Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U4 U/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%
Q1 2027 Q2 2027 Q3 2027 Data Date
CO04AU4120 — 04A U/G Piping Installation | 29-Jan-27 → 09-Aug-27 | Not Started 0% | float 108.0d CO04AU4120 WO04AE0100 — 04A Above Ground Electrical | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AE0100 WO04AI0100 — 04A Install Instruments & Test | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AI0100 WO04AM0100 — 04A Major Equipment | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AM0100 WO04AS0100 — 04A Erect Steel | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AS0100 WO04AU4100 — 04A U/G Piping Installation | 29-Jan-27 → 01-Sep-27 | Not Started 0% | float 108.0d WO04AU4100 CO04AU4130 — 04A Punchlist / Test U/G Piping | 28-Apr-27 → 01-Sep-27 | Not Started 0% | float 108.0d CO04AU4130