EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in U4 U/G Piping
× clear
Code
Activity
Start
Finish
Flt
%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%