EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in S0 Structural / Misc. Steel × clear
Code
Activity
Start
Finish
Flt
%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug Data Date
CO05AS0110 — 05A Erect Structural Steel - Structure | 09-Jul-27 → 21-Jul-27 | Not Started 0% | float 23.0d CO05AS0110 WO050S0100 — 050 Erect Steel | 09-Jul-27 → 13-Aug-27 | Not Started 0% | float 23.0d WO050S0100 CO05AS0120 — 05A Erect Misc Steel | 06-Aug-27 → 13-Aug-27 | Not Started 0% | float 23.0d CO05AS0120