Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in T0 Mechanical Completion × clear
Code
Activity
Start
Finish
Flt
%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%
27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar 03-Apr 10-Apr 17-Apr 24-Apr 01-May 08-May 15-May 22-May 29-May Data Date
CO05BT0110 — 05B Mechanical Completion | 24-Jan-28 | Not Started SC05BT0120 — 05B RFSU | 15-Feb-28 | Not Started CO05AT0110 — 05A Mechanical Completion | 05-May-28 | Not Started SC05AT0120 — 05A RFSU | 10-May-28 | Not Started