EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 21
activities
in V1 Painting
× clear
Code
Activity
Start
Finish
Flt
%
CO03YV1110
03Y Paint Fabricated Pipe Spools
13-Jan-27
13-Feb-27
154.0d
0%
WO030V1100
030 Paint
13-Jan-27
23-Aug-27
153.0d
0%
CO03CV1110
03C Paint Fabricated Pipe Spools
13-Feb-27
24-Feb-27
191.0d
0%
CO03EV1110
03E Paint Fabricated Pipe Spools
19-Feb-27
09-Mar-27
171.0d
0%
CO03FV1110
03F Paint Fabricated Pipe Spools
19-Feb-27
02-Mar-27
183.0d
0%
CO03AV1110
03A Paint Fabricated Pipe Spools
27-Feb-27
10-Mar-27
148.0d
0%
CO03DV1110
03D Paint Fabricated Pipe Spools
06-Mar-27
11-Mar-27
172.0d
0%
CO03FV1130
03F Paint Touch-up - Equipment
17-Mar-27
27-Mar-27
183.0d
0%
CO03CV1130
03C Paint Touch-up - Equipment
24-Mar-27
05-Apr-27
195.0d
0%
CO03BV1110
03B Paint Fabricated Pipe Spools
05-Apr-27
15-Apr-27
223.0d
0%
CO03DV1130
03D Paint Touch-up - Equipment (& 2002-F Tank)
06-Apr-27
12-Apr-27
189.0d
0%
CO03BV1130
03B Paint Touch-up - Equipment
19-Apr-27
29-Apr-27
248.0d
0%
CO03YV1120
03Y Paint Touch-up - Piping
29-May-27
23-Jul-27
175.0d
0%
CO03FV1120
03F Paint Touch-up - Piping
06-Jul-27
16-Jul-27
112.0d
0%
CO03DV1120
03D Paint Touch-up - Piping
06-Jul-27
12-Jul-27
111.0d
0%
CO03AV1120
03A Paint Touch-up - Piping
10-Jul-27
21-Jul-27
58.0d
0%
CO03AV1130
03A Paint Touch-up - Equipment
10-Jul-27
21-Jul-27
58.0d
0%
CO03CV1120
03C Paint Touch-up - Piping
10-Jul-27
21-Jul-27
102.0d
0%
CO03EV1120
03E Paint Touch-up - Piping
27-Jul-27
13-Aug-27
58.0d
0%
CO03EV1130
03E Paint Touch-up - Equipment
27-Jul-27
13-Aug-27
58.0d
0%
CO03BV1120
03B Paint Touch-up - Piping
07-Aug-27
23-Aug-27
153.0d
0%