EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in E0 A/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Apr 2028 Data Date
CO05BE0130 — 05B Power/Control JB's, Tray, Cable, Termination | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BE0130 WO050E0100 — 050 Above Ground Electrical | 19-Oct-27 → 06-Apr-28 | Not Started 0% | float 8.0d WO050E0100 CO05AE0130 — 05A Power/Control JB's, Tray, Cable, Termination | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AE0130 CO05AE0110 — 05A Lighting JB's, Stands, Tray & Cable | 03-Mar-28 → 30-Mar-28 | Not Started 0% | float -22.0d CO05AE0110 CO05AE0120 — 05A Lighting Fixture Installation/Termination | 24-Mar-28 → 06-Apr-28 | Not Started 0% | float -22.0d CO05AE0120