EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in C1 Concrete Paving
× clear
Code
Activity
Start
Finish
Flt
%
CO03DC0130
03D Install Paving
01-Feb-27
06-Feb-27
189.0d
0%
WO030C0110
030 Concrete Paving
01-Feb-27
17-Apr-27
210.0d
0%
CO03BC0130
03B Install Paving
04-Mar-27
17-Mar-27
237.0d
0%
CO03AC0130
03A Install Paving
08-Mar-27
13-Mar-27
133.0d
0%
CO03CC0130
03C Install Paving
15-Mar-27
20-Mar-27
158.0d
0%
CO03FC0130
03F Install Paving
22-Mar-27
03-Apr-27
147.0d
0%
CO03EC0130
03E Install Paving
05-Apr-27
17-Apr-27
108.0d
0%