Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in K0 Site Prep × clear
Code
Activity
Start
Finish
Flt
%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 29-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May Data Date
CO05AK0120 — 05A Construct Dike (Retaining Wall) | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0120 CO05AK0130 — 05A Guard Posts, Fence, Gravel... | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d CO05AK0130 WO050K0100 — 050 Site Prep | 26-Feb-28 → 05-May-28 | Not Started 0% | float -47.0d WO050K0100