Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 28 activities in E0 A/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO01BE0110
01B Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO01EE0110
01E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
180.0d
0%
CO01FE0110
01F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
152.0d
0%
CO01GE0130
01G Power Tray, Cable, Terminations
17-May-27
12-Jun-27
92.0d
0%
WO010E0100
010 Above Ground Electrical
17-May-27
05-Oct-27
131.0d
0%
CO01YE0110
01Y Lighting JB's, Stands, Tray & Cable
22-May-27
02-Jul-27
175.0d
0%
CO01CE0110
01C Lighting JB's, Stands, Tray & Cable
29-May-27
18-Jun-27
124.0d
0%
CO01DE0110
01D Lighting JB's, Stands, Tray & Cable
02-Jun-27
13-Jul-27
66.0d
0%
CO01HE0110
01H Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
69.0d
0%
CO01CE0120
01C Lighting Fixture Installation/Termination
19-Jun-27
25-Jun-27
124.0d
0%
CO01HE0140
01H Set Transformers TR-100/ 103/ 104/ 105
19-Jun-27
02-Jul-27
33.0d
0%
CO01YE0130
01Y Power/Control JB's, Tray, Cable, Termination
19-Jun-27
30-Jul-27
39.0d
0%
CO01CE0130
01C Power/Control JB's, Tray, Cable, Termination
21-Jun-27
12-Jul-27
100.0d
0%
CO01GE0110
01G Lighting JB's, Stands, Tray & Cable
25-Jun-27
05-Aug-27
28.0d
0%
CO01GE0140
01G Install UPS in Control Building
25-Jun-27
15-Jul-27
-8.0d
0%
CO01BE0130
01B Power/Control JB's, Tray, Cable, Termination
26-Jun-27
05-Oct-27
32.0d
0%
CO01DE0130
01D Power/Control JB's, Tray, Cable, Termination
26-Jun-27
10-Sep-27
39.0d
0%
CO01BE0120
01B Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO01EE0120
01E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
180.0d
0%
CO01FE0120
01F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
152.0d
0%
CO01HE0120
01H Lighting Fixture Installation/Termination
03-Jul-27
16-Jul-27
69.0d
0%
CO01HE0130
01H Power/Control JB's, Tray, Cable, Termination
03-Jul-27
10-Sep-27
33.0d
0%
CO01YE0120
01Y Lighting Fixture Installation/Termination
03-Jul-27
23-Jul-27
175.0d
0%
CO01AE0110
01A Lighting JB's, Stands, Tray & Cable
13-Jul-27
26-Jul-27
91.0d
0%
CO01DE0120
01D Lighting Fixture Installation/Termination
14-Jul-27
03-Aug-27
66.0d
0%
CO01AE0120
01A Lighting Fixture Installation/Termination
27-Jul-27
02-Aug-27
91.0d
0%
CO01GE0120
01G Lighting Fixture Installation/Termination
06-Aug-27
08-Sep-27
28.0d
0%
CO01AE0130
01A Power/Control JB's, Tray, Cable, Termination
03-Sep-27
21-Sep-27
66.0d
0%
26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Data Date
CO01BE0110 — 01B Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO01BE0110 CO01EE0110 — 01E Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 180.0d CO01EE0110 CO01FE0110 — 01F Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 152.0d CO01FE0110 CO01GE0130 — 01G Power Tray, Cable, Terminations | 17-May-27 → 12-Jun-27 | Not Started 0% | float 92.0d CO01GE0130 WO010E0100 — 010 Above Ground Electrical | 17-May-27 → 05-Oct-27 | Not Started 0% | float 131.0d WO010E0100 CO01YE0110 — 01Y Lighting JB's, Stands, Tray & Cable | 22-May-27 → 02-Jul-27 | Not Started 0% | float 175.0d CO01YE0110 CO01CE0110 — 01C Lighting JB's, Stands, Tray & Cable | 29-May-27 → 18-Jun-27 | Not Started 0% | float 124.0d CO01CE0110 CO01DE0110 — 01D Lighting JB's, Stands, Tray & Cable | 02-Jun-27 → 13-Jul-27 | Not Started 0% | float 66.0d CO01DE0110 CO01HE0110 — 01H Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 69.0d CO01HE0110 CO01CE0120 — 01C Lighting Fixture Installation/Termination | 19-Jun-27 → 25-Jun-27 | Not Started 0% | float 124.0d CO01CE0120 CO01HE0140 — 01H Set Transformers TR-100/ 103/ 104/ 105 | 19-Jun-27 → 02-Jul-27 | Not Started 0% | float 33.0d CO01HE0140 CO01YE0130 — 01Y Power/Control JB's, Tray, Cable, Termination | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 39.0d CO01YE0130 CO01CE0130 — 01C Power/Control JB's, Tray, Cable, Termination | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO01CE0130 CO01GE0110 — 01G Lighting JB's, Stands, Tray & Cable | 25-Jun-27 → 05-Aug-27 | Not Started 0% | float 28.0d CO01GE0110 CO01GE0140 — 01G Install UPS in Control Building | 25-Jun-27 → 15-Jul-27 | Not Started 0% | float -8.0d CO01GE0140 CO01BE0130 — 01B Power/Control JB's, Tray, Cable, Termination | 26-Jun-27 → 05-Oct-27 | Not Started 0% | float 32.0d CO01BE0130 CO01DE0130 — 01D Power/Control JB's, Tray, Cable, Termination | 26-Jun-27 → 10-Sep-27 | Not Started 0% | float 39.0d CO01DE0130 CO01BE0120 — 01B Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO01BE0120 CO01EE0120 — 01E Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 180.0d CO01EE0120 CO01FE0120 — 01F Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 152.0d CO01FE0120 CO01HE0120 — 01H Lighting Fixture Installation/Termination | 03-Jul-27 → 16-Jul-27 | Not Started 0% | float 69.0d CO01HE0120 CO01HE0130 — 01H Power/Control JB's, Tray, Cable, Termination | 03-Jul-27 → 10-Sep-27 | Not Started 0% | float 33.0d CO01HE0130 CO01YE0120 — 01Y Lighting Fixture Installation/Termination | 03-Jul-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO01YE0120 CO01AE0110 — 01A Lighting JB's, Stands, Tray & Cable | 13-Jul-27 → 26-Jul-27 | Not Started 0% | float 91.0d CO01AE0110 CO01DE0120 — 01D Lighting Fixture Installation/Termination | 14-Jul-27 → 03-Aug-27 | Not Started 0% | float 66.0d CO01DE0120 CO01AE0120 — 01A Lighting Fixture Installation/Termination | 27-Jul-27 → 02-Aug-27 | Not Started 0% | float 91.0d CO01AE0120 CO01GE0120 — 01G Lighting Fixture Installation/Termination | 06-Aug-27 → 08-Sep-27 | Not Started 0% | float 28.0d CO01GE0120 CO01AE0130 — 01A Power/Control JB's, Tray, Cable, Termination | 03-Sep-27 → 21-Sep-27 | Not Started 0% | float 66.0d CO01AE0130