EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in U4 U/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO05AU4120
05A U/G Piping Installation
13-May-27
07-Jul-27
77.0d
0%
WO050U4100
050 U/G Piping Installation
13-May-27
30-Sep-27
135.0d
0%
CO05UP0150
05U LB Pipe Erection (Firewater Piping)
17-Jun-27
30-Sep-27
135.0d
0%
26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep Data Date
CO05AU4120 — 05A U/G Piping Installation | 13-May-27 → 07-Jul-27 | Not Started 0% | float 77.0d CO05AU4120 WO050U4100 — 050 U/G Piping Installation | 13-May-27 → 30-Sep-27 | Not Started 0% | float 135.0d WO050U4100 CO05UP0150 — 05U LB Pipe Erection (Firewater Piping) | 17-Jun-27 → 30-Sep-27 | Not Started 0% | float 135.0d CO05UP0150