EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 4
activities
in T0 Mechanical Completion
× clear
Code
Activity
Start
Finish
Flt
%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%