EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 21
activities
in E0 A/G Electrical
× clear
Code
Activity
Start
Finish
Flt
%
CO03CE0110
03C Lighting JB's, Stands, Tray & Cable
17-May-27
12-Jun-27
123.0d
0%
CO03DE0110
03D Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03DE0130
03D Power/Control JB's, Tray, Cable, Termination
17-May-27
04-Jun-27
131.0d
0%
CO03EE0110
03E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03FE0110
03F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
111.0d
0%
CO03YE0110
03Y Lighting JB's, Stands, Tray & Cable
17-May-27
07-Aug-27
162.0d
0%
CO03YE0130
03Y Power/Control JB's, Tray, Cable, Termination
17-May-27
07-Aug-27
32.0d
0%
WO030E0100
030 Above Ground Electrical
17-May-27
23-Aug-27
153.0d
0%
CO03FE0130
03F Power/Control JB's, Tray, Cable, Termination
08-Jun-27
16-Jul-27
97.0d
0%
CO03AE0130
03A Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
56.0d
0%
CO03BE0110
03B Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
187.0d
0%
CO03CE0130
03C Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
87.0d
0%
CO03EE0130
03E Power/Control JB's, Tray, Cable, Termination
12-Jun-27
13-Aug-27
61.0d
0%
CO03CE0120
03C Lighting Fixture Installation/Termination
14-Jun-27
26-Jun-27
123.0d
0%
CO03AE0110
03A Lighting JB's, Stands, Tray & Cable
19-Jun-27
09-Jul-27
75.0d
0%
CO03DE0120
03D Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03EE0120
03E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03FE0120
03F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
111.0d
0%
CO03BE0120
03B Lighting Fixture Installation/Termination
03-Jul-27
09-Jul-27
187.0d
0%
CO03AE0120
03A Lighting Fixture Installation/Termination
10-Jul-27
16-Jul-27
75.0d
0%
CO03BE0130
03B Power/Control JB's, Tray, Cable, Termination
12-Jul-27
23-Aug-27
138.0d
0%