EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 8
activities
in C0 Concrete / Piling
× clear
Code
Activity
Start
Finish
Flt
%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%