Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in A0 Buildings × clear
Code
Activity
Start
Finish
Flt
%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
Q3 2027 Q4 2027 Data Date
CO05BA0110 — 05B Erect Dock Control Operating Building | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d WO050A0100 — 050 Buildings | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d