 02H Install Spring Hangers & Align (101-B) | 31-May-27 → 10-Jul-27 | Not Started 0% | float 186.0d CO02HM0227 CO02HM0245 — 02H Install Insulation (101-B) | 31-May-27 → 24-Jul-27 | Not Started 0% | float 174.0d CO02HM0245 CO01CA0110 — 01C Erect - EDR Shelter | 31-May-27 → 21-Jun-27 | Not Started 0% | float 98.0d CO01CA0110 CO01AK0150 — 01A Excavate Evaporation Pond | 01-Jun-27 → 12-Jul-27 | Not Started 0% | float 54.0d CO01AK0150 CO02CE0130 — 02C Power/Control JB's, Tray, Cable, Termination | 01-Jun-27 → 22-Oct-27 | Not Started 0% | float 88.0d CO02CE0130 CO02CI0120 — 02C Instrument JB's, Field Instr, Tray, Cable | 01-Jun-27 → 22-Oct-27 | Not Started 0% | float 88.0d CO02CI0120 CO02JM0110 — 02J Set Static Equipment - Gen'l | 01-Jun-27 → 11-Jun-27 | Not Started 0% | float 98.0d CO02JM0110 CO02MM0130 — 02M Set (Heavy Lift) - 105-D (Ammonia Converter) | 01-Jun-27 → 05-Jun-27 | Not Started 0% | float 56.0d CO02MM0130 CO03FP0140 — 03F SB Pipe Erection | 01-Jun-27 → 09-Jul-27 | Not Started 0% | float 88.0d CO03FP0140 WO010K0100 — 010 Site Prep | 01-Jun-27 → 28-Jan-28 | Not Started 0% | float 37.0d WO010K0100 CO01DE0110 — 01D Lighting JB's, Stands, Tray & Cable | 02-Jun-27 → 13-Jul-27 | Not Started 0% | float 66.0d CO01DE0110 CO03YP0150 — 03Y Punchlist / Test Piping | 02-Jun-27 → 23-Jul-27 | Not Started 0% | float 139.0d CO03YP0150 CO01BV1130 — 01B Paint Touch-up - Equipment | 03-Jun-27 → 25-Jun-27 | Not Started 0% | float 100.0d CO01BV1130 PO05AS0000 — 05A Recv at Site - Structural Steel | 04-Jun-27 | Not Started PO05AS0010 — 05A Recv at Site - Misc Steel | 04-Jun-27 | Not Started CO02AM0110 — 02A Set Static Equipment | 05-Jun-27 → 18-Jun-27 | Not Started 0% | float 144.0d CO02AM0110 CO02JS0120 — 02J Erect Misc Steel - Structure | 05-Jun-27 → 11-Jun-27 | Not Started 0% | float 98.0d CO02JS0120 CO02LE0110 — 02L Lighting JB's, Stands, Tray & Cable | 05-Jun-27 → 16-Jul-27 | Not Started 0% | float 163.0d CO02LE0110 CO03AP0140 — 03A SB Pipe Erection | 05-Jun-27 → 14-Jul-27 | Not Started 0% | float 56.0d CO03AP0140 CO03CP0140 — 03C SB Pipe Erection | 05-Jun-27 → 14-Jul-27 | Not Started 0% | float 87.0d CO03CP0140 CO03EP0140 — 03E SB Pipe Erection | 05-Jun-27 → 06-Aug-27 | Not Started 0% | float 58.0d CO03EP0140 CO03FV2110 — 03F Insulate - Equipment | 05-Jun-27 → 19-Jun-27 | Not Started 0% | float 135.0d CO03FV2110 WO030V2100 — 030 Insulation | 05-Jun-27 → 02-Oct-27 | Not Started 0% | float 133.0d WO030V2100 CO02FV2110 — 02F Insulate - Equipment | 07-Jun-27 → 24-Jun-27 | Not Started 0% | float 200.0d CO02FV2110 CO02MM0140 — 02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.) | 07-Jun-27 → 11-Jun-27 | Not Started 0% | float 56.0d CO02MM0140 CO03DP0130 — 03D LB Pipe Erection | 07-Jun-27 → 25-Jun-27 | Not Started 0% | float 98.0d CO03DP0130 CO01CP0130 — 01C LB Pipe Erection | 07-Jun-27 → 28-Jun-27 | Not Started 0% | float 93.0d CO01CP0130 CO02KS0120 — 02K Erect Misc Steel | 07-Jun-27 → 28-Jun-27 | Not Started 0% | float 101.0d CO02KS0120 CO01DV1130 — 01D Paint Touch-up - Equipment | 08-Jun-27 → 25-Jun-27 | Not Started 0% | float 88.0d CO01DV1130 CO03FE0130 — 03F Power/Control JB's, Tray, Cable, Termination | 08-Jun-27 → 16-Jul-27 | Not Started 0% | float 97.0d CO03FE0130 CO03FI0120 — 03F Instrument JB's, Field Instr, Tray, Cable | 08-Jun-27 → 16-Jul-27 | Not Started 0% | float 97.0d CO03FI0120 CO02KV2110 — 02K Insulate - Equipment | 10-Jun-27 → 05-Jul-27 | Not Started 0% | float 192.0d CO02KV2110 CO01BP0130 — 01B LB Pipe Erection | 12-Jun-27 → 21-Sep-27 | Not Started 0% | float 32.0d CO01BP0130 CO01DP0130 — 01D LB Pipe Erection | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 34.0d CO01DP0130 CO01HE0110 — 01H Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 69.0d CO01HE0110 CO02AS0120 — 02A Erect Misc Steel | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 103.0d CO02AS0120 CO02BE0110 — 02B Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 25-Jun-27 | Not Started 0% | float 193.0d CO02BE0110 CO02EE0110 — 02E Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02EE0110 CO02EM0110 — 02E Set Static Equipment | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 127.0d CO02EM0110 CO02FE0110 — 02F Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02FE0110 CO02JE0110 — 02J Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 23-Jul-27 | Not Started 0% | float 157.0d CO02JE0110 CO02JP0130 — 02J LB Pipe Erection | 12-Jun-27 → 27-Sep-27 | Not Started 0% | float 98.0d CO02JP0130 CO02ME0110 — 02M Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 09-Jul-27 | Not Started 0% | float 175.0d CO02ME0110 CO02MV1130 — 02M Paint Touch-up - Equipment | 12-Jun-27 → 29-Jun-27 | Not Started 0% | float 172.0d CO02MV1130 CO02NM0110 — 02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller) | 12-Jun-27 → 17-Jun-27 | Not Started 0% | float 56.0d CO02NM0110 CO03AE0130 — 03A Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 56.0d CO03AE0130 CO03AI0120 — 03A Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 56.0d CO03AI0120 CO03BE0110 — 03B Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 187.0d CO03BE0110 CO03CE0130 — 03C Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CE0130 CO03CI0120 — 03C Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CI0120 CO03EE0130 — 03E Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 61.0d CO03EE0130 CO03EI0120 — 03E Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 61.0d CO03EI0120 PO05BS0010 — 05B Recv at Site - Misc Steel | 12-Jun-27 | Not Started CO02BV2110 — 02B Insulate - Equipment | 14-Jun-27 → 19-Jun-27 | Not Started 0% | float 204.0d CO02BV2110 CO03CE0120 — 03C Lighting Fixture Installation/Termination | 14-Jun-27 → 26-Jun-27 | Not Started 0% | float 123.0d CO03CE0120 CO01CP0140 — 01C SB Pipe Erection | 14-Jun-27 → 05-Jul-27 | Not Started 0% | float 93.0d CO01CP0140 CO02PM0110 — 02P Set 101-U Dearator | 15-Jun-27 → 28-Jun-27 | Not Started 0% | float 103.0d CO02PM0110 CO02QM0110 — 02Q Set 101-F Steam Drum | 15-Jun-27 → 21-Jun-27 | Not Started 0% | float 101.0d CO02QM0110 CO05BC0110 — 05B Form, Pour, Strip Fnds - Sleepers | 15-Jun-27 → 30-Jul-27 | Not Started 0% | float 152.0d CO05BC0110 CO03DP0140 — 03D SB Pipe Erection | 15-Jun-27 → 05-Jul-27 | Not Started 0% | float 97.0d CO03DP0140 CO05AC0110 — 05A Form, Pour, Strip Fnds - Major Fnds Gen'l | 17-Jun-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AC0110 CO05AU3110 — 05A U/G Earthing Installation | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d CO05AU3110 CO05UP0150 — 05U LB Pipe Erection (Firewater Piping) | 