EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in C0 Concrete / Piling × clear
Code
Activity
Start
Finish
Flt
%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%
01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul Data Date
CO05AC0150 — 05A Install Piling - 2101-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -51.0d CO05AC0150 CO05AC0155 — 05A Install Piling - 2102-F Ammonia Tank | 01-Feb-27 → 19-Apr-27 | Not Started 0% | float -40.0d CO05AC0155 WO050C0100 — 050 Concrete & Excavation | 01-Feb-27 → 30-Jul-27 | Not Started 0% | float 152.0d WO050C0100 CO05AC0160 — 05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -51.0d CO05AC0160 CO05AC0165 — 05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank | 20-Apr-27 → 16-Jun-27 | Not Started 0% | float -40.0d CO05AC0165 CO05AC0120 — 05A Form, Pour, Strip Fnds - Sleeper & Rack | 11-May-27 → 14-Jun-27 | Not Started 0% | float 44.0d CO05AC0120 CO05BC0110 — 05B Form, Pour, Strip Fnds - Sleepers | 15-Jun-27 → 30-Jul-27 | Not Started 0% | float 152.0d CO05BC0110 CO05AC0110 — 05A Form, Pour, Strip Fnds - Major Fnds Gen'l | 17-Jun-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AC0110