EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in C1 Concrete Paving × clear
Code
Activity
Start
Finish
Flt
%
CO03DC0130
03D Install Paving
01-Feb-27
06-Feb-27
189.0d
0%
WO030C0110
030 Concrete Paving
01-Feb-27
17-Apr-27
210.0d
0%
CO03BC0130
03B Install Paving
04-Mar-27
17-Mar-27
237.0d
0%
CO03AC0130
03A Install Paving
08-Mar-27
13-Mar-27
133.0d
0%
CO03CC0130
03C Install Paving
15-Mar-27
20-Mar-27
158.0d
0%
CO03FC0130
03F Install Paving
22-Mar-27
03-Apr-27
147.0d
0%
CO03EC0130
03E Install Paving
05-Apr-27
17-Apr-27
108.0d
0%
01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr Data Date
CO03DC0130 — 03D Install Paving | 01-Feb-27 → 06-Feb-27 | Not Started 0% | float 189.0d CO03DC0130 WO030C0110 — 030 Concrete Paving | 01-Feb-27 → 17-Apr-27 | Not Started 0% | float 210.0d WO030C0110 CO03BC0130 — 03B Install Paving | 04-Mar-27 → 17-Mar-27 | Not Started 0% | float 237.0d CO03BC0130 CO03AC0130 — 03A Install Paving | 08-Mar-27 → 13-Mar-27 | Not Started 0% | float 133.0d CO03AC0130 CO03CC0130 — 03C Install Paving | 15-Mar-27 → 20-Mar-27 | Not Started 0% | float 158.0d CO03CC0130 CO03FC0130 — 03F Install Paving | 22-Mar-27 → 03-Apr-27 | Not Started 0% | float 147.0d CO03FC0130 CO03EC0130 — 03E Install Paving | 05-Apr-27 → 17-Apr-27 | Not Started 0% | float 108.0d CO03EC0130