EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 16
activities
in T0 Mechanical Completion
× clear
Code
Activity
Start
Finish
Flt
%
CO03UDT110
03U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
SC03UT0120
03U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CO03AT0110
03A Mechanical Completion
09-Dec-27
09-Dec-27
-26.0d
0%
CO03FT0110
03F Mechanical Completion
13-Dec-27
13-Dec-27
8.0d
0%
SC03AT0120
03A RFSU
20-Dec-27
20-Dec-27
-47.0d
0%
CO03BT0110
03B Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
SC03FT0120
03F RFSU
24-Dec-27
24-Dec-27
-2.0d
0%
CO03CT0110
03C Mechanical Completion
27-Dec-27
27-Dec-27
-10.0d
0%
CO03DT0110
03D Mechanical Completion
29-Dec-27
29-Dec-27
-12.0d
0%
SC03BT0120
03B RFSU
03-Jan-28
03-Jan-28
69.0d
0%
CO03ET0110
03E Mechanical Completion
04-Jan-28
04-Jan-28
-17.0d
0%
SC03DT0120
03D RFSU
04-Jan-28
04-Jan-28
-20.0d
0%
SC03CT0120
03C RFSU
07-Jan-28
07-Jan-28
-23.0d
0%
CO03YT0110
03Y Mechanical Completion
17-Jan-28
17-Jan-28
47.0d
0%
SC03ET0120
03E RFSU
22-Jan-28
22-Jan-28
-38.0d
0%
SC03YT0120
03Y RFSU
24-Jan-28
24-Jan-28
48.0d
0%