EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 8
activities
in V2 Insulation
× clear
Code
Activity
Start
Finish
Flt
%
CO03FV2110
03F Insulate - Equipment
05-Jun-27
19-Jun-27
135.0d
0%
WO030V2100
030 Insulation
05-Jun-27
02-Oct-27
133.0d
0%
CO03YV2120
03Y Insulate - Piping
30-Jun-27
03-Sep-27
148.0d
0%
CO03AV2120
03A Insulate - Piping
16-Jul-27
30-Jul-27
63.0d
0%
CO03AV2110
03A Insulate - Equipment
22-Jul-27
05-Aug-27
58.0d
0%
CO03FV2120
03F Insulate - Piping
30-Jul-27
13-Aug-27
88.0d
0%
CO03EV2110
03E Insulate - Equipment
20-Aug-27
02-Oct-27
58.0d
0%
CO03EV2120
03E Insulate - Piping
20-Aug-27
02-Oct-27
58.0d
0%