Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U3 U/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO03DU3110
03D U/G Earthing Installation
15-Jan-27
19-Jan-27
199.0d
0%
WO030U3100
030 Install U/G Electrical
15-Jan-27
12-Mar-27
229.0d
0%
CO03BU3110
03B U/G Earthing Installation
23-Feb-27
03-Mar-27
237.0d
0%
CO03CU3110
03C U/G Earthing Installation
24-Feb-27
04-Mar-27
166.0d
0%
CO03FU3110
03F U/G Earthing Installation
24-Feb-27
04-Mar-27
161.0d
0%
CO03AU3110
03A U/G Earthing Installation
26-Feb-27
04-Mar-27
135.0d
0%
CO03EU3110
03E U/G Earthing Installation
27-Feb-27
12-Mar-27
127.0d
0%
Jan 2027 Feb 2027 Mar 2027 Data Date
CO03DU3110 — 03D U/G Earthing Installation | 15-Jan-27 → 19-Jan-27 | Not Started 0% | float 199.0d CO03DU3110 WO030U3100 — 030 Install U/G Electrical | 15-Jan-27 → 12-Mar-27 | Not Started 0% | float 229.0d WO030U3100 CO03BU3110 — 03B U/G Earthing Installation | 23-Feb-27 → 03-Mar-27 | Not Started 0% | float 237.0d CO03BU3110 CO03CU3110 — 03C U/G Earthing Installation | 24-Feb-27 → 04-Mar-27 | Not Started 0% | float 166.0d CO03CU3110 CO03FU3110 — 03F U/G Earthing Installation | 24-Feb-27 → 04-Mar-27 | Not Started 0% | float 161.0d CO03FU3110 CO03AU3110 — 03A U/G Earthing Installation | 26-Feb-27 → 04-Mar-27 | Not Started 0% | float 135.0d CO03AU3110 CO03EU3110 — 03E U/G Earthing Installation | 27-Feb-27 → 12-Mar-27 | Not Started 0% | float 127.0d CO03EU3110