EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in A0 Buildings × clear
Code
Activity
Start
Finish
Flt
%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct Data Date
CO05BA0110 — 05B Erect Dock Control Operating Building | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d CO05BA0110 WO050A0100 — 050 Buildings | 21-Sep-27 → 19-Oct-27 | Not Started 0% | float 135.0d WO050A0100