Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in S0 Structural / Misc. Steel × clear
Code
Activity
Start
Finish
Flt
%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
Q3 2027 Data Date
CO05AS0110 — 05A Erect Structural Steel - Structure | 09-Jul-27 → 21-Jul-27 | Not Started 0% | float 23.0d WO050S0100 — 050 Erect Steel | 09-Jul-27 → 13-Aug-27 | Not Started 0% | float 23.0d CO05AS0120 — 05A Erect Misc Steel | 06-Aug-27 → 13-Aug-27 | Not Started 0% | float 23.0d