17-Jun-27 → 30-Sep-27 | Not Started 0% | float 135.0d CO05UP0150 WO050U3100 — 050 Install U/G Electrical | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d WO050U3100 CO02NS0120 — 02N Erect Misc Steel | 18-Jun-27 → 22-Jul-27 | Not Started 0% | float 56.0d CO02NS0120 CO01BP0140 — 01B SB Pipe Erection | 19-Jun-27 → 28-Sep-27 | Not Started 0% | float 32.0d CO01BP0140 CO01CE0120 — 01C Lighting Fixture Installation/Termination | 19-Jun-27 → 25-Jun-27 | Not Started 0% | float 124.0d CO01CE0120 CO01DP0140 — 01D SB Pipe Erection | 19-Jun-27 → 27-Aug-27 | Not Started 0% | float 34.0d CO01DP0140 CO01HE0140 — 01H Set Transformers TR-100/ 103/ 104/ 105 | 19-Jun-27 → 02-Jul-27 | Not Started 0% | float 33.0d CO01HE0140 CO01YE0130 — 01Y Power/Control JB's, Tray, Cable, Termination | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 39.0d CO01YE0130 CO01YI0120 — 01Y Instrument JB's, Field Instr, Tray, Cable | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 39.0d CO01YI0120 CO01YV1120 — 01Y Paint Touch-up - Piping | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 169.0d CO01YV1120 CO02DE0110 — 02D Lighting JB's, Stands, Tray & Cable | 19-Jun-27 → 16-Jul-27 | Not Started 0% | float 169.0d CO02DE0110 CO02JP0140 — 02J SB Pipe Erection | 19-Jun-27 → 04-Oct-27 | Not Started 0% | float 98.0d CO02JP0140 CO02LM0110 — 02L Set Static Equipment - Gen'l | 19-Jun-27 → 21-Jul-27 | Not Started 0% | float 103.0d CO02LM0110 CO02LM0120 — 02L Set Static Equipment - 02L Structure | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float -15.0d CO02LM0120 CO03AE0110 — 03A Lighting JB's, Stands, Tray & Cable | 19-Jun-27 → 09-Jul-27 | Not Started 0% | float 75.0d CO03AE0110 WO010I0100 — 010 Install Instruments & Test | 19-Jun-27 → 03-Jan-28 | Not Started 0% | float 53.0d WO010I0100 CO01CE0130 — 01C Power/Control JB's, Tray, Cable, Termination | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO01CE0130 CO01CI0120 — 01C Instrument JB's, Field Instr, Tray, Cable | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO01CI0120 CO01CV1120 — 01C Paint Touch-up - Piping | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 93.0d CO01CV1120 CO01CV1130 — 01C Paint Touch-up - Equipment | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 93.0d CO01CV1130 CO02QS0120 — 02Q Erect Misc Steel | 22-Jun-27 → 12-Jul-27 | Not Started 0% | float 101.0d CO02QS0120 CO03DI0120 — 03D Instrument JB's, Field Instr, Tray, Cable | 22-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO03DI0120 CO01GC0130 — 01G Install Paving - Control Building | 25-Jun-27 → 08-Jul-27 | Not Started 0% | float 70.0d CO01GC0130 CO01GE0110 — 01G Lighting JB's, Stands, Tray & Cable | 25-Jun-27 → 05-Aug-27 | Not Started 0% | float 28.0d CO01GE0110 CO01GE0140 — 01G Install UPS in Control Building | 25-Jun-27 → 15-Jul-27 | Not Started 0% | float -8.0d CO01GE0140 CO01GI0150 — 01G Install DCS | 25-Jun-27 → 25-Aug-27 | Not Started 0% | float -14.0d CO01GI0150 CO02AV2110 — 02A Insulate - Equipment | 25-Jun-27 → 16-Jul-27 | Not Started 0% | float 181.0d CO02AV2110 CO02DV2110 — 02D Insulate - Equipment | 25-Jun-27 → 09-Jul-27 | Not Started 0% | float 187.0d CO02DV2110 CO02NP0130 — 02N LB Pipe Erection | 25-Jun-27 → 10-Nov-27 | Not Started 0% | float 56.0d CO02NP0130 CO01BE0130 — 01B Power/Control JB's, Tray, Cable, Termination | 26-Jun-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BE0130 CO01BI0120 — 01B Instrument JB's, Field Instr, Tray, Cable | 26-Jun-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BI0120 CO01DE0130 — 01D Power/Control JB's, Tray, Cable, Termination | 26-Jun-27 → 10-Sep-27 | Not Started 0% | float 39.0d CO01DE0130 CO01DI0120 — 01D Instrument JB's, Field Instr, Tray, Cable | 26-Jun-27 → 10-Sep-27 | Not Started 0% | float 39.0d CO01DI0120 CO02BE0120 — 02B Lighting Fixture Installation/Termination | 26-Jun-27 → 02-Jul-27 | Not Started 0% | float 193.0d CO02BE0120 CO01BE0120 — 01B Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO01BE0120 CO01EE0120 — 01E Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 180.0d CO01EE0120 CO01FE0120 — 01F Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 152.0d CO01FE0120 CO02MP0130 — 02M LB Pipe Erection | 28-Jun-27 → 08-Oct-27 | Not Started 0% | float 92.0d CO02MP0130 CO03BP0130 — 03B LB Pipe Erection | 28-Jun-27 → 04-Aug-27 | Not Started 0% | float 138.0d CO03BP0130 CO03DE0120 — 03D Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO03DE0120 CO03EE0120 — 03E Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO03EE0120 CO03FE0120 — 03F Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 111.0d CO03FE0120 CO03FP0150 — 03F Punchlist / Test Piping | 28-Jun-27 → 16-Jul-27 | Not Started 0% | float 88.0d CO03FP0150 CO02KE0110 — 02K Lighting JB's, Stands, Tray & Cable | 28-Jun-27 → 09-Aug-27 | Not Started 0% | float 144.0d CO02KE0110 CO02PS0120 — 02P Erect Misc Steel | 29-Jun-27 → 26-Jul-27 | Not Started 0% | float 103.0d CO02PS0120 CO02QP0130 — 02Q LB Pipe Erection | 29-Jun-27 → 28-Sep-27 | Not Started 0% | float 101.0d CO02QP0130 CO02YE0110 — 02Y Lighting JB's, Stands, Tray & Cable | 29-Jun-27 → 12-Oct-27 | Not Started 0% | float 90.0d CO02YE0110 CO03YV2120 — 03Y Insulate - Piping | 30-Jun-27 → 03-Sep-27 | Not Started 0% | float 148.0d CO03YV2120 CO01BV2110 — 01B Insulate - Equipment | 01-Jul-27 → 23-Jul-27 | Not Started 0% | float 100.0d CO01BV2110 CO05AM0145 — 05A Tank Erection 2101-F (Ammonia Storage Tank) | 01-Jul-27 → 25-Feb-28 | Not Started 0% | float -51.0d CO05AM0145 WO010V2100 — 010 Insulation | 01-Jul-27 → 02-Nov-27 | Not Started 0% | float 107.0d WO010V2100 WT050M0100 — 05A Tank Erection | 01-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d WT050M0100 CO01CP0150 — 01C Punchlist / Test Piping | 01-Jul-27 → 12-Jul-27 | Not Started 0% | float 96.0d CO01CP0150 CO02JE0130 — 02J Power/Control JB's, Tray, Cable, Termination | 02-Jul-27 → 11-Oct-27 | Not Started 0% | float 98.0d CO02JE0130 CO02JI0120 — 02J Instrument JB's, Field Instr, Tray, Cable | 02-Jul-27 → 11-Oct-27 | Not Started 0% | float 98.0d CO02JI0120 CO03AP0150 — 03A Punchlist / Test Piping | 02-Jul-27 → 21-Jul-27 | Not Started 0% | float 62.0d CO03AP0150 CO03CP0150 — 03C Punchlist / Test Piping | 02-Jul-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CP0150 CO03DP0150 — 03D Punchlist / Test Piping | 02-Jul-27 → 12-Jul-27 | Not Started 0% | float 97.0d CO03DP0150 CO01HE0120 — 01H Lighting Fixture Installation/Termination | 03-Jul-27 → 16-Jul-27 | Not Started 0% | float 69.0d CO01HE0120 CO01HE0130 — 01H Power/Control JB's, Tray, Cable, Termination | 03-Jul-27 → 10-Sep-27 | Not Started 0% | float 33.0d CO01HE0130 CO01YE0120 — 01Y Lighting Fixture Installation/Termination | 03-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO01YE0120 CO01YP0150 — 01Y Punchlist / Test Piping - Pipe Rack | 03-Jul-27 → 30-Jul-27 | Not Started 0% | float 133.0d CO01YP0150 CO02AE0110 — 02A Lighting JB's, Stands, Tray & Cable | 03-Jul-27 → 30-Jul-27 | Not Started 0% | float 157.0d CO02AE0110 CO02EV1130 — 02E Paint Touch-up - Equipment | 03-Jul-27 → 23-Jul-27 | Not Started 0% | float 151.0d CO02EV1130 CO03BE0120 — 03B Lighting Fixture Installation/Termination | 03-Jul-27 → 09-Jul-27 | Not Started 0% | float 187.0d CO03BE0120 CO02FP0130 — 02F LB Pipe Erection | 05-Jul-27 → 27-Sep-27 | Not Started 0% | float 102.0d CO02FP0130 CO03BP0140 — 03B SB Pipe Erection | 05-Jul-27 → 11-Aug-27 | Not Started 0% | float 138.0d CO03BP0140 CO01DV2110 — 01D Insulate - Equipment | 06-Jul-27 → 23-Jul-27 | Not Started 0% | float 88.0d CO01DV2110 CO02GE0110 — 02G Lighting JB's, Stands, Tray & Cable | 06-Jul-27 → 18-Aug-27 | Not Started 0% | float 149.0d CO02GE0110 CO02PP0130 — 02P LB Pipe Erection | 06-Jul-27 → 21-Sep-27 | Not Started 0% | float 103.0d CO02PP0130 CO03FV1120 — 03F Paint Touch-up - Piping | 06-Jul-27 → 16-Jul-27 | Not Started 0% | float 112.0d CO03FV1120 CO03DV1120 — 03D Paint Touch-up - Piping | 06-Jul-27 → 12-Jul-27 | Not Started 0% | float 111.0d CO03DV1120 CO01CV2120 — 01C Insulate - Piping | 08-Jul-27 → 29-Jul-27 | Not Started 0% | float 96.0d CO01CV2120 CO05AS0110 — 05A Erect Structural Steel - Structure | 09-Jul-27 → 21-Jul-27 | Not Started 0% | float 23.0d CO05AS0110 WO050S0100 — 050 Erect Steel | 09-Jul-27 → 13-Aug-27 | Not Started 0% | float 23.0d WO050S0100 CO02EE0120 — 02E Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02EE0120 CO02FE0120 — 02F Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02FE0120 CO02ME0120 — 02M Lighting Fixture Installation/Termination | 10-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO02ME0120 CO02MV2110 — 02M Insulate - Equipment | 10-Jul-27 → 27-Jul-27 | Not Started 0% | float 172.0d CO02MV2110 CO03AE0120 — 03A Lighting Fixture Installation/Termination | 10-Jul-27 → 16-Jul-27 | Not Started 0% | float 75.0d CO03AE0120 CO03AV1120 — 03A Paint Touch-up - Piping | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 58.0d CO03AV1120 CO03AV1130 — 03A Paint Touch-up - Equipment | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 58.0d CO03AV1130 CO03CV1120 — 03C Paint Touch-up - Piping | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 102.0d CO03CV1120 CO02DP0130 — 02D LB Pipe Erection | 12-Jul-27 → 22-Oct-27 | Not Started 0% | float 62.0d CO02DP0130 CO02FP0140 — 02F SB Pipe Erection | 12-Jul-27 → 04-Oct-27 | Not Started 0% | float 102.0d CO02FP0140 CO03BE0130 — 03B Power/Control JB's, Tray, Cable, Termination | 12-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BE0130 CO03BI0120 — 03B Instrument JB's, Field Instr, Tray, Cable | 12-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BI0120 CO01CI0130 — 01C Install In Line Instruments | 12-Jul-27 → 15-Jul-27 | Not Started 0% | float 96.0d CO01CV2110 — 01C Insulate - Equipment | 12-Jul-27 → 02-Aug-27 | Not Started 0% | float 93.0d CO01CV2110 CO02KP0130 — 02K LB Pipe Erection | 12-Jul-27 → 23-Oct-27 | Not Started 0% | float 77.0d CO02KP0130 CO03DI0130 — 03D Install In Line Instruments | 12-Jul-27 → 14-Jul-27 | Not Started 0% | float 97.0d CO01AE0110 — 01A Lighting JB's, Stands, Tray & Cable | 13-Jul-27 → 26-Jul-27 | Not Started 0% | float 91.0d CO01AE0110 CO01AK0160 — 01A Install Liner at Evaporation Pond | 13-Jul-27 → 18-Aug-27 | Not Started 0% | float 54.0d CO01AK0160 CO01JC0150 — 01K Excavate Pond | 13-Jul-27 → 09-Aug-27 | Not Started 0% | float 55.0d CO01JC0150 CO02QE0110 — 02Q Lighting JB's, Stands, Tray & Cable | 13-Jul-27 → 19-Jul-27 | Not Started 0% | float 162.0d CO02QE0110 CO01DE0120 — 01D Lighting Fixture Installation/Termination | 14-Jul-27 → 03-Aug-27 | Not Started 0% | float 66.0d CO01DE0120 CO03EP0150 — 03E Punchlist / Test Piping | 14-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03EP0150 CO05AM0155 — 05A Tank Erection 2102-F (Ammonia Storage Tank) | 14-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d CO05AM0155 CO03AV2120 — 03A Insulate - Piping | 16-Jul-27 → 30-Jul-27 | Not Started 0% | float 63.0d CO03AV2120 CO02GP0150 — 02G Punchlist / Test Piping | 16-Jul-27 → 02-Oct-27 | Not Started 0% | float 105.0d CO02GP0150 CO02DE0120 — 02D Lighting Fixture Installation/Termination | 17-Jul-27 → 30-Jul-27 | Not Started 0% | float 169.0d CO02DE0120 CO02LE0120 — 02L Lighting Fixture Installation/Termination | 17-Jul-27 → 06-Aug-27 | Not Started 0% | float 163.0d CO02LE0120 CO02LP0130 — 02L LB Pipe Erection | 17-Jul-27 → 31-Jan-28 | Not Started 0% | float -15.0d CO02LP0130 CO02LV1130 — 02L Paint Touch-up - Equipment | 17-Jul-27 → 28-Sep-27 | Not Started 0% | float 69.0d CO02LV1130 CO03FI0130 — 03F Install In Line Instruments | 17-Jul-27 → 20-Jul-27 | Not Started 0% | float 97.0d CO01ET0110 — 01E Mechanical Completion | 17-Jul-27 | Not Started CO01FT0110 — 01F Mechanical Completion | 17-Jul-27 | Not Started SC01ET0120 — 01E RFSU | 17-Jul-27 | Not Started SC01FT0120 — 01F RFSU | 17-Jul-27 | Not Started CO02AP0130 — 02A LB Pipe Erection | 19-Jul-27 → 23-Oct-27 | Not Started 0% | float 78.0d CO02AP0130 CO02BP0130 — 02B LB Pipe Erection | 19-Jul-27 → 16-Aug-27 | Not Started 0% | float 120.0d CO02BP0130 CO02KP0140 — 02K SB Pipe Erection | 19-Jul-27 → 30-Oct-27 | Not Started 0% | float 77.0d CO02KP0140 CO02QE0120 — 02Q Lighting Fixture Installation/Termination | 20-Jul-27 → 26-Jul-27 | Not Started 0% | float 173.0d CO02QE0120 CO02YE0130 — 02Y Power/Control JB's, Tray, Cable, Termination | 20-Jul-27 → 16-Nov-27 | Not Started 0% | float -35.0d CO02YE0130 CO02YI0120 — 02Y Instrument JB's, Field Instr, Tray, Cable | 20-Jul-27 → 16-Nov-27 | Not Started 0% | float -35.0d CO02YI0120 CO02FE0130 — 02F Power/Control JB's, Tray, Cable, Termination | 22-Jul-27 → 11-Oct-27 | Not Started 0% | float 104.0d CO02FE0130 CO02FI0120 — 02F Instrument JB's, Field Instr, Tray, Cable | 22-Jul-27 → 11-Oct-27 | Not Started 0% | float 104.0d CO02FI0120 CO03AI0130 — 03A Install In Line Instruments | 22-Jul-27 → 24-Jul-27 | Not Started 0% | float 62.0d CO03AV2110 — 03A Insulate - Equipment | 22-Jul-27 → 05-Aug-27 | Not Started 0% | float 58.0d CO03AV2110 CO03CI0130 — 03C Install In Line Instruments | 22-Jul-27 → 24-Jul-27 | Not Started 0% | float 87.0d CO02NE0110 — 02N Lighting