Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in P0 A/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
Q3 2027 Q4 2027 Q1 2028 Data Date
CO05BP0130 — 05B LB Pipe Erection - To Loading Arm | 31-Jul-27 → 21-Sep-27 | Not Started 0% | float 152.0d CO05BP0130 WO050P0100 — 050 Above Ground Pipe | 31-Jul-27 → 14-Mar-28 | Not Started 0% | float 19.0d WO050P0100 CO05BP0140 — 05B SB Pipe Erection - To Loading Arm | 07-Aug-27 → 28-Sep-27 | Not Started 0% | float 152.0d CO05BP0140 CO05AP0130 — 05A LB Pipe Erection | 04-Nov-27 → 29-Feb-28 | Not Started 0% | float -29.0d CO05AP0130 CO05AP0140 — 05A SB Pipe Erection | 11-Nov-27 → 07-Mar-28 | Not Started 0% | float -29.0d CO05AP0140 CO05BP0150 — 05B Punchlist / Test Piping | 08-Jan-28 → 24-Jan-28 | Not Started 0% | float 63.0d CO05AP0150 — 05A Punchlist / Test Piping | 19-Jan-28 → 14-Mar-28 | Not Started 0% | float -29.0d CO05AP0150