Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in U4 U/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO03DU4120
03D U/G Piping Installation
28-Dec-26
05-Jan-27
199.0d
0%
WO030U4100
030 U/G Piping Installation
28-Dec-26
26-Feb-27
229.0d
0%
CO03UP0150
03U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO03AU4120
03A U/G Piping Installation
30-Jan-27
18-Feb-27
135.0d
0%
CO03BU4120
03B U/G Piping Installation
30-Jan-27
17-Feb-27
237.0d
0%
CO03CU4120
03C U/G Piping Installation
30-Jan-27
18-Feb-27
166.0d
0%
CO03EU4120
03E U/G Piping Installation
30-Jan-27
26-Feb-27
121.0d
0%
CO03FU4120
03F U/G Piping Installation
30-Jan-27
18-Feb-27
155.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb Data Date
CO03DU4120 — 03D U/G Piping Installation | 28-Dec-26 → 05-Jan-27 | Not Started 0% | float 199.0d CO03DU4120 WO030U4100 — 030 U/G Piping Installation | 28-Dec-26 → 26-Feb-27 | Not Started 0% | float 229.0d WO030U4100 CO03UP0150 — 03U LB Pipe Erection (Firewater Piping) | 16-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO03UP0150 CO03AU4120 — 03A U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 135.0d CO03AU4120 CO03BU4120 — 03B U/G Piping Installation | 30-Jan-27 → 17-Feb-27 | Not Started 0% | float 237.0d CO03BU4120 CO03CU4120 — 03C U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 166.0d CO03CU4120 CO03EU4120 — 03E U/G Piping Installation | 30-Jan-27 → 26-Feb-27 | Not Started 0% | float 121.0d CO03EU4120 CO03FU4120 — 03F U/G Piping Installation | 30-Jan-27 → 18-Feb-27 | Not Started 0% | float 155.0d CO03FU4120