JB's, Stands, Tray & Cable | 23-Jul-27 → 12-Aug-27 | Not Started 0% | float 152.0d CO02NE0110 CO02NV1130 — 02N Paint Touch-up - Equipment | 23-Jul-27 → 29-Jul-27 | Not Started 0% | float 146.0d CO02NV1130 CO02JE0120 — 02J Lighting Fixture Installation/Termination | 24-Jul-27 → 13-Aug-27 | Not Started 0% | float 157.0d CO02JE0120 CO02LP0140 — 02L SB Pipe Erection | 24-Jul-27 → 07-Feb-28 | Not Started 0% | float -15.0d CO02LP0140 CO03YI0130 — 03Y Install In Line Instruments | 24-Jul-27 → 27-Aug-27 | Not Started 0% | float 139.0d CO03YI0130 CO02HM0275 — 02H Complete Primary Reformer Erection (101-B) | 24-Jul-27 | Not Started CO02AP0140 — 02A SB Pipe Erection | 26-Jul-27 → 30-Oct-27 | Not Started 0% | float 78.0d CO02AP0140 CO01AE0120 — 01A Lighting Fixture Installation/Termination | 27-Jul-27 → 02-Aug-27 | Not Started 0% | float 91.0d CO01AE0120 CO02HP0130 — 02H LB Pipe Erection | 27-Jul-27 → 05-Jan-28 | Not Started 0% | float 10.0d CO02HP0130 CO02MP0140 — 02M SB Pipe Erection | 27-Jul-27 → 15-Oct-27 | Not Started 0% | float 92.0d CO02MP0140 CO02PE0110 — 02P Lighting JB's, Stands, Tray & Cable | 27-Jul-27 → 02-Aug-27 | Not Started 0% | float 150.0d CO02PE0110 CO02YV1120 — 02Y Paint Touch-up - Piping | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1120 CO02YV1130 — 02Y Paint Touch-up - Pipe Rack | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1130 CO03EV1120 — 03E Paint Touch-up - Piping | 27-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03EV1120 CO03EV1130 — 03E Paint Touch-up - Equipment | 27-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03EV1130 CO01DP0150 — 01D Punchlist / Test Piping | 28-Jul-27 → 10-Sep-27 | Not Started 0% | float 34.0d CO01DP0150 CO02CP0150 — 02C Punchlist / Test Piping | 28-Jul-27 → 22-Oct-27 | Not Started 0% | float 83.0d CO02CP0150 CO02HM0120 — 02H Set (Heavey Lift) - 101-C & 102-C | 30-Jul-27 → 04-Aug-27 | Not Started 0% | float 10.0d CO02HM0120 CO03FV2120 — 03F Insulate - Piping | 30-Jul-27 → 13-Aug-27 | Not Started 0% | float 88.0d CO03FV2120 CO02GV1130 — 02G Paint Touch-up - Equipment | 30-Jul-27 → 25-Sep-27 | Not Started 0% | float 116.0d CO02GV1130 CO02KE0130 — 02K Power/Control JB's, Tray, Cable, Termination | 30-Jul-27 → 06-Nov-27 | Not Started 0% | float 77.0d CO02KE0130 CO02KI0120 — 02K Instrument JB's, Field Instr, Tray, Cable | 30-Jul-27 → 06-Nov-27 | Not Started 0% | float 77.0d CO02KI0120 CO01YI0130 — 01Y Install In Line Instruments | 31-Jul-27 → 27-Aug-27 | Not Started 0% | float 139.0d CO01YI0130 CO01YV2120 — 01Y Insulate - Piping | 31-Jul-27 → 02-Oct-27 | Not Started 0% | float 133.0d CO01YV2120 CO02AE0120 — 02A Lighting Fixture Installation/Termination | 31-Jul-27 → 13-Aug-27 | Not Started 0% | float 157.0d CO02AE0120 CO02EV2110 — 02E Insulate - Equipment | 31-Jul-27 → 27-Aug-27 | Not Started 0% | float 151.0d CO02EV2110 CO03BP0150 — 03B Punchlist / Test Piping | 31-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BP0150 CO05BP0130 — 05B LB Pipe Erection - To Loading Arm | 31-Jul-27 → 21-Sep-27 | Not Started 0% | float 152.0d CO05BP0130 WO050P0100 — 050 Above Ground Pipe | 31-Jul-27 → 14-Mar-28 | Not Started 0% | float 19.0d WO050P0100 CO05BM0110 — 05B Install Loading Arm | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 62.0d CO05BM0110 WO050M0100 — 050 Major Equipment | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 61.0d WO050M0100 CO02CE0110 — 02C Lighting JB's, Stands, Tray & Cable | 03-Aug-27 → 05-Oct-27 | Not Started 0% | float 113.0d CO02CE0110 CO02GE0120 — 02G Lighting Fixture Installation/Termination | 03-Aug-27 → 01-Sep-27 | Not Started 0% | float 149.0d CO02GE0120 CO02HP0140 — 02H SB Pipe Erection | 03-Aug-27 → 12-Jan-28 | Not Started 0% | float 10.0d CO02HP0140 CO02PE0120 — 02P Lighting Fixture Installation/Termination | 03-Aug-27 → 09-Aug-27 | Not Started 0% | float 161.0d CO02PE0120 CO01BP0150 — 01B Punchlist / Test Piping | 05-Aug-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BP0150 CO020M0130 — Demobilize Heavy Lift Crane | 05-Aug-27 → 16-Aug-27 | Not Started 0% | float 56.0d CO020M0130 CO02HS0110 — 02H Erect Structural Steel - Structure | 05-Aug-27 → 07-Oct-27 | Not Started 0% | float 10.0d CO02HS0110 CO01GE0120 — 01G Lighting Fixture Installation/Termination | 06-Aug-27 → 08-Sep-27 | Not Started 0% | float 28.0d CO01GE0120 CO02GV1120 — 02G Paint Touch-up - Piping | 06-Aug-27 → 02-Oct-27 | Not Started 0% | float 134.0d CO02GV1120 CO05AS0120 — 05A Erect Misc Steel | 06-Aug-27 → 13-Aug-27 | Not Started 0% | float 23.0d CO05AS0120 CO02AE0130 — 02A Power/Control JB's, Tray, Cable, Termination | 07-Aug-27 → 06-Nov-27 | Not Started 0% | float 78.0d CO02AE0130 CO02AI0120 — 02A Instrument JB's, Field Instr, Tray, Cable | 07-Aug-27 → 06-Nov-27 | Not Started 0% | float 78.0d CO02AI0120 CO02ME0130 — 02M Power/Control JB's, Tray, Cable, Termination | 07-Aug-27 → 22-Oct-27 | Not Started 0% | float 95.0d CO02ME0130 CO02MI0120 — 02M Instrument JB's, Field Instr, Tray, Cable | 07-Aug-27 → 22-Oct-27 | Not Started 0% | float 95.0d CO02MI0120 CO03BV1120 — 03B Paint Touch-up - Piping | 07-Aug-27 → 23-Aug-27 | Not Started 0% | float 153.0d CO03BV1120 CO05BP0140 — 05B SB Pipe Erection - To Loading Arm | 07-Aug-27 → 28-Sep-27 | Not Started 0% | float 152.0d CO05BP0140 CO02BP0140 — 02B SB Pipe Erection | 09-Aug-27 → 30-Aug-27 | Not Started 0% | float 120.0d CO02BP0140 CO02JP0150 — 02J Punchlist / Test Piping | 09-Aug-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JP0150 CO02KE0120 — 02K Lighting Fixture Installation/Termination | 09-Aug-27 → 21-Sep-27 | Not Started 0% | float 144.0d CO02KE0120 CO01DV1120 — 01D Paint Touch-up - Piping | 10-Aug-27 → 10-Sep-27 | Not Started 0% | float 45.0d CO01DV1120 CO02YP0150 — 02Y Punchlist / Test Piping | 10-Aug-27 → 09-Nov-27 | Not Started 0% | float 65.0d CO02YP0150 CO02LE0130 — 02L Power/Control JB's, Tray, Cable, Termination | 11-Aug-27 → 14-Feb-28 | Not Started 0% | float -12.0d CO02LE0130 CO02LI0120 — 02L Instrument JB's, Field Instr, Tray, Cable | 11-Aug-27 → 14-Feb-28 | Not Started 0% | float -12.0d CO02LI0120 CO02NE0120 — 02N Lighting Fixture Installation/Termination | 13-Aug-27 → 25-Aug-27 | Not Started 0% | float 152.0d CO02NE0120 CO02NV2110 — 02N Insulate - Equipment | 13-Aug-27 → 08-Sep-27 | Not Started 0% | float 146.0d CO02NV2110 CO02EP0140 — 02E SB Pipe Erection | 16-Aug-27 → 13-Nov-27 | Not Started 0% | float 67.0d CO02EP0140 CO02LV2110 — 02L Insulate - Equipment | 16-Aug-27 → 26-Oct-27 | Not Started 0% | float 69.0d CO02LV2110 CO03EI0130 — 03E Install In Line Instruments | 16-Aug-27 → 25-Aug-27 | Not Started 0% | float 65.0d CO03EI0130 CO01AM0150 — 01A Install Spray Devices | 20-Aug-27 → 01-Sep-27 | Not Started 0% | float 54.0d CO01AM0150 CO03EV2110 — 03E Insulate - Equipment | 20-Aug-27 → 02-Oct-27 | Not Started 0% | float 58.0d CO03EV2110 CO03EV2120 — 03E Insulate - Piping | 20-Aug-27 → 02-Oct-27 | Not Started 0% | float 58.0d CO03EV2120 CO02HE0130 — 02H Power/Control JB's, Tray, Cable, Termination | 23-Aug-27 → 19-Jan-28 | Not Started 0% | float 15.0d CO02HE0130 CO02HI0120 — 02H Instrument JB's, Field Instr, Tray, Cable | 23-Aug-27 → 19-Jan-28 | Not Started 0% | float 15.0d CO02HI0120 CO05AM0160 — 05A Tank Erection 2105-F (Fire Water Tank) | 23-Aug-27 → 16-Oct-27 | Not Started 0% | float -29.0d CO05AM0160 CO02FP0150 — 02F Punchlist / Test Piping | 25-Aug-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02FP0150 CO03BI0130 — 03B Install In Line Instruments | 25-Aug-27 → 30-Aug-27 | Not Started 0% | float 138.0d CO03BI0130 CO01BV1120 — 01B Paint Touch-up - Piping | 30-Aug-27 → 05-Oct-27 | Not Started 0% | float 56.0d CO01BV1120 CO02BE0130 — 02B Power/Control JB's, Tray, Cable, Termination | 30-Aug-27 → 20-Sep-27 | Not Started 0% | float 136.0d CO02BE0130 CO02BI0120 — 02B Instrument JB's, Field Instr, Tray, Cable | 30-Aug-27 → 20-Sep-27 | Not Started 0% | float 136.0d CO02BI0120 CO02PP0140 — 02P SB Pipe Erection | 30-Aug-27 → 28-Sep-27 | Not Started 0% | float 103.0d CO02PP0140 CO02BP0150 — 02B Punchlist / Test Piping | 01-Sep-27 → 20-Sep-27 | Not Started 0% | float 120.0d CO02BP0150 CO02BV1120 — 02B Paint Touch-up - Piping | 01-Sep-27 → 20-Sep-27 | Not Started 0% | float 144.0d CO02BV1120 CO02CV1120 — 02C Paint Touch-up - Piping | 01-Sep-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02CV1120 CO01AE0130 — 01A Power/Control JB's, Tray, Cable, Termination | 03-Sep-27 → 21-Sep-27 | Not Started 0% | float 66.0d CO01AE0130 CO01AP0130 — 01A LB Pipe Erection | 03-Sep-27 → 28-Sep-27 | Not Started 0% | float 54.0d CO01AP0130 CO02GV2120 — 02G Insulate - Piping | 03-Sep-27 → 30-Oct-27 | Not Started 0% | float 110.0d CO02GV2120 CO02JV1120 — 02J Paint Touch-up - Piping | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JV1120 CO02JV1130 — 02J Paint Touch-up - Equipment | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JV1130 CO02EE0130 — 02E Power/Control JB's, Tray, Cable, Termination | 08-Sep-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EE0130 CO02EI0120 — 02E Instrument JB's, Field Instr, Tray, Cable | 08-Sep-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EI0120 CO02HV1130 — 02H Paint Touch-up - Equipment | 10-Sep-27 → 28-Oct-27 | Not Started 0% | float 52.0d CO02HV1130 CO02GV2110 — 02G Insulate - Equipment | 10-Sep-27 → 23-Oct-27 | Not Started 0% | float 116.0d CO02GV2110 CO01HT0110 — 01H Mechanical Completion | 10-Sep-27 | Not Started CO01DI0130 — 01D Install In Line Instruments | 20-Sep-27 → 24-Sep-27 | Not Started 0% | float 41.0d CO01DI0130 CO02QP0140 — 02Q SB Pipe Erection | 20-Sep-27 → 05-Oct-27 | Not Started 0% | float 101.0d CO02QP0140 CO02BI0130 — 02B Install In Line Instruments | 21-Sep-27 → 22-Sep-27 | Not Started 0% | float 130.0d CO02PI0120 — 02P Instrument JB's, Field Instr, Tray, Cable | 21-Sep-27 → 05-Oct-27 | Not Started 0% | float 121.0d CO02PI0120 CO05BA0110 — 05B Erect Dock Control Operating Building | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d CO05BA0110 WO050A0100 — 050 Buildings | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d WO050A0100 CO01DV2120 — 01D Insulate - Piping | 23-Sep-27 → 16-Oct-27 | Not Started 0% | float 34.0d CO01DV2120 CO02FV1120 — 02F Paint Touch-up - Piping | 23-Sep-27 → 11-Oct-27 | Not Started 0% | float 126.0d CO02FV1120 CO02HE0110 — 02H Lighting JB's, Stands, Tray & Cable | 24-Sep-27 → 04-Nov-27 | Not Started 0% | float 87.0d CO02HE0110 CO02MP0150 — 02M Punchlist / Test Piping | 24-Sep-27 → 22-Oct-27 | Not Started 0% | float 92.0d CO02MP0150 CO05BV1120 — 05B Paint Touch-up - Piping | 27-Sep-27 → 05-Oct-27 | Not Started 0% | float 170.0d CO05BV1120 CO02KP0150 — 02K Punchlist / Test Piping | 27-Sep-27 → 06-Nov-27 | Not Started 0% | float 80.0d CO02KP0150 CO02PP0150 — 02P Punchlist / Test Piping | 28-Sep-27 → 05-Oct-27 | Not Started 0% | float 107.0d CO02PP0150 CO02QI0120 — 02Q Instrument JB's, Field Instr, Tray, Cable | 28-Sep-27 → 12-Oct-27 | Not Started 0% | float 115.0d CO02QI0120 CO01AI0120 — 01A Instrument JB's, Field Instr, Tray, Cable | 29-Sep-27 → 05-Oct-27 | Not Started 0% | float 54.0d CO01AI0120 CO01AP0150 — 01A Punchlist / Test Piping | 29-Sep-27 → 01-Oct-27 | Not Started 0% | float 57.0d CO01AV1120 — 01A Paint Touch-up - Piping | 29-Sep-27 → 01-Oct-27 | Not Started 0% | float 58.0d CO02CV2120 — 02C Insulate - Piping | 29-Sep-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02CV2120 CO02PV1130 — 02P Paint Touch-up - Equipment | 29-Sep-27 → 02-Oct-27 | Not Started 0% | float 103.0d CO02YV2120 — 02Y Insulate - Piping | 29-Sep-27 → 27-Dec-27 | Not Started 0% | float 65.0d CO02YV2120 CO02DP0140 — 02D SB Pipe Erection | 30-Sep-27 → 25-Nov-27 | Not Started 0% | float 62.0d CO02DP0140 CO02AP0150 — 02A Punchlist / Test Piping | 01-Oct-27 → 06-Nov-27 | Not Started 0% | float 79.0d CO02AP0150 CO02PV1120 — 02P Paint Touch-up - Piping | 01-Oct-27 → 05-Oct-27 | Not Started 0% | float 125.0d CO02PV1120 CO01AI0130 — 01A Install In Line Instruments | 02-Oct-27 → 02-Oct-27 | Not Started 0% | float 57.0d CO01BV2120 — 01B Insulate - Piping | 02-Oct-27 → 02-Nov-27 | Not Started 0% | float 32.0d CO01BV2120 CO02GI0130 — 02G Install In Line Instruments | 02-Oct-27 → 13-Oct-27 | Not Started 0% | float 105.0d CO02GI0130 CO02QP0150 — 02Q Punchlist / Test Piping | 05-Oct-27 → 12-Oct-27 | Not Started 0% | float 101.0d CO02QP0150 CO04AT0110 — 04A Mechanical Completion | 05-Oct-27 | Not Started CO01BI0130 — 01B Install In Line Instruments | 06-Oct-27 → 13-Oct-27 | Not Started 0% | float 37.0d CO01BI0130 CO01GI0120 — 01G DCS Cable Terminations | 06-Oct-27 → 06-Dec-27 | Not Started 0% | float -35.0d CO01GI0120 CO02CE0120 — 02C Lighting Fixture Installation/Termination | 06-Oct-27 → 26-Oct-27 | Not Started 0% | float 113.0d CO02CE0120 CO02JV2120 — 02J Insulate - Piping | 06-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2120 CO02MV1120 — 02M Paint Touch-up - Piping | 06-Oct-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02MV1120 CO02PI0130 — 02P Install In Line Instruments | 06-Oct-27 → 06-Oct-27 | Not Started 0% | float 118.0d CO02QV1120 — 02Q Paint Touch-up - Piping | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02QV1130 — 02Q Paint Touch-up - Equipment | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02DE0130 — 02D Power/Control JB's, Tray, Cable, Termination | 11-Oct-27 → 02-Dec-27 | Not Started 0% | float 68.0d CO02DE0130 CO02DI0120 — 02D Instrument JB's, Field Instr, Tray, Cable | 11-Oct-27 → 02-Dec-27 | Not Started 0% | float 68.0d CO02DI0120 CO02QV2110 — 02Q Insulate - Equipment | 11-Oct-27 → 16-Oct-27 | Not Started 0% | float 121.0d CO02QV2110 CO02BV2120 — 02B Insulate - Piping | 12-Oct-27 → 18-Oct-27 | Not Started 0% | float 120.0d CO02BV2120 CO02FI0130 — 02F Install In Line Instruments | 12-Oct-27 → 16-Oct-27 | Not Started 0% | float 109.0d CO02FI0130 CO02JI0130 — 02J Install In Line Instruments | 12-Oct-27 → 19-Oct-27 | Not Started 0% | float 104.0d CO02JI0130 CO02QI0130 — 02Q Install In Line Instruments | 13-Oct-27 → 13-Oct-27 | Not Started 0% | float 112.0d CO02YE0120 — 02Y Lighting Fixture Installation/Termination | 13-Oct-27 → 27-Nov-27 | Not Started 0% | float 90.0d CO02YE0120 CO02KV1120 — 02K Paint Touch-up - Piping | 13-Oct-27 → 06-Nov-27 | Not Started 0% | float 104.0d CO02KV1120 CO02FV2120 — 02F Insulate - Piping | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02FV2120 CO02JV2110 — 02J Insulate - Equipment | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2110 CO02AV1120 — 02A Paint Touch-up - Piping | 16-Oct-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02AV1120 CO02HV2110 — 02H Insulate - Equipment | 16-Oct-27 → 01-Dec-27 | Not Started 0% | float 52.0d CO02HV2110 SC01HT0120 — 01H RFSU | 17-Oct-27 | Not Started CO02EP0150 — 02E Punchlist / Test Piping | 18-Oct-27 → 26-Nov-27 | Not Started 0% | float 67.0d CO02EP0150 CO05BE0130 — 05B Power/Control JB's, Tray, Cable, Termination | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BE0130 CO05BI0120 — 05B Instrument JB's, Field Instr, Tray, Cable | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BI0120 WO050E0100 — 050 Above Ground Electrical | 19-Oct-27 → 06-Apr-28 | Not Started 0% | float 8.0d WO050E0100 WO050I0100 — 050 Install Instruments & Test | 19-Oct-27 → 25-Mar-28 | Not Started 0% | float 24.0d WO050I0100 CO02CI0130 — 02C Install In Line Instruments | 23-Oct-27 → 04-Nov-27 | Not Started 0% | float 83.0d CO02CI0130 CO02MI0130 — 02M Install In Line Instruments | 23-Oct-27 → 28-Oct-27 | Not Started 0% | float 99.0d CO02MI0130 CO02PV2120 — 02P Insulate - Piping | 27-Oct-27 → 02-Nov-27 | Not Started 0% | float 107.0d CO02PV2120 CO02MV2120 — 02M Insulate - Piping | 28-Oct-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02MV2120 CO05AM0110 — 05A Set 2202-B Flare & KO Drum | 28-Oct-27 → 04-Dec-27 | Not Started 0% | float 21.0d CO05AM0110 CO05AM0130 — 05A Set 2101-L Ammonia Refrigeration Package | 28-Oct-27 → 30-Oct-27 | Not Started 0% | float 46.0d CO05AM0150 — 05A Set Rotating Equipment | 28-Oct-27 → 17-Nov-27 | Not Started 0% | float 31.0d CO05AM0150 CO010K0130 — 010 Compl Roads, Ditches, Paving, & Rock Surfacing | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 9.0d CO010K0130 CO010K0140 — 010 Finish Grading | 01-Nov-27 → 28-Jan-28 | Not Started 0% | float 37.0d CO010K0140 CO020K0100 — 020 Site Prep - Guard Posts & Gravel | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d CO020K0100 CO02EV1120 — 02E Paint Touch-up - Piping | 01-Nov-27 → 26-Nov-27 | Not Started 0% | float 91.0d CO02EV1120 CO02PV2110 — 02P Insulate - Equipment | 01-Nov-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02PV2110 CO030K0100 — 030 Site Prep - Guard Posts & Gravel | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d CO030K0100 WO020K0100 — 020 Site Prep | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d WO020K0100 WO030K0100 — 030 Site Prep | 01-Nov-27 → 01-Mar-28 | Not Started 0% | float 9.0d WO030K0100 CO02DP0150 — 02D Punchlist / Test Piping | 02-Nov-27 → 02-Dec-27 | Not Started 0% | float 62.0d CO02DP0150 CO02KV2120 — 02K Insulate - Piping | 02-Nov-27 → 10-Dec-27 | Not Started 0% | float 80.0d CO02KV2120 SC04AT0120 — 04A RFSU | 02-Nov-27 | Not Started CO02QV2120 — 02Q Insulate - Piping | 03-Nov-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02QV2120 CO05AP0130 — 05A LB Pipe Erection | 04-Nov-27 → 29-Feb-28 | Not Started 0% | float -29.0d CO05AP0130 CO02AV2120 — 02A Insulate - Piping | 05-Nov-27 → 10-Dec-27 | Not Started 0% | float 79.0d CO02AV2120 CO02HE0120 — 02H Lighting Fixture Installation/Termination | 05-Nov-27 → 01-Dec-27 | Not Started 0% | float 87.0d CO02HE0120 CO02KI0130 — 02K Install In Line Instruments | 06-Nov-27 → 15-Nov-27 | Not Started 0% | float 83.0d CO02KI0130 CO02AI0130 — 02A Install In Line Instruments | 08-Nov-27 → 13-Nov-27 | Not Started 0% | float 84.0d CO02AI0130 CO02NP0140 — 02N SB Pipe Erection | 08-Nov-27 → 17-Nov-27 | Not Started 0% | float 56.0d CO02NP0140 CO02YI0130 — 02Y Install In Line Instruments | 10-Nov-27 → 13-Dec-27 | Not Started 0% | float 65.0d CO02YI0130 CO02HP0150 — 02H Punchlist / Test Piping | 11-Nov-27 → 19-Jan-28 | Not Started 0% | float 10.0d CO02HP0150 CO05AP0140 — 05A SB Pipe Erection | 11-Nov-27 → 07-Mar-28 | Not Started 0% | float -29.0d CO05AP0140 CO02DV1120 — 02D Paint Touch-up - Piping | 12-Nov-27 → 02-Dec-27 | Not Started 0% | float 86.0d CO02DV1120 CO02NE0130 — 02N Power/Control JB's, Tray, Cable, Termination | 15-Nov-27 → 30-Nov-27 | Not Started 0% | float 80.0d CO02NE0130 CO02NI0120 — 02N Instrument JB's, Field Instr, Tray, Cable | 15-Nov-27 → 30-Nov-27 | Not Started 0% | float 80.0d CO02NI0120 CO02LP0150 — 02L Punchlist / Test Piping | 16-Nov-27 → 14-Feb-28 | Not Started 0% | float -15.0d CO02LP0150 CO02NV1120 — 02N Paint Touch-up - Piping | 18-Nov-27 → 30-Nov-27 | Not Started 0% | float 88.0d CO02NV1120 CO05AE0130 — 05A Power/Control JB's, Tray, Cable, Termination | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AE0130 CO05AI0120 — 05A Instrument JB's, Field Instr, Tray, Cable | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AI0120 CO02NP0150 — 02N Punchlist / Test Piping | 26-Nov-27 → 30-Nov-27 | Not Started 0% | float 56.0d CO02NP0150 CO02EI0130 — 02E Install In Line Instruments | 27-Nov-27 → 03-Dec-27 | Not Started 0% | float 73.0d CO02EI0130 CO02EV2120 — 02E Insulate - Piping | 27-Nov-27 → 24-Dec-27 | Not Started 0% | float 67.0d CO02EV2120 CO02NI0130 — 02N Install In Line Instruments | 01-Dec-27 → 01-Dec-27 | Not Started 0% | float 75.0d CO02DI0130 — 02D Install In Line Instruments | 03-Dec-27 → 07-Dec-27 | Not Started 0% | float 70.0d CO02DI0130 CO01GT0110 — 01G Mechanical Completion | 06-Dec-27 | Not Started SC01GT0120 — 01G RFSU | 06-Dec-27 | Not Started CO01DI0140 — 01D Continuity Testing | 07-Dec-27 → 11-Dec-27 | Not Started 0% | float -22.0d CO01DI0140 CO02GI0140 — 02G Continuity Testing | 07-Dec-27 → 16-Dec-27 | Not Started 0% | float 54.0d CO02GI0140 CO02YI0140 — 02Y Continuity Testing | 07-Dec-27 → 03-Jan-28 | Not Started 0% | float 53.0d CO02YI0140 CO03AI0140 — 03A Continuity Testing | 07-Dec-27 → 09-Dec-27 | Not Started 0% | float -35.0d CO03YI0140 — 03Y Continuity Testing | 07-Dec-27 → 17-Jan-28 | Not Started 0% | float 41.0d CO03YI0140 CO05BI0140 — 05B Continuity Testing | 07-Dec-27 → 07-Dec-27 | Not Started 0% | float 118.0d SC02GI0150 — 02G Function Testing | 07-Dec-27 → 09-Jan-28 | Not Started 0% | float 63.0d SC02GI0150 WC000T1100 — 000 Commissioning | 07-Dec-27 → 22-Sep-28 | Not Started 0% | float -59.0d WC000T1100 CO03AT0110 — 03A Mechanical Completion | 09-Dec-27 | Not Started CO02DV2120 — 02D Insulate - Piping | 10-Dec-27 → 30-Dec-27 | Not Started 0% | float 62.0d CO02DV2120 CO02HV1120 — 02H Paint Touch-up - Piping | 10-Dec-27 → 19-Jan-28 | Not Started 0% | float 45.0d CO02HV1120 CO03FI0140 — 03F Continuity Testing | 10-Dec-27 → 13-Dec-27 | Not Started 0% | float -1.0d SC03AI0150 — 03A Function Testing | 10-Dec-27 → 20-Dec-27 | Not Started 0% | float -47.0d SC03AI0150 CO01DT0110 — 01D Mechanical Completion | 11-Dec-27 | Not Started SC01DI0150 — 01D Function Testing | 12-Dec-27 → 29-Dec-27 | Not Started 0% | float -28.0d SC01DI0150 CO03FT0110 — 03F Mechanical Completion | 13-Dec-27 | Not Started CO01YI0140 — 01Y Continuity Testing | 14-Dec-27 → 03-Jan-28 | Not Started 0% | float 53.0d CO01YI0140 CO02AI0140 — 02A Continuity Testing | 14-Dec-27 → 20-Dec-27 | Not Started 0% | float 52.0d CO02AI0140 CO02BI0140 — 02B Continuity Testing | 14-Dec-27 → 15-Dec-27 | Not Started 0% | float 73.0d SC03FI0150 — 03F Function Testing | 14-Dec-27 → 24-Dec-27 | Not Started 0% | float -2.0d SC03FI0150 CO02KI0140 — 02K Continuity Testing | 15-Dec-27 → 22-Dec-27 | Not Started 0% | float 48.0d CO02KI0140 CO02BT0110 — 02B Mechanical Completion | 15-Dec-27 | Not Started CO02DI0140 — 02D Continuity Testing | 16-Dec-27 → 20-Dec-27 | Not Started 0% | float 59.0d CO02DI0140 SC02BI0150 — 02B Function Testing | 16-Dec-27 → 18-Dec-27 | Not Started 0% | float 85.0d CO02GT0110 — 02G Mechanical Completion | 16-Dec-27 | Not Started CO02CI0140 — 02C Continuity Testing | 17-Dec-27 → 29-Dec-27 | Not Started 0% | float 41.0d CO02CI0140 SC02CI0150 — 02C Function Testing | 17-Dec-27 → 24-Jan-28 | Not Started 0% | float 48.0d SC02CI0150 SC02YI0150 — 02Y Function Testing | 18-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC02YI0150 SC02BT0120 — 02B RFSU | 18-Dec-27 | Not Started CO02AT0110 — 02A Mechanical Completion | 20-Dec-27 | Not Started CO02DT0110 — 02D Mechanical Completion | 20-Dec-27 | Not Started SC03AT0120 — 03A RFSU | 20-Dec-27 | Not Started CO01BI0140 — 01B Continuity Testing | 21-Dec-27 → 28-Dec-27 | Not Started 0% | float -29.0d CO01BI0140 CO01CI0140 — 01C Continuity Testing | 21-Dec-27 → 23-Dec-27 | Not Started 0% | float -12.0d CO02EI0140 — 02E Continuity Testing | 21-Dec-27 → 27-Dec-27 | Not Started 0% | float 47.0d CO02EI0140 CO02JI0140 — 02J Continuity Testing | 21-Dec-27 → 28-Dec-27 | Not Started 0% | float 42.0d CO02JI0140 CO02MI0140 — 02M Continuity Testing | 21-Dec-27 → 25-Dec-27 | Not Started 0% | float 51.0d CO02MI0140 CO03BI0140 — 03B Continuity Testing | 21-Dec-27 → 23-Dec-27 | Not Started 0% | float 59.0d SC02AI0150 — 02A Function Testing | 21-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02AI0150 SC02DI0150 — 02D Function Testing | 21-Dec-27 → 04-Jan-28 | Not Started 0% | float 68.0d SC02DI0150 SC03AT0130 — 03A Commission | 21-Dec-27 → 27-Dec-27 | Not Started 0% | float -47.0d SC03AT0130 CO02NI0140 — 02N Continuity Testing | 22-Dec-27 → 22-Dec-27 | Not Started 0% | float 67.0d CO02KT0110 — 02K Mechanical Completion | 22-Dec-27 | Not Started CO02NT0110 — 02N Mechanical Completion | 22-Dec-27 | Not Started CO02PI0140 — 02P Continuity Testing | 23-Dec-27 → 23-Dec-27 | Not Started 0% | float 64.0d SC02KI0150 — 02K Function Testing | 23-Dec-27 → 16-Jan-28 | Not Started 0% | float 56.0d SC02KI0150 SC02NI0150 — 02N Function Testing | 23-Dec-27 → 25-Dec-27 | Not Started 0% | float 78.0d CO01CT0110 — 01C Mechanical Completion | 23-Dec-27 | Not Started CO02PT0110 — 02P Mechanical Completion | 23-Dec-27 | Not Started CO03BT0110 — 03B Mechanical Completion | 23-Dec-27 | Not Started CO02HV2120 — 02H Insulate - Piping | 24-Dec-27 → 16-Feb-28 | Not Started 0% | float 21.0d CO02HV2120 CO02NV2120 — 02N Insulate - Piping | 24-Dec-27 → 06-Jan-28 | Not Started 0% | float 56.0d CO02NV2120 CO02QI0140 — 02Q Continuity Testing | 24-Dec-27 → 24-Dec-27 | Not Started 0% | float 63.0d CO03CI0140 — 03C Continuity Testing | 24-Dec-27 → 27-Dec-27 | Not Started 0% | float -19.0d SC01CI0150 — 01C Function Testing | 24-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01CI0150 SC01YI0150 — 01Y Function Testing | 24-Dec-27 → 10-Jan-28 | Not Started 0% | float 62.0d SC01YI0150 SC02PI0150 — 02P Function Testing | 24-Dec-27 → 28-Dec-27 | Not Started 0% | float 75.0d SC02PI0150 SC03BI0150 — 03B Function Testing | 24-Dec-27 → 03-Jan-28 | Not Started 0% | float 69.0d SC03BI0150 CO02QT0110 — 02Q Mechanical Completion | 24-Dec-27 | Not Started SC03FT0120 — 03F RFSU | 24-Dec-27 | Not Started CO02LV1120 — 02L Paint Touch-up - Piping | 25-Dec-27 → 14-Feb-28 | Not Started 0% | float 23.0d CO02LV1120 SC02QI0150 — 02Q Function Testing | 25-Dec-27 → 29-Dec-27 | Not Started 0% | float 74.0d SC02QI0150 CO02MT0110 — 02M Mechanical Completion | 25-Dec-27 | Not Started SC02MI0150 — 02M Function Testing | 26-Dec-27 → 12-Jan-28 | Not Started 0% | float 60.0d SC02MI0150 CO02ET0110 — 02E Mechanical Completion | 27-Dec-27 | Not Started CO03CT0110 — 03C Mechanical Completion | 27-Dec-27 | Not Started CO01AI0140 — 01A Continuity Testing | 28-Dec-27 → 28-Dec-27 | Not Started 0% | float -12.0d CO02FI0140 — 02F Continuity Testing | 28-Dec-27 → 01-Jan-28 | Not Started 0% | float 44.0d CO02FI0140 CO03DI0140 — 03D Continuity Testing | 28-Dec-27 → 29-Dec-27 | Not Started 0% | float -17.0d SC01DT0130 — 01D Commission | 28-Dec-27 → 07-Feb-28 | Not Started 0% | float -47.0d SC01DT0130 SC02EI0150 — 02E Function Testing | 28-Dec-27 → 17-Jan-28 | Not Started 0% | float 55.0d SC02EI0150 SC03CI0150 — 03C Function Testing | 28-Dec-27 → 07-Jan-28 | Not Started 0% | float -23.0d SC03CI0150 CO01AT0110 — 01A Mechanical Completion | 28-Dec-27 | Not Started CO01BT0110 — 01B Mechanical Completion | 28-Dec-27 | Not Started CO02JT0110 — 02J Mechanical Completion | 28-Dec-27 | Not Started SC02PT0120 — 02P RFSU | 28-Dec-27 | Not Started SC01AI0150 — 01A Function Testing | 29-Dec-27 → 29-Dec-27 | Not Started 0% | float -14.0d SC01BI0150 — 01B Function Testing | 29-Dec-27 → 19-Jan-28 | Not Started 0% | float -35.0d SC01BI0150 SC02JI0150 — 02J Function Testing | 29-Dec-27 → 23-Jan-28 | Not Started 0% | float 49.0d SC02JI0150 CO02CT0110 — 02C Mechanical Completion | 29-Dec-27 | Not Started CO03DT0110 — 03D Mechanical Completion | 29-Dec-27 | Not Started SC01AT0120 — 01A RFSU | 29-Dec-27 | Not Started SC01CT0120 — 01C RFSU | 29-Dec-27 | Not Started SC01DT0120 — 01D RFSU | 29-Dec-27 | Not Started SC02QT0120 — 02Q RFSU | 29-Dec-27 | Not Started CO03EI0140 — 03E Continuity Testing | 30-Dec-27 → 04-Jan-28 | Not Started 0% | float -32.0d CO03EI0140 SC03DI0150 — 03D Function Testing | 30-Dec-27 → 04-Jan-28 | Not Started 0% | float -20.0d SC03DI0150 SC03YI0150 — 03Y Function Testing | 01-Jan-28 → 24-Jan-28 | Not Started 0% | float 48.0d SC03YI0150 CO02FT0110 — 02F Mechanical Completion | 01-Jan-28 | Not Started SC02FI0150 — 02F Function Testing | 02-Jan-28 → 20-Jan-28 | Not Started 0% | float 52.0d SC02FI0150 CO01YT0110 — 01Y Mechanical Completion | 03-Jan-28 | Not Started CO02YT0110 — 02Y Mechanical Completion | 03-Jan-28 | Not Started SC03BT0120 — 03B RFSU | 03-Jan-28 | Not Started CO03ET0110 — 03E Mechanical Completion | 04-Jan-28 | Not Started SC02DT0120 — 02D RFSU | 04-Jan-28 | Not Started SC03DT0120 — 03D RFSU | 04-Jan-28 | Not Started CO02LV2120 — 02L Insulate - Piping | 05-Jan-28 → 13-Mar-28 | Not Started 0% | float -1.0d CO02LV2120 SC03EI0150 — 03E Function Testing | 05-Jan-28 → 22-Jan-28 | Not Started 0% | float -38.0d SC03EI0150 SC02NT0120 — 02N RFSU | 06-Jan-28 | Not Started SC03CT0120 — 03C RFSU | 07-Jan-28 | Not Started CO05BP0150 — 05B Punchlist / Test Piping | 08-Jan-28 → 24-Jan-28 | Not Started 0% | float 63.0d CO05BP0150 CO05BV1130 — 05B Paint Touch-up - Equipment | 08-Jan-28 → 18-Jan-28 | Not Started 0% | float 62.0d CO05BV1130 SC02GT0120 — 02G RFSU | 09-Jan-28 | Not Started SC01YT0120 — 01Y RFSU | 10-Jan-28 | Not Started SC02YT0120 — 02Y RFSU | 10-Jan-28 | Not Started SC02AT0120 — 02A RFSU | 12-Jan-28 | Not Started SC02MT0120 — 02M RFSU | 12-Jan-28 | Not Started CO02HI0140 — 02H Continuity Testing | 14-Jan-28 → 26-Jan-28 | Not Started 0% | float 15.0d CO02HI0140 SC02KT0120 — 02K RFSU | 16-Jan-28 | Not Started CO03YT0110 — 03Y Mechanical Completion | 17-Jan-28 | Not Started SC02ET0120 — 02E RFSU | 17-Jan-28 | Not Started CO05AP0150 — 05A Punchlist / Test Piping | 19-Jan-28 → 14-Mar-28 | Not Started 0% | float -29.0d CO05AP0150 SC01BT0120 — 01B RFSU | 19-Jan-28 | Not Started CO02HI0130 — 02H Install In Line Instruments | 20-Jan-28 → 01-Feb-28 | Not Started 0% | float 10.0d CO02HI0130 SC02HI0150 — 02H Function Testing | 20-Jan-28 → 29-Feb-28 | Not Started 0% | float 12.0d SC02HI0150 SC02FT0120 — 02F RFSU | 20-Jan-28 | Not Started SC03ET0120 — 03E RFSU | 22-Jan-28 | Not Started SC02JT0120 — 02J RFSU | 23-Jan-28 | Not Started CO05BI0130 — 05B Install In Line Instruments | 24-Jan-28 → 25-Jan-28 | Not Started 0% | float 68.0d CO05BT0110 — 05B Mechanical Completion | 24-Jan-28 | Not Started CO05BV2120 — 05B Insulate - Piping | 24-Jan-28 → 14-Feb-28 | Not Started 0% | float 63.0d CO05BV2120 WO050V2100 — 050 Insulation | 24-Jan-28 → 10-May-28 | Not Started 0% | float -12.0d WO050V2100 SC02CT0120 — 02C RFSU | 24-Jan-28 | Not Started SC03YT0120 — 03Y RFSU | 24-Jan-28 | Not Started CO05BV2110 — 05B Insulate - Equipment | 25-Jan-28 → 15-Feb-28 | Not Started 0% | float 62.0d CO05BV2110 CO02HI0145 — 02H Contingency (101-B) | 27-Jan-28 → 23-Feb-28 | Not Started 0% | float 15.0d CO02HI0145 CO02LI0140 — 02L Continuity Testing | 05-Feb-28 → 21-Feb-28 | Not Started 0% | float -12.0d CO02LI0140 SC05BI0150 — 05B Function Testing | 05-Feb-28 → 08-Feb-28 | Not Started 0% | float 79.0d SC02LI0150 — 02L Function Testing | 08-Feb-28 → 29-Mar-28 | Not Started 0% | float -17.0d SC02LI0150 SC03FT0130 — 03F Commission | 08-Feb-28 → 28-Feb-28 | Not Started 0% | float -47.0d SC03FT0130 CO05AV1120 — 05A Paint Touch-up - Piping | 10-Feb-28 → 14-Mar-28 | Not Started 0% | float -2.0d CO05AV1120 CO02LI0130 — 02L Install In Line Instruments | 15-Feb-28 → 01-Mar-28 | Not Started 0% | float -15.0d CO02LI0130 SC05BT0120 — 05B RFSU | 15-Feb-28 | Not Started CO02LT0110 — 02L Mechanical Completion | 21-Feb-28 | Not Started CO02HT0110 — 02H Mechanical Completion | 23-Feb-28 | Not Started CO05AK0120 — 05A Construct Dike (Retaining Wall) | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0120 CO05AK0130 — 05A Guard Posts, Fence, Gravel... | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0130 WO050K0100 — 050 Site Prep | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d WO050K0100 CO05AV2120 — 05A Insulate - Piping | 28-Feb-28 → 11-Apr-28 | Not Started 0% | float -26.0d CO05AV2120 CO06AV2120 — 05A Insulate - Piping | 28-Feb-28 → 11-Apr-28 | Not Started 0% | float -26.0d CO06AV2120 SC000T0100 — 020 Commission ISBL | 29-Feb-28 → 28-Apr-28 | Not Started 0% | float -47.0d SC000T0100 SC02HT0120 — 02H RFSU | 29-Feb-28 | Not Started CO05AE0110 — 05A Lighting JB's, Stands, Tray & Cable | 03-Mar-28 → 30-Mar-28 | Not Started 0% | float -22.0d CO05AE0110 CO05AI0140 — 05A Continuity Testing | 10-Mar-28 → 21-Mar-28 | Not Started 0% | float -25.0d CO05AI0140 CO05AV1130 — 05A Paint Touch-up - Equipment | 10-Mar-28 → 12-Apr-28 | Not Started 0% | float -51.0d CO05AV1130 CO05AI0130 — 05A Install In Line Instruments | 15-Mar-28 → 25-Mar-28 | Not Started 0% | float -29.0d CO05AI0130 SC05AI0150 — 05A Function Testing | 15-Mar-28 → 15-Apr-28 | Not Started 0% | float -34.0d SC05AI0150 CO05AE0120 — 05A Lighting Fixture Installation/Termination | 24-Mar-28 → 06-Apr-28 | Not Started 0% | float -22.0d CO05AE0120 CO05AV2110 — 05A Insulate - Equipment | 28-Mar-28 → 10-May-28 | Not Started 0% | float -51.0d CO05AV2110 CO06AV2110 — 05A Insulate - Equipment | 28-Mar-28 → 10-May-28 | Not Started 0% | float -51.0d CO06AV2110 SC02LT0120 — 02L RFSU | 29-Mar-28 | Not Started CO05AT0110 — 05A Mechanical Completion | 05-May-28 | Not Started SC05AT0120 — 05A RFSU | 10-May-28 | Not Started SC000T0105 — 020 Startup ISBL | 11-May-28 → 24-Jun-28 | Not Started 0% | float -59.0d SC000T0105 SC000T0110 — Performance Test Period | 25-Jun-28 → 22-Sep-28 | Not Started 0% | float -59.0d SC000T0110 SC000YA100 — Construction Bonus Period | 23-Sep-28 → 15-Mar-29 | Not Started 0% | float -59.0d SC000YA100