Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in P0 A/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar Data Date
CO05BP0130 — 05B LB Pipe Erection - To Loading Arm | 31-Jul-27 → 21-Sep-27 | Not Started 0% | float 152.0d CO05BP0130 WO050P0100 — 050 Above Ground Pipe | 31-Jul-27 → 14-Mar-28 | Not Started 0% | float 19.0d WO050P0100 CO05BP0140 — 05B SB Pipe Erection - To Loading Arm | 07-Aug-27 → 28-Sep-27 | Not Started 0% | float 152.0d CO05BP0140 CO05AP0130 — 05A LB Pipe Erection | 04-Nov-27 → 29-Feb-28 | Not Started 0% | float -29.0d CO05AP0130 CO05AP0140 — 05A SB Pipe Erection | 11-Nov-27 → 07-Mar-28 | Not Started 0% | float -29.0d CO05AP0140 CO05BP0150 — 05B Punchlist / Test Piping | 08-Jan-28 → 24-Jan-28 | Not Started 0% | float 63.0d CO05BP0150 CO05AP0150 — 05A Punchlist / Test Piping | 19-Jan-28 → 14-Mar-28 | Not Started 0% | float -29.0d CO05AP0150