EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 4 activities in M0 Mechanical Equipment × clear
Code
Activity
Start
Finish
Flt
%
CO05AM0145
05A Tank Erection 2101-F (Ammonia Storage Tank)
01-Jul-27
25-Feb-28
-51.0d
0%
WT050M0100
05A Tank Erection
01-Jul-27
09-Mar-28
-51.0d
0%
CO05AM0155
05A Tank Erection 2102-F (Ammonia Storage Tank)
14-Jul-27
09-Mar-28
-51.0d
0%
CO05AM0160
05A Tank Erection 2105-F (Fire Water Tank)
23-Aug-27
16-Oct-27
-29.0d
0%
28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar Data Date
CO05AM0145 — 05A Tank Erection 2101-F (Ammonia Storage Tank) | 01-Jul-27 → 25-Feb-28 | Not Started 0% | float -51.0d CO05AM0145 WT050M0100 — 05A Tank Erection | 01-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d WT050M0100 CO05AM0155 — 05A Tank Erection 2102-F (Ammonia Storage Tank) | 14-Jul-27 → 09-Mar-28 | Not Started 0% | float -51.0d CO05AM0155 CO05AM0160 — 05A Tank Erection 2105-F (Fire Water Tank) | 23-Aug-27 → 16-Oct-27 | Not Started 0% | float -29.0d CO05AM0160