Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in M0 Mechanical Equipment × clear
Code
Activity
Start
Finish
Flt
%
CO05BM0110
05B Install Loading Arm
02-Aug-27
04-Dec-27
62.0d
0%
WO050M0100
050 Major Equipment
02-Aug-27
04-Dec-27
61.0d
0%
CO05AM0110
05A Set 2202-B Flare & KO Drum
28-Oct-27
04-Dec-27
21.0d
0%
CO05AM0130
05A Set 2101-L Ammonia Refrigeration Package
28-Oct-27
30-Oct-27
46.0d
0%
CO05AM0150
05A Set Rotating Equipment
28-Oct-27
17-Nov-27
31.0d
0%
Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Data Date
CO05BM0110 — 05B Install Loading Arm | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 62.0d CO05BM0110 WO050M0100 — 050 Major Equipment | 02-Aug-27 → 04-Dec-27 | Not Started 0% | float 61.0d WO050M0100 CO05AM0110 — 05A Set 2202-B Flare & KO Drum | 28-Oct-27 → 04-Dec-27 | Not Started 0% | float 21.0d CO05AM0110 CO05AM0130 — 05A Set 2101-L Ammonia Refrigeration Package | 28-Oct-27 → 30-Oct-27 | Not Started 0% | float 46.0d CO05AM0150 — 05A Set Rotating Equipment | 28-Oct-27 → 17-Nov-27 | Not Started 0% | float 31.0d CO05AM0150