EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 21 activities in E0 A/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO03CE0110
03C Lighting JB's, Stands, Tray & Cable
17-May-27
12-Jun-27
123.0d
0%
CO03DE0110
03D Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03DE0130
03D Power/Control JB's, Tray, Cable, Termination
17-May-27
04-Jun-27
131.0d
0%
CO03EE0110
03E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03FE0110
03F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
111.0d
0%
CO03YE0110
03Y Lighting JB's, Stands, Tray & Cable
17-May-27
07-Aug-27
162.0d
0%
CO03YE0130
03Y Power/Control JB's, Tray, Cable, Termination
17-May-27
07-Aug-27
32.0d
0%
WO030E0100
030 Above Ground Electrical
17-May-27
23-Aug-27
153.0d
0%
CO03FE0130
03F Power/Control JB's, Tray, Cable, Termination
08-Jun-27
16-Jul-27
97.0d
0%
CO03AE0130
03A Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
56.0d
0%
CO03BE0110
03B Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
187.0d
0%
CO03CE0130
03C Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
87.0d
0%
CO03EE0130
03E Power/Control JB's, Tray, Cable, Termination
12-Jun-27
13-Aug-27
61.0d
0%
CO03CE0120
03C Lighting Fixture Installation/Termination
14-Jun-27
26-Jun-27
123.0d
0%
CO03AE0110
03A Lighting JB's, Stands, Tray & Cable
19-Jun-27
09-Jul-27
75.0d
0%
CO03DE0120
03D Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03EE0120
03E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03FE0120
03F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
111.0d
0%
CO03BE0120
03B Lighting Fixture Installation/Termination
03-Jul-27
09-Jul-27
187.0d
0%
CO03AE0120
03A Lighting Fixture Installation/Termination
10-Jul-27
16-Jul-27
75.0d
0%
CO03BE0130
03B Power/Control JB's, Tray, Cable, Termination
12-Jul-27
23-Aug-27
138.0d
0%
26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug Data Date
CO03CE0110 — 03C Lighting JB's, Stands, Tray & Cable | 17-May-27 → 12-Jun-27 | Not Started 0% | float 123.0d CO03CE0110 CO03DE0110 — 03D Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO03DE0110 CO03DE0130 — 03D Power/Control JB's, Tray, Cable, Termination | 17-May-27 → 04-Jun-27 | Not Started 0% | float 131.0d CO03DE0130 CO03EE0110 — 03E Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 105.0d CO03EE0110 CO03FE0110 — 03F Lighting JB's, Stands, Tray & Cable | 17-May-27 → 26-Jun-27 | Not Started 0% | float 111.0d CO03FE0110 CO03YE0110 — 03Y Lighting JB's, Stands, Tray & Cable | 17-May-27 → 07-Aug-27 | Not Started 0% | float 162.0d CO03YE0110 CO03YE0130 — 03Y Power/Control JB's, Tray, Cable, Termination | 17-May-27 → 07-Aug-27 | Not Started 0% | float 32.0d CO03YE0130 WO030E0100 — 030 Above Ground Electrical | 17-May-27 → 23-Aug-27 | Not Started 0% | float 153.0d WO030E0100 CO03FE0130 — 03F Power/Control JB's, Tray, Cable, Termination | 08-Jun-27 → 16-Jul-27 | Not Started 0% | float 97.0d CO03FE0130 CO03AE0130 — 03A Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 56.0d CO03AE0130 CO03BE0110 — 03B Lighting JB's, Stands, Tray & Cable | 12-Jun-27 → 02-Jul-27 | Not Started 0% | float 187.0d CO03BE0110 CO03CE0130 — 03C Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CE0130 CO03EE0130 — 03E Power/Control JB's, Tray, Cable, Termination | 12-Jun-27 → 13-Aug-27 | Not Started 0% | float 61.0d CO03EE0130 CO03CE0120 — 03C Lighting Fixture Installation/Termination | 14-Jun-27 → 26-Jun-27 | Not Started 0% | float 123.0d CO03CE0120 CO03AE0110 — 03A Lighting JB's, Stands, Tray & Cable | 19-Jun-27 → 09-Jul-27 | Not Started 0% | float 75.0d CO03AE0110 CO03DE0120 — 03D Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO03DE0120 CO03EE0120 — 03E Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 105.0d CO03EE0120 CO03FE0120 — 03F Lighting Fixture Installation/Termination | 28-Jun-27 → 17-Jul-27 | Not Started 0% | float 111.0d CO03FE0120 CO03BE0120 — 03B Lighting Fixture Installation/Termination | 03-Jul-27 → 09-Jul-27 | Not Started 0% | float 187.0d CO03BE0120 CO03AE0120 — 03A Lighting Fixture Installation/Termination | 10-Jul-27 → 16-Jul-27 | Not Started 0% | float 75.0d CO03AE0120 CO03BE0130 — 03B Power/Control JB's, Tray, Cable, Termination | 12-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BE0130