EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 3
activities
in K0 Site Prep
× clear
Code
Activity
Start
Finish
Flt
%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%