EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in S0 Structural / Misc. Steel × clear
Code
Activity
Start
Finish
Flt
%
CO03YS0110
03Y Erect Structural Steel
06-Mar-27
26-Mar-27
39.0d
0%
WO030S0100
030 Erect Steel
06-Mar-27
25-Jun-27
157.0d
0%
CO03BS0120
03B Erect Misc Steel - Structure
15-May-27
11-Jun-27
169.0d
0%
CO03FS0120
03F Erect Misc Steel
15-May-27
25-Jun-27
88.0d
0%
CO03AS0120
03A Erect Misc Steel - Structure
22-May-27
18-Jun-27
56.0d
0%
CO03CS0120
03C Erect Misc Steel
22-May-27
11-Jun-27
87.0d
0%
CO03DS0120
03D Erect Misc Steel
22-May-27
18-Jun-27
98.0d
0%
CO03ES0120
03E Erect Misc Steel - Structure
22-May-27
18-Jun-27
58.0d
0%
Mar 2027 Apr 2027 May 2027 Jun 2027 Data Date
CO03YS0110 — 03Y Erect Structural Steel | 06-Mar-27 → 26-Mar-27 | Not Started 0% | float 39.0d CO03YS0110 WO030S0100 — 030 Erect Steel | 06-Mar-27 → 25-Jun-27 | Not Started 0% | float 157.0d WO030S0100 CO03BS0120 — 03B Erect Misc Steel - Structure | 15-May-27 → 11-Jun-27 | Not Started 0% | float 169.0d CO03BS0120 CO03FS0120 — 03F Erect Misc Steel | 15-May-27 → 25-Jun-27 | Not Started 0% | float 88.0d CO03FS0120 CO03AS0120 — 03A Erect Misc Steel - Structure | 22-May-27 → 18-Jun-27 | Not Started 0% | float 56.0d CO03AS0120 CO03CS0120 — 03C Erect Misc Steel | 22-May-27 → 11-Jun-27 | Not Started 0% | float 87.0d CO03CS0120 CO03DS0120 — 03D Erect Misc Steel | 22-May-27 → 18-Jun-27 | Not Started 0% | float 98.0d CO03DS0120 CO03ES0120 — 03E Erect Misc Steel - Structure | 22-May-27 → 18-Jun-27 | Not Started 0% | float 58.0d CO03ES0120