EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in I0 Instrumentation × clear
Code
Activity
Start
Finish
Flt
%
CO05BI0120
05B Instrument JB's, Field Instr, Tray, Cable
19-Oct-27
30-Oct-27
140.0d
0%
WO050I0100
050 Install Instruments & Test
19-Oct-27
25-Mar-28
24.0d
0%
CO05AI0120
05A Instrument JB's, Field Instr, Tray, Cable
18-Nov-27
14-Mar-28
-25.0d
0%
CO05BI0140
05B Continuity Testing
07-Dec-27
07-Dec-27
118.0d
0%
CO05BI0130
05B Install In Line Instruments
24-Jan-28
25-Jan-28
68.0d
0%
CO05AI0140
05A Continuity Testing
10-Mar-28
21-Mar-28
-25.0d
0%
CO05AI0130
05A Install In Line Instruments
15-Mar-28
25-Mar-28
-29.0d
0%
Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Data Date
CO05BI0120 — 05B Instrument JB's, Field Instr, Tray, Cable | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BI0120 WO050I0100 — 050 Install Instruments & Test | 19-Oct-27 → 25-Mar-28 | Not Started 0% | float 24.0d WO050I0100 CO05AI0120 — 05A Instrument JB's, Field Instr, Tray, Cable | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AI0120 CO05BI0140 — 05B Continuity Testing | 07-Dec-27 → 07-Dec-27 | Not Started 0% | float 118.0d CO05BI0130 — 05B Install In Line Instruments | 24-Jan-28 → 25-Jan-28 | Not Started 0% | float 68.0d CO05AI0140 — 05A Continuity Testing | 10-Mar-28 → 21-Mar-28 | Not Started 0% | float -25.0d CO05AI0140 CO05AI0130 — 05A Install In Line Instruments | 15-Mar-28 → 25-Mar-28 | Not Started 0% | float -29.0d CO05AI0130