EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 22
activities
in I0 Instrumentation
× clear
Code
Activity
Start
Finish
Flt
%
CO03YI0120
03Y Instrument JB's, Field Instr, Tray, Cable
17-May-27
07-Aug-27
32.0d
0%
WO030I0100
030 Install Instruments & Test
17-May-27
17-Jan-28
41.0d
0%
CO03FI0120
03F Instrument JB's, Field Instr, Tray, Cable
08-Jun-27
16-Jul-27
97.0d
0%
CO03AI0120
03A Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
56.0d
0%
CO03CI0120
03C Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
87.0d
0%
CO03EI0120
03E Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
13-Aug-27
61.0d
0%
CO03DI0120
03D Instrument JB's, Field Instr, Tray, Cable
22-Jun-27
12-Jul-27
100.0d
0%
CO03BI0120
03B Instrument JB's, Field Instr, Tray, Cable
12-Jul-27
23-Aug-27
138.0d
0%
CO03DI0130
03D Install In Line Instruments
12-Jul-27
14-Jul-27
97.0d
0%
CO03FI0130
03F Install In Line Instruments
17-Jul-27
20-Jul-27
97.0d
0%
CO03AI0130
03A Install In Line Instruments
22-Jul-27
24-Jul-27
62.0d
0%
CO03CI0130
03C Install In Line Instruments
22-Jul-27
24-Jul-27
87.0d
0%
CO03YI0130
03Y Install In Line Instruments
24-Jul-27
27-Aug-27
139.0d
0%
CO03EI0130
03E Install In Line Instruments
16-Aug-27
25-Aug-27
65.0d
0%
CO03BI0130
03B Install In Line Instruments
25-Aug-27
30-Aug-27
138.0d
0%
CO03AI0140
03A Continuity Testing
07-Dec-27
09-Dec-27
-35.0d
0%
CO03YI0140
03Y Continuity Testing
07-Dec-27
17-Jan-28
41.0d
0%
CO03FI0140
03F Continuity Testing
10-Dec-27
13-Dec-27
-1.0d
0%
CO03BI0140
03B Continuity Testing
21-Dec-27
23-Dec-27
59.0d
0%
CO03CI0140
03C Continuity Testing
24-Dec-27
27-Dec-27
-19.0d
0%
CO03DI0140
03D Continuity Testing
28-Dec-27
29-Dec-27
-17.0d
0%
CO03EI0140
03E Continuity Testing
30-Dec-27
04-Jan-28
-32.0d
0%