Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in E0 A/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 29-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr Data Date
CO05BE0130 — 05B Power/Control JB's, Tray, Cable, Termination | 19-Oct-27 → 30-Oct-27 | Not Started 0% | float 140.0d CO05BE0130 WO050E0100 — 050 Above Ground Electrical | 19-Oct-27 → 06-Apr-28 | Not Started 0% | float 8.0d WO050E0100 CO05AE0130 — 05A Power/Control JB's, Tray, Cable, Termination | 18-Nov-27 → 14-Mar-28 | Not Started 0% | float -25.0d CO05AE0130 CO05AE0110 — 05A Lighting JB's, Stands, Tray & Cable | 03-Mar-28 → 30-Mar-28 | Not Started 0% | float -22.0d CO05AE0110 CO05AE0120 — 05A Lighting Fixture Installation/Termination | 24-Mar-28 → 06-Apr-28 | Not Started 0% | float -22.0d CO05AE0120