Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in K0 Site Prep × clear
Code
Activity
Start
Finish
Flt
%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
Feb 2028 Mar 2028 Apr 2028 May 2028 Data Date
CO05AK0120 — 05A Construct Dike (Retaining Wall) | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0120 CO05AK0130 — 05A Guard Posts, Fence, Gravel... | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0130 WO050K0100 — 050 Site Prep | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d WO050K0100