EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in T0 Mechanical Completion × clear
Code
Activity
Start
Finish
Flt
%
CO04AT0110
04A Mechanical Completion
05-Oct-27
05-Oct-27
108.0d
0%
SC04AT0120
04A RFSU
02-Nov-27
02-Nov-27
132.0d
0%
Q4 2027 Data Date
CO04AT0110 — 04A Mechanical Completion | 05-Oct-27 | Not Started SC04AT0120 — 04A RFSU | 02-Nov-27 | Not Started