Code
Activity
Start
Finish
Flt
%
CO03YI0120
03Y Instrument JB's, Field Instr, Tray, Cable
17-May-27
07-Aug-27
32.0d
0%
WO030I0100
030 Install Instruments & Test
17-May-27
17-Jan-28
41.0d
0%
CO03FI0120
03F Instrument JB's, Field Instr, Tray, Cable
08-Jun-27
16-Jul-27
97.0d
0%
CO03AI0120
03A Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
56.0d
0%
CO03CI0120
03C Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
87.0d
0%
CO03EI0120
03E Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
13-Aug-27
61.0d
0%
CO03DI0120
03D Instrument JB's, Field Instr, Tray, Cable
22-Jun-27
12-Jul-27
100.0d
0%
CO03BI0120
03B Instrument JB's, Field Instr, Tray, Cable
12-Jul-27
23-Aug-27
138.0d
0%
CO03DI0130
03D Install In Line Instruments
12-Jul-27
14-Jul-27
97.0d
0%
CO03FI0130
03F Install In Line Instruments
17-Jul-27
20-Jul-27
97.0d
0%
CO03AI0130
03A Install In Line Instruments
22-Jul-27
24-Jul-27
62.0d
0%
CO03CI0130
03C Install In Line Instruments
22-Jul-27
24-Jul-27
87.0d
0%
CO03YI0130
03Y Install In Line Instruments
24-Jul-27
27-Aug-27
139.0d
0%
CO03EI0130
03E Install In Line Instruments
16-Aug-27
25-Aug-27
65.0d
0%
CO03BI0130
03B Install In Line Instruments
25-Aug-27
30-Aug-27
138.0d
0%
CO03AI0140
03A Continuity Testing
07-Dec-27
09-Dec-27
-35.0d
0%
CO03YI0140
03Y Continuity Testing
07-Dec-27
17-Jan-28
41.0d
0%
CO03FI0140
03F Continuity Testing
10-Dec-27
13-Dec-27
-1.0d
0%
CO03BI0140
03B Continuity Testing
21-Dec-27
23-Dec-27
59.0d
0%
CO03CI0140
03C Continuity Testing
24-Dec-27
27-Dec-27
-19.0d
0%
CO03DI0140
03D Continuity Testing
28-Dec-27
29-Dec-27
-17.0d
0%
CO03EI0140
03E Continuity Testing
30-Dec-27
04-Jan-28
-32.0d
0%
26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan Data Date
CO03YI0120 — 03Y Instrument JB's, Field Instr, Tray, Cable | 17-May-27 → 07-Aug-27 | Not Started 0% | float 32.0d CO03YI0120 WO030I0100 — 030 Install Instruments & Test | 17-May-27 → 17-Jan-28 | Not Started 0% | float 41.0d WO030I0100 CO03FI0120 — 03F Instrument JB's, Field Instr, Tray, Cable | 08-Jun-27 → 16-Jul-27 | Not Started 0% | float 97.0d CO03FI0120 CO03AI0120 — 03A Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 56.0d CO03AI0120 CO03CI0120 — 03C Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CI0120 CO03EI0120 — 03E Instrument JB's, Field Instr, Tray, Cable | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 61.0d CO03EI0120 CO03DI0120 — 03D Instrument JB's, Field Instr, Tray, Cable | 22-Jun-27 → 12-Jul-27 | Not Started 0% | float 100.0d CO03DI0120 CO03BI0120 — 03B Instrument JB's, Field Instr, Tray, Cable | 12-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BI0120 CO03DI0130 — 03D Install In Line Instruments | 12-Jul-27 → 14-Jul-27 | Not Started 0% | float 97.0d CO03DI0130 CO03FI0130 — 03F Install In Line Instruments | 17-Jul-27 → 20-Jul-27 | Not Started 0% | float 97.0d CO03FI0130 CO03AI0130 — 03A Install In Line Instruments | 22-Jul-27 → 24-Jul-27 | Not Started 0% | float 62.0d CO03AI0130 CO03CI0130 — 03C Install In Line Instruments | 22-Jul-27 → 24-Jul-27 | Not Started 0% | float 87.0d CO03CI0130 CO03YI0130 — 03Y Install In Line Instruments | 24-Jul-27 → 27-Aug-27 | Not Started 0% | float 139.0d CO03YI0130 CO03EI0130 — 03E Install In Line Instruments | 16-Aug-27 → 25-Aug-27 | Not Started 0% | float 65.0d CO03EI0130 CO03BI0130 — 03B Install In Line Instruments | 25-Aug-27 → 30-Aug-27 | Not Started 0% | float 138.0d CO03BI0130 CO03AI0140 — 03A Continuity Testing | 07-Dec-27 → 09-Dec-27 | Not Started 0% | float -35.0d CO03AI0140 CO03YI0140 — 03Y Continuity Testing | 07-Dec-27 → 17-Jan-28 | Not Started 0% | float 41.0d CO03YI0140 CO03FI0140 — 03F Continuity Testing | 10-Dec-27 → 13-Dec-27 | Not Started 0% | float -1.0d CO03FI0140 CO03BI0140 — 03B Continuity Testing | 21-Dec-27 → 23-Dec-27 | Not Started 0% | float 59.0d CO03BI0140 CO03CI0140 — 03C Continuity Testing | 24-Dec-27 → 27-Dec-27 | Not Started 0% | float -19.0d CO03CI0140 CO03DI0140 — 03D Continuity Testing | 28-Dec-27 → 29-Dec-27 | Not Started 0% | float -17.0d CO03DI0140 CO03EI0140 — 03E Continuity Testing | 30-Dec-27 → 04-Jan-28 | Not Started 0% | float -32.0d CO03EI0140