Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 21 activities in V1 Painting × clear
Code
Activity
Start
Finish
Flt
%
CO03YV1110
03Y Paint Fabricated Pipe Spools
13-Jan-27
13-Feb-27
154.0d
0%
WO030V1100
030 Paint
13-Jan-27
23-Aug-27
153.0d
0%
CO03CV1110
03C Paint Fabricated Pipe Spools
13-Feb-27
24-Feb-27
191.0d
0%
CO03EV1110
03E Paint Fabricated Pipe Spools
19-Feb-27
09-Mar-27
171.0d
0%
CO03FV1110
03F Paint Fabricated Pipe Spools
19-Feb-27
02-Mar-27
183.0d
0%
CO03AV1110
03A Paint Fabricated Pipe Spools
27-Feb-27
10-Mar-27
148.0d
0%
CO03DV1110
03D Paint Fabricated Pipe Spools
06-Mar-27
11-Mar-27
172.0d
0%
CO03FV1130
03F Paint Touch-up - Equipment
17-Mar-27
27-Mar-27
183.0d
0%
CO03CV1130
03C Paint Touch-up - Equipment
24-Mar-27
05-Apr-27
195.0d
0%
CO03BV1110
03B Paint Fabricated Pipe Spools
05-Apr-27
15-Apr-27
223.0d
0%
CO03DV1130
03D Paint Touch-up - Equipment (& 2002-F Tank)
06-Apr-27
12-Apr-27
189.0d
0%
CO03BV1130
03B Paint Touch-up - Equipment
19-Apr-27
29-Apr-27
248.0d
0%
CO03YV1120
03Y Paint Touch-up - Piping
29-May-27
23-Jul-27
175.0d
0%
CO03FV1120
03F Paint Touch-up - Piping
06-Jul-27
16-Jul-27
112.0d
0%
CO03DV1120
03D Paint Touch-up - Piping
06-Jul-27
12-Jul-27
111.0d
0%
CO03AV1120
03A Paint Touch-up - Piping
10-Jul-27
21-Jul-27
58.0d
0%
CO03AV1130
03A Paint Touch-up - Equipment
10-Jul-27
21-Jul-27
58.0d
0%
CO03CV1120
03C Paint Touch-up - Piping
10-Jul-27
21-Jul-27
102.0d
0%
CO03EV1120
03E Paint Touch-up - Piping
27-Jul-27
13-Aug-27
58.0d
0%
CO03EV1130
03E Paint Touch-up - Equipment
27-Jul-27
13-Aug-27
58.0d
0%
CO03BV1120
03B Paint Touch-up - Piping
07-Aug-27
23-Aug-27
153.0d
0%
Q1 2027 Q2 2027 Q3 2027 Data Date
CO03YV1110 — 03Y Paint Fabricated Pipe Spools | 13-Jan-27 → 13-Feb-27 | Not Started 0% | float 154.0d WO030V1100 — 030 Paint | 13-Jan-27 → 23-Aug-27 | Not Started 0% | float 153.0d WO030V1100 CO03CV1110 — 03C Paint Fabricated Pipe Spools | 13-Feb-27 → 24-Feb-27 | Not Started 0% | float 191.0d CO03EV1110 — 03E Paint Fabricated Pipe Spools | 19-Feb-27 → 09-Mar-27 | Not Started 0% | float 171.0d CO03FV1110 — 03F Paint Fabricated Pipe Spools | 19-Feb-27 → 02-Mar-27 | Not Started 0% | float 183.0d CO03AV1110 — 03A Paint Fabricated Pipe Spools | 27-Feb-27 → 10-Mar-27 | Not Started 0% | float 148.0d CO03DV1110 — 03D Paint Fabricated Pipe Spools | 06-Mar-27 → 11-Mar-27 | Not Started 0% | float 172.0d CO03FV1130 — 03F Paint Touch-up - Equipment | 17-Mar-27 → 27-Mar-27 | Not Started 0% | float 183.0d CO03CV1130 — 03C Paint Touch-up - Equipment | 24-Mar-27 → 05-Apr-27 | Not Started 0% | float 195.0d CO03BV1110 — 03B Paint Fabricated Pipe Spools | 05-Apr-27 → 15-Apr-27 | Not Started 0% | float 223.0d CO03DV1130 — 03D Paint Touch-up - Equipment (& 2002-F Tank) | 06-Apr-27 → 12-Apr-27 | Not Started 0% | float 189.0d CO03BV1130 — 03B Paint Touch-up - Equipment | 19-Apr-27 → 29-Apr-27 | Not Started 0% | float 248.0d CO03YV1120 — 03Y Paint Touch-up - Piping | 29-May-27 → 23-Jul-27 | Not Started 0% | float 175.0d CO03YV1120 CO03FV1120 — 03F Paint Touch-up - Piping | 06-Jul-27 → 16-Jul-27 | Not Started 0% | float 112.0d CO03DV1120 — 03D Paint Touch-up - Piping | 06-Jul-27 → 12-Jul-27 | Not Started 0% | float 111.0d CO03AV1120 — 03A Paint Touch-up - Piping | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 58.0d CO03AV1130 — 03A Paint Touch-up - Equipment | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 58.0d CO03CV1120 — 03C Paint Touch-up - Piping | 10-Jul-27 → 21-Jul-27 | Not Started 0% | float 102.0d CO03EV1120 — 03E Paint Touch-up - Piping | 27-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03EV1130 — 03E Paint Touch-up - Equipment | 27-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03BV1120 — 03B Paint Touch-up - Piping | 07-Aug-27 → 23-Aug-27 | Not Started 0% | float 153.0d