Legend: Not Started In Progress Complete Critical Milestone Showing 22 activities in P0 A/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO03YP0130
03Y LB Pipe Erection
27-Mar-27
09-Jul-27
39.0d
0%
WO030P0100
030 Above Ground Pipe
27-Mar-27
23-Aug-27
138.0d
0%
CO03YP0140
03Y SB Pipe Erection
03-Apr-27
16-Jul-27
45.0d
0%
CO03FP0130
03F LB Pipe Erection
25-May-27
02-Jul-27
88.0d
0%
CO03AP0130
03A LB Pipe Erection
29-May-27
07-Jul-27
56.0d
0%
CO03CP0130
03C LB Pipe Erection
29-May-27
07-Jul-27
87.0d
0%
CO03EP0130
03E LB Pipe Erection
29-May-27
30-Jul-27
58.0d
0%
CO03FP0140
03F SB Pipe Erection
01-Jun-27
09-Jul-27
88.0d
0%
CO03YP0150
03Y Punchlist / Test Piping
02-Jun-27
23-Jul-27
139.0d
0%
CO03AP0140
03A SB Pipe Erection
05-Jun-27
14-Jul-27
56.0d
0%
CO03CP0140
03C SB Pipe Erection
05-Jun-27
14-Jul-27
87.0d
0%
CO03EP0140
03E SB Pipe Erection
05-Jun-27
06-Aug-27
58.0d
0%
CO03DP0130
03D LB Pipe Erection
07-Jun-27
25-Jun-27
98.0d
0%
CO03DP0140
03D SB Pipe Erection
15-Jun-27
05-Jul-27
97.0d
0%
CO03BP0130
03B LB Pipe Erection
28-Jun-27
04-Aug-27
138.0d
0%
CO03FP0150
03F Punchlist / Test Piping
28-Jun-27
16-Jul-27
88.0d
0%
CO03AP0150
03A Punchlist / Test Piping
02-Jul-27
21-Jul-27
62.0d
0%
CO03CP0150
03C Punchlist / Test Piping
02-Jul-27
21-Jul-27
87.0d
0%
CO03DP0150
03D Punchlist / Test Piping
02-Jul-27
12-Jul-27
97.0d
0%
CO03BP0140
03B SB Pipe Erection
05-Jul-27
11-Aug-27
138.0d
0%
CO03EP0150
03E Punchlist / Test Piping
14-Jul-27
13-Aug-27
58.0d
0%
CO03BP0150
03B Punchlist / Test Piping
31-Jul-27
23-Aug-27
138.0d
0%
01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug Data Date
CO03YP0130 — 03Y LB Pipe Erection | 27-Mar-27 → 09-Jul-27 | Not Started 0% | float 39.0d CO03YP0130 WO030P0100 — 030 Above Ground Pipe | 27-Mar-27 → 23-Aug-27 | Not Started 0% | float 138.0d WO030P0100 CO03YP0140 — 03Y SB Pipe Erection | 03-Apr-27 → 16-Jul-27 | Not Started 0% | float 45.0d CO03YP0140 CO03FP0130 — 03F LB Pipe Erection | 25-May-27 → 02-Jul-27 | Not Started 0% | float 88.0d CO03FP0130 CO03AP0130 — 03A LB Pipe Erection | 29-May-27 → 07-Jul-27 | Not Started 0% | float 56.0d CO03AP0130 CO03CP0130 — 03C LB Pipe Erection | 29-May-27 → 07-Jul-27 | Not Started 0% | float 87.0d CO03CP0130 CO03EP0130 — 03E LB Pipe Erection | 29-May-27 → 30-Jul-27 | Not Started 0% | float 58.0d CO03EP0130 CO03FP0140 — 03F SB Pipe Erection | 01-Jun-27 → 09-Jul-27 | Not Started 0% | float 88.0d CO03FP0140 CO03YP0150 — 03Y Punchlist / Test Piping | 02-Jun-27 → 23-Jul-27 | Not Started 0% | float 139.0d CO03YP0150 CO03AP0140 — 03A SB Pipe Erection | 05-Jun-27 → 14-Jul-27 | Not Started 0% | float 56.0d CO03AP0140 CO03CP0140 — 03C SB Pipe Erection | 05-Jun-27 → 14-Jul-27 | Not Started 0% | float 87.0d CO03CP0140 CO03EP0140 — 03E SB Pipe Erection | 05-Jun-27 → 06-Aug-27 | Not Started 0% | float 58.0d CO03EP0140 CO03DP0130 — 03D LB Pipe Erection | 07-Jun-27 → 25-Jun-27 | Not Started 0% | float 98.0d CO03DP0130 CO03DP0140 — 03D SB Pipe Erection | 15-Jun-27 → 05-Jul-27 | Not Started 0% | float 97.0d CO03DP0140 CO03BP0130 — 03B LB Pipe Erection | 28-Jun-27 → 04-Aug-27 | Not Started 0% | float 138.0d CO03BP0130 CO03FP0150 — 03F Punchlist / Test Piping | 28-Jun-27 → 16-Jul-27 | Not Started 0% | float 88.0d CO03FP0150 CO03AP0150 — 03A Punchlist / Test Piping | 02-Jul-27 → 21-Jul-27 | Not Started 0% | float 62.0d CO03AP0150 CO03CP0150 — 03C Punchlist / Test Piping | 02-Jul-27 → 21-Jul-27 | Not Started 0% | float 87.0d CO03CP0150 CO03DP0150 — 03D Punchlist / Test Piping | 02-Jul-27 → 12-Jul-27 | Not Started 0% | float 97.0d CO03DP0150 CO03BP0140 — 03B SB Pipe Erection | 05-Jul-27 → 11-Aug-27 | Not Started 0% | float 138.0d CO03BP0140 CO03EP0150 — 03E Punchlist / Test Piping | 14-Jul-27 → 13-Aug-27 | Not Started 0% | float 58.0d CO03EP0150 CO03BP0150 — 03B Punchlist / Test Piping | 31-Jul-27 → 23-Aug-27 | Not Started 0% | float 138.0d CO03BP0150