Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in V2 Insulation × clear
Code
Activity
Start
Finish
Flt
%
CO04AV2110
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
WO04AV2100
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Data Date
CO04AV2110 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d CO04AV2110 WO04AV2100 — 04A Insulation | 12-May-27 → 28-Sep-27 | Not Started 0% | float 108.0d WO04AV2100