EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in U3 U/G Electrical
× clear
Code
Activity
Start
Finish
Flt
%
CO03DU3110
03D U/G Earthing Installation
15-Jan-27
19-Jan-27
199.0d
0%
WO030U3100
030 Install U/G Electrical
15-Jan-27
12-Mar-27
229.0d
0%
CO03BU3110
03B U/G Earthing Installation
23-Feb-27
03-Mar-27
237.0d
0%
CO03CU3110
03C U/G Earthing Installation
24-Feb-27
04-Mar-27
166.0d
0%
CO03FU3110
03F U/G Earthing Installation
24-Feb-27
04-Mar-27
161.0d
0%
CO03AU3110
03A U/G Earthing Installation
26-Feb-27
04-Mar-27
135.0d
0%
CO03EU3110
03E U/G Earthing Installation
27-Feb-27
12-Mar-27
127.0d
0%