EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 18 activities in I0 Instrumentation × clear
Code
Activity
Start
Finish
Flt
%
CO01YI0120
01Y Instrument JB's, Field Instr, Tray, Cable
19-Jun-27
30-Jul-27
39.0d
0%
WO010I0100
010 Install Instruments & Test
19-Jun-27
03-Jan-28
53.0d
0%
CO01CI0120
01C Instrument JB's, Field Instr, Tray, Cable
21-Jun-27
12-Jul-27
100.0d
0%
CO01GI0150
01G Install DCS
25-Jun-27
25-Aug-27
-14.0d
0%
CO01BI0120
01B Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
05-Oct-27
32.0d
0%
CO01DI0120
01D Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
10-Sep-27
39.0d
0%
CO01CI0130
01C Install In Line Instruments
12-Jul-27
15-Jul-27
96.0d
0%
CO01YI0130
01Y Install In Line Instruments
31-Jul-27
27-Aug-27
139.0d
0%
CO01DI0130
01D Install In Line Instruments
20-Sep-27
24-Sep-27
41.0d
0%
CO01AI0120
01A Instrument JB's, Field Instr, Tray, Cable
29-Sep-27
05-Oct-27
54.0d
0%
CO01AI0130
01A Install In Line Instruments
02-Oct-27
02-Oct-27
57.0d
0%
CO01BI0130
01B Install In Line Instruments
06-Oct-27
13-Oct-27
37.0d
0%
CO01GI0120
01G DCS Cable Terminations
06-Oct-27
06-Dec-27
-35.0d
0%
CO01DI0140
01D Continuity Testing
07-Dec-27
11-Dec-27
-22.0d
0%
CO01YI0140
01Y Continuity Testing
14-Dec-27
03-Jan-28
53.0d
0%
CO01BI0140
01B Continuity Testing
21-Dec-27
28-Dec-27
-29.0d
0%
CO01CI0140
01C Continuity Testing
21-Dec-27
23-Dec-27
-12.0d
0%
CO01AI0140
01A Continuity Testing
28-Dec-27
28-Dec-27
-12.0d
0%
31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CO01YI0120 — 01Y Instrument JB's, Field Instr, Tray, Cable | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 39.0d CO01YI0120 WO010I0100 — 010 Install Instruments & Test | 19-Jun-27 → 03-Jan-28 | Not Started 0% | float 53.0d WO010I0100 CO01CI0120 — 01C Instrument JB's, Field Instr, Tray, Cable | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO01CI0120 CO01GI0150 — 01G Install DCS | 25-Jun-27 → 25-Aug-27 | Not Started 0% | float -14.0d CO01GI0150 CO01BI0120 — 01B Instrument JB's, Field Instr, Tray, Cable | 26-Jun-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BI0120 CO01DI0120 — 01D Instrument JB's, Field Instr, Tray, Cable | 26-Jun-27 → 10-Sep-27 | Not Started 0% | float 39.0d CO01DI0120 CO01CI0130 — 01C Install In Line Instruments | 12-Jul-27 → 15-Jul-27 | Not Started 0% | float 96.0d CO01CI0130 CO01YI0130 — 01Y Install In Line Instruments | 31-Jul-27 → 27-Aug-27 | Not Started 0% | float 139.0d CO01YI0130 CO01DI0130 — 01D Install In Line Instruments | 20-Sep-27 → 24-Sep-27 | Not Started 0% | float 41.0d CO01DI0130 CO01AI0120 — 01A Instrument JB's, Field Instr, Tray, Cable | 29-Sep-27 → 05-Oct-27 | Not Started 0% | float 54.0d CO01AI0120 CO01AI0130 — 01A Install In Line Instruments | 02-Oct-27 → 02-Oct-27 | Not Started 0% | float 57.0d CO01BI0130 — 01B Install In Line Instruments | 06-Oct-27 → 13-Oct-27 | Not Started 0% | float 37.0d CO01BI0130 CO01GI0120 — 01G DCS Cable Terminations | 06-Oct-27 → 06-Dec-27 | Not Started 0% | float -35.0d CO01GI0120 CO01DI0140 — 01D Continuity Testing | 07-Dec-27 → 11-Dec-27 | Not Started 0% | float -22.0d CO01DI0140 CO01YI0140 — 01Y Continuity Testing | 14-Dec-27 → 03-Jan-28 | Not Started 0% | float 53.0d CO01YI0140 CO01BI0140 — 01B Continuity Testing | 21-Dec-27 → 28-Dec-27 | Not Started 0% | float -29.0d CO01BI0140 CO01CI0140 — 01C Continuity Testing | 21-Dec-27 → 23-Dec-27 | Not Started 0% | float -12.0d CO01CI0140 CO01AI0140 — 01A Continuity Testing | 28-Dec-27 → 28-Dec-27 | Not Started 0% | float -12.0d