Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in V1 Painting × clear
Code
Activity
Start
Finish
Flt
%
CO05AV1110
05A Paint Fabricated Pipe Spools
05-May-27
07-Jun-27
166.0d
0%
WO050V1100
050 Paint
05-May-27
12-Apr-28
12.0d
0%
CO05BV1110
05B Paint Fabricated Pipe Spools
29-May-27
07-Jun-27
214.0d
0%
CO05BV1120
05B Paint Touch-up - Piping
27-Sep-27
05-Oct-27
170.0d
0%
CO05BV1130
05B Paint Touch-up - Equipment
08-Jan-28
18-Jan-28
62.0d
0%
CO05AV1120
05A Paint Touch-up - Piping
10-Feb-28
14-Mar-28
-2.0d
0%
CO05AV1130
05A Paint Touch-up - Equipment
10-Mar-28
12-Apr-28
-51.0d
0%
26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar 03-Apr 10-Apr 17-Apr 24-Apr Data Date
CO05AV1110 — 05A Paint Fabricated Pipe Spools | 05-May-27 → 07-Jun-27 | Not Started 0% | float 166.0d CO05AV1110 WO050V1100 — 050 Paint | 05-May-27 → 12-Apr-28 | Not Started 0% | float 12.0d WO050V1100 CO05BV1110 — 05B Paint Fabricated Pipe Spools | 29-May-27 → 07-Jun-27 | Not Started 0% | float 214.0d CO05BV1110 CO05BV1120 — 05B Paint Touch-up - Piping | 27-Sep-27 → 05-Oct-27 | Not Started 0% | float 170.0d CO05BV1120 CO05BV1130 — 05B Paint Touch-up - Equipment | 08-Jan-28 → 18-Jan-28 | Not Started 0% | float 62.0d CO05BV1130 CO05AV1120 — 05A Paint Touch-up - Piping | 10-Feb-28 → 14-Mar-28 | Not Started 0% | float -2.0d CO05AV1120 CO05AV1130 — 05A Paint Touch-up - Equipment | 10-Mar-28 → 12-Apr-28 | Not Started 0% | float -51.0d CO05AV1130