Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in U3 U/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO05AU3110
05A U/G Earthing Installation
17-Jun-27
14-Jul-27
77.0d
0%
WO050U3100
050 Install U/G Electrical
17-Jun-27
14-Jul-27
77.0d
0%
31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul Data Date
CO05AU3110 — 05A U/G Earthing Installation | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d CO05AU3110 WO050U3100 — 050 Install U/G Electrical | 17-Jun-27 → 14-Jul-27 | Not Started 0% | float 77.0d WO050U